State v. Ashton Company

422 P.2d 727, 4 Ariz. App. 599, 1967 Ariz. App. LEXIS 344
CourtCourt of Appeals of Arizona
DecidedJanuary 27, 1967
Docket2 CA-CIV 152
StatusPublished
Cited by20 cases

This text of 422 P.2d 727 (State v. Ashton Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Ashton Company, 422 P.2d 727, 4 Ariz. App. 599, 1967 Ariz. App. LEXIS 344 (Ark. Ct. App. 1967).

Opinion

HATHAWAY, Chief Judge.

This is an appeal by the State of Arizona (defendant below) from a judgment entered against it in favor of the Ashton Company, Inc. (plaintiff below) in the amount of $57,140.40, together with interest thereon, upon the granting of plaintiffs motion for summary judgment.

The litigation arose out of a contract entered into by the plaintiff and defendant concerning the construction of a highway in Tucson, Arizona. The plans for the construction project, which were incorporated by reference into the contract, detailed in cubic yards the quantities of borrow material which would be needed to construct the highway, i. e., approximately 463,968 cubic yards. The State, however, required that bids be submitted on a price-per-ton basis.

The materials division of the State Highway Department furnished prospective bidders with information concerning sources of materials and pertinent test analyses. These “information sheets” specifically advised that they were made available for information purposes only and were not to-be considered a part of the contract papers, and, further, that the State declined to-accept responsibility for “any conditions encountered which may be at variance from information contained herein.”

The standard specifications for road and bridge construction, which were part of the subject contract, contained a section dealing with material pits which likewise referred to the materials division information :

“ * * * This information will be furnished the contractor as an attachment to the plans and is solely for informational purposes. This information is not to be construed as a guaranty of the area of the pit, nor of the quantity or depth of acceptable material.” (Emphasis supplied)

The contract bidding schedule which set forth the approximate quantities of various items of the construction project indicated that, as to borrow, an approximate quantity of 783,000 tons would be required as to which a unit bid price in dollars and cents and a total bid in dollars and cents was to be submitted.

According to an affidavit supporting the plaintiff’s motion for summary judgment, the bid of forty cents per ton of borrow submitted by the plaintiff and accepted by the State was arrived at by figuring the costs involved in the excavation, hauling, placement and compaction of the cubic yard quantity of borrow as shown in the plans furnished by the State plus a reasonable profit thereon and converting the cubic yard cost plus profit to a per ton basis as required by the bidding schedule. The plaintiff believed that the quantity of cubic yards required by the plans would weigh approximately 783,000 tons as set forth in the bidding schedule and, in reliance upon this information as to tonnage, submitted the forty cents per ton bid. *601 The affidavit further stated that the only method by which the borrow item could be bid was by using the cubic yard quantity •shown by the plans and then converting this to a per ton unit figure based upon the weight given for the total cubic yards required.

The complaint filed by the plaintiff set forth several claims for relief. One claim asserted that the written agreement of the parties did not reflect their actual agreement and reformation of the contract in conformity therewith was sought. The motion for summary judgment was presented on the basis that plaintiff was entitled, as a matter of law, to summary judgment granting reformation of the contract and for judgment upon the contract as reformed.

The 783,000 tons estimated by the State as the approximate quantity of borrow required was calculated on the basis of a 125 pounds per cubic foot density of the material to be removed from the borrow pit. This density figure was the result of one test analysis procured by the State on material extracted from the pit at a particular level. The plaintiff performed no tests prior to submission of its bid as it was not the custom or practice of bidders to so do. The average density of the materials removed from the designated pits and hauled by the plaintiff in performance of the subject contract was 105 pounds per cubic foot.

The contract between the parties in substance provided that the plaintiff would furnish the specified number of cubic yards of compacted borrow material at a price of forty cents per ton. The plaintiff’s position in the superior court, which prevailed on the motion for summary judgment, was that the actual agreement required that the plaintiff would furnish 463,968.64 cubic yards at the unit price of Qy'z cents per cubic yard, or a total consideration of $313,200, and it was to be paid the sum of $319,615.20 (the unit price per cubic yard multiplied by the actual cubic yards furnished), leaving a balance due to plaintiff in the sum of $57,140.40. The $313,200 figure was computed by the plaintiff by multiplying forty cents per ton by the number of tons specified in the bidding schedule as the approximate quantity of borrow, i. e., 783,000 tons. The plaintiff’s computation of the balance due’ was as follows:

1. The bidding proposal shows forty cents per ton on an estimated tonnage of 783,000, or a total of $313,200.
2. Therefore, plaintiff’s bid was $313,-200 for 463,968 compacted cubic yards.
3. $313,200 divided by 463,968 cubic yards equals 67^4 cents per cubic yard.
4. 473,504 cubic yards actually furnished multiplied by 67}/¿ cents equals $319,615.20.
5. $319,615.20, less the amount paid by the State, leaves a balance of $57,-140.40.

As we have previously indicated, the superior court awarded judgment to the plaintiff in this amount, i. e., $57,140.40, together with interest thereon, thereby determining there was no genuine issue as to any material fact and that plaintiff was entitled to reformation as a matter of law.

This case has been thoroughly and extensively briefed by counsel for the respective parties. The sole issue on review, however, is whether disposition of the case on a motion for summary judgment was proper under Rule 56(c), as amended, Arizona Rules of Civil Procedure, 16 A.R.S. In determining whether there was error in the granting of plaintiff’s motion for summary judgment, the record must be construed most strongly in defendant’s favor. Peterson v. Valley National Bank of Phoenix, 90 Ariz. 361, 368 P.2d 317 (1962); Ray Scottsdale Lumber Co. v. First Federal Savings and Loan Association, 3 Ariz.App. 366, 414 P.2d 754 (1966) ; State v. Standard Oil Company of California, 3 Ariz.App. 389, 414 P.2d 992 (1966).

*602 The Supreme Court of Arizona has suggested that trial judges should exercise great care in granting motions for summary-judgment, notwithstanding the desirability of prompt dispatch of judicial business. Lujan v. MacMurtrie, 94 Ariz. 273, 383 P.2d 187 (1963).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson v. Manten
Court of Appeals of Arizona, 2023
HSBC v. Cluff
Court of Appeals of Arizona, 2018
Holm v. Gateway
Court of Appeals of Arizona, 2018
Diaz-Amador v. Wells Fargo Home Mortgages
856 F. Supp. 2d 1074 (D. Arizona, 2012)
Mann v. GTCR Golder Rauner, L.L.C.
425 F. Supp. 2d 1015 (D. Arizona, 2006)
Dalton v. McLaughlin
635 P.2d 863 (Court of Appeals of Arizona, 1981)
Northern Contracting Co. v. Allis-Chalmers Corp.
573 P.2d 65 (Arizona Supreme Court, 1977)
Richard W. Bosse v. Crowell Collier and MacMillan
565 F.2d 602 (Ninth Circuit, 1977)
Bohn v. Divine
544 P.2d 916 (Court of Civil Appeals of Oklahoma, 1975)
Wick v. Wick
481 P.2d 298 (Court of Appeals of Arizona, 1971)
Howell v. Remme
480 P.2d 365 (Court of Appeals of Arizona, 1971)
Hackin v. Pioneer Plumbing Supply Co.
457 P.2d 312 (Court of Appeals of Arizona, 1969)
ASHTON COMPANY, INC., CONTR. & ENG'RS v. State
454 P.2d 1004 (Court of Appeals of Arizona, 1969)
Gaethje v. Gaethje
442 P.2d 870 (Court of Appeals of Arizona, 1968)
Executive Towers v. Leonard
439 P.2d 303 (Court of Appeals of Arizona, 1968)
Cordoba v. Wiswall
436 P.2d 922 (Court of Appeals of Arizona, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
422 P.2d 727, 4 Ariz. App. 599, 1967 Ariz. App. LEXIS 344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-ashton-company-arizctapp-1967.