Doehler Metal Furniture Co. v. United States

149 F.2d 130, 1945 U.S. App. LEXIS 3421
CourtCourt of Appeals for the Second Circuit
DecidedApril 26, 1945
Docket287
StatusPublished
Cited by230 cases

This text of 149 F.2d 130 (Doehler Metal Furniture Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doehler Metal Furniture Co. v. United States, 149 F.2d 130, 1945 U.S. App. LEXIS 3421 (2d Cir. 1945).

Opinions

FRANK, Circuit Judge.

1. Since Doehler was in default as to delivery of all the furniture covered by the contract, the government had the privilege, conferred by the reletting provision, to refuse to accept delivery in toto and to let a new contract for the 6,321 pieces, holding Doehler for the “excess cost.” Doehler contends that the government could not exercise that privilege as to reletting with respect to part of the furniture, while calling on Doehler to deliver the balance, and that therefore Doehler cannot be held liable pursuant to the reletting provision. In effect, the argument is that, by its conduct, the government abandoned its rights under that provision. That contention is untenable. The government’s voluntary relinquishment of a portion of its privilege was not an abandonment of the rest of it. Although we do not so decide, we may assume, arguendo, that Doehler might properly have refused to deliver the 677 pieces; but even if it were true that, in that respect, the government sought to [133]*133deviate from the terms of the contract conferring the privilege, that fact would not invalidate the exercise of that privilege as to the 5,644 pieces.

We may arrive at the same conclusion by another route: If we assume that the attempted exercise of the privilege, because partial, was invalid, then the notice of April 17-18 was an offer to Doehler by the government to exercise that privilege in part and to receive delivery from Doehler of the 677 pieces; assuming further that Doehler could properly have refused that offer and that, had it done so, the government, by reletting a contract for only 5,644 pieces, would have lost its rights under the reletting provision, the fact is that Doehler did not refuse but, on May 31, some six weeks after the notice, delivered the 677 pieces; accordingly, whatever Doehler’s legal position might otherwise have been, it is surely now in no position to object to the enforcement of the reletting provision as to the 5,644 pieces.

2. Doehler contends that the inclusion in the Equipment contract of the liquidated damage clause wiped out Doehler’s liability for “excess cost” under the reletting provision, regardless of whether or not, in fact, that inclusion caused all or part of the increased price under the Equipment contract. For, argues Doehler, the addition of that clause was a material change which “affected the price as a matter of law.” This alleged doctrine (reminiscent, in its rigid formality, of the rule in Shelley’s case) finds no support in the cases; those cited by Doehler related to relet contracts calling for performance of work of a kind substantially different from that which the first contractor had agreed to perform or for the delivery of goods of a substantially different character.2

The addition, however, of the liquidated damage clause may in fact have accounted, to some extent or entirely, for the increased price named in the Equipment contract. Doehler argues that Equipment must have known that the government could never prove any precise amount of damages caused by delay; and that, therefore, Equipment, recognizing that the added clause increased its risk, should it delay in making delivery, must be “conclusively presumed” to have demanded that its contract included a promise of extra compensation for taking that risk. But that argument impliedly rests on the axiom that businessmen invariably recognize the risks they take and always nicely calculate them in dollars and cents. Doubtless at one time many economists, believing it to be self-evidently true that every man is .solely a fanatically rational “economic man,” accepted that axiom as virtually a law of nature; but, as the result of accurate observation of human behavior, that axiom is now generally treated as an assumption to be used most cautiously with full awareness that it is a “neglective fiction.”3 Courts use such (and other) fictions; but [134]*134this particular fiction should surely not be the basis of a “conclusive presumption” or otherwise serve as a substitute for evidence'.

Moreover, we would indulge in the sheerest guessing if we were to say that Equipment must necessarily have regarded the added clause as appreciably augmenting its risk; for the contract, even without that clause, would have subjected Equipment, if it delayed, to the consequences of the relet provision with a possibility of its liability for increased costs, a possibility which, in wartime conditions, might easily have become a strong probability. Besides, as Doehler (somewhat inconsistently) says in its brief, Equipment, when it made its contract, “may have been so sanguine of ability to perform in time as to make any delay damage seem unimportant.”

Whether, then, and to what extent, the added clause affected the price named in the Equipment contract are questions of [135]*135fact which cannot be answered on the basis of the data before us or before the trial judge when he gave summary judgment for the government. There must be a trial on those issues.

With respect to those issues, we think that the burden of proof must be on the government. Had the second contract, except as to price, been the same in terms as the first, the price named in the second contract would be assumed to be reasonable, absent any contrary evidence.4 But such an assumption is unwarranted in the light of the additional clause. We cannot say that there is a strong probability that that clause did not raise the price; nor is it true that the facts are more accessible to Doehler than to the government; nor are there any policy grounds for not letting the burden rest where it ordinarily would rest, i. e., on the government, which, under the counterclaim, is asserting a claim against Doehler.

If, at the trial it should be proved that the added clause explains the entire difference between the prices in the two contracts, then the government’s counterclaim must fail. Should it appear, however, that the added clause increased the price only in part, then the counterclaim will not wholly fail but will merely be reduced by the amount of such partial increase. For the situation here is not like that which exists when the government, in a purported reletting, contracts for work or goods substantially different from that covered by the original contract; in such a case, the government cannot recover under the re-letting provision for the reason that, the two contracts being incommensurable, the price named in the second contract “cannot be used for the measure of recovery for breach of the original contract.”5 The attempted comparison is then like one between pigs and apples. But where the goods to be delivered under the two contracts are precisely the same and the only difference is an added item of obligation which enhances the cost in an ascertainable amount, the comparison, once the cost of that item is deducted from the price in the second contract, is unimpeachable. Consider, for instance, a contract for Idaho potatoes to be delivered at St. Louis followed by a relet contract, at a greater price, which requires delivery at Cleveland, where part of the increase in price can be shown to be due to additional transportation charges.

We take this occasion to suggest that trial judges should exercise great care in granting motions for summary judgment. A litigant has a right to a trial where there is the slightest doubt as to the facts, and a denial of that right is reviewable; but refusal to grant a summary judgment is not reviewable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McDermott v. TENDUN CONSTRUCTORS, ROHR INDUSTRIES, INC.
511 A.2d 690 (New Jersey Superior Court App Division, 1986)
Felicity Fashions, Inc. v. Macy
512 F. Supp. 742 (E.D. New York, 1981)
Lofland v. Meyers
442 F. Supp. 955 (S.D. New York, 1977)
Higbie v. Kopy-Kat, Inc.
391 F. Supp. 808 (E.D. Pennsylvania, 1975)
Xerox Corporation v. Dennison Manufacturing Company
322 F. Supp. 963 (S.D. New York, 1971)
Dolgow v. Anderson
438 F.2d 825 (Second Circuit, 1970)
Elliott v. Elliott
49 F.R.D. 283 (S.D. New York, 1970)
State v. Ashton Company
422 P.2d 727 (Court of Appeals of Arizona, 1967)
Lemelson v. Kellogg Co.
259 F. Supp. 904 (S.D. New York, 1966)
ICE CORPORATION v. Armco Steel Corporation
250 F. Supp. 738 (S.D. New York, 1966)
Mistretta v. S. S. Ocean Evelyn
243 F. Supp. 86 (E.D. New York, 1964)
Carroll v. American Federation of Musicians
35 F.R.D. 535 (S.D. New York, 1964)
Tinsley v. Mavala, Inc.
226 F. Supp. 477 (S.D. New York, 1964)
List v. Fashion Park, Inc.
222 F. Supp. 798 (S.D. New York, 1963)
Ruvolo v. American Casualty Co.
189 A.2d 204 (Supreme Court of New Jersey, 1963)
Drake v. Handman
30 F.R.D. 394 (S.D. New York, 1962)
Peterson v. Valley National Bank of Phoenix
368 P.2d 317 (Arizona Supreme Court, 1962)
Riollano v. District Director of Internal Revenue
197 F. Supp. 318 (S.D. New York, 1961)
Dale Hilton, Inc. v. Triangle Publications, Inc.
27 F.R.D. 468 (S.D. New York, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
149 F.2d 130, 1945 U.S. App. LEXIS 3421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doehler-metal-furniture-co-v-united-states-ca2-1945.