Seaboard Lumber Co. v. United States

48 Fed. Cl. 814, 2001 U.S. Claims LEXIS 32, 2001 WL 280246
CourtUnited States Court of Federal Claims
DecidedMarch 15, 2001
DocketNos. 370-88C, 610-84C
StatusPublished
Cited by9 cases

This text of 48 Fed. Cl. 814 (Seaboard Lumber Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Lumber Co. v. United States, 48 Fed. Cl. 814, 2001 U.S. Claims LEXIS 32, 2001 WL 280246 (uscfc 2001).

Opinion

OPINION

BRUGGINK, Judge.

This action is part of a consolidated group of cases arising out of termination by the United States Forest Service (“Service” or “Forest Service”) of timber sales contracts in the Northwest during the 1980’s. Seaboard Lumber Company (“Seaboard”), along with other companies, brought actions under the Contract Disputes Act1 in an effort to have their non-performances of contract declared legally excused and to have the Service’s claims reduced or set aside. The government has counterclaimed. Most issues raised in the complaint and counterclaim have been resolved in this action, as in others.2 Trial was conducted from October 16 through 19,2000, in Seattle.

A single contract between Seaboard and the Forest Service is at issue: the “What” sale. It involved timber on Forest Service managed lands in Washington state. Seaboard’s non-performance is conceded. Pursuant to the contract, remaining timber was offered for resale. The terms of the resale were not identical to the original sale. Partly this is due to the fact that, at the time the contract at issue was re-offered, new regulations had changed the terms under which timber contracts legally could be entered. The government has conceded that some of those changes had a material effect on the amount of the resale.

The primary issue addressed by the trial in Seaboard is whether the government lost or compromised its right to pursue a damage claim against Seaboard because the Forest Service resold the remaining timber on sub[816]*816stantially different terms from those in the original contract. Post-trial briefing is complete. For the reasons which follow, the court concludes that defendant is entitled to recover on its counterclaim, as adjusted herein.

FACTUAL AND PROCEDURAL BACKGROUND

The parties have entered into a substantial stipulation in this case. In addition, the court’s prior rulings provide much of the general factual and procedural background. Familiarity with those rulings is presumed. See supra note 2. The parties have also agreed that all testimony in the 1999 trial in a related case, Capital Development Corp. v. United States, Fed.Cl Ct. Nos. 610-84C and 750-87C (referred to herein as “CDC”), can be used in deciding this case.

Timber Sales Generally

The government relied primarily on two witnesses to explain the major components of the bidding process for Forest Service timber contracts. Jerry Hofer is currently head of sales, contracts and measurements for the Pacific Northwest Region of the Service, headquartered in Portland. The Pacific Northwest Region embraces the contracts at issue. He has served in the region previously as a Regional Forester Representative, acting on the Forester’s behalf in determining whether timber sale administrators were performing as required. In addition, he has served as a contracting officer and is a certified appraiser. The second witness was Christine Anderson. She is currently both a contracting officer and Assistant for Timber Management Sales to the Regional Forester. Neither witness was directly involved in the termination of the contract at bar, or in the subsequent resales. Their evidence was directed at how the Region typically conducted its activities during the relevant period, and, based on their review of the records, what happened in these contracts.

From the standpoint of potential bidders, a timber sale commences when the Forest Service puts out a prospectus describing the timber site and the terms on which the contract is offered. Imbedded within the prospectus are numerous figures, calculations, and implicit decisions made internally by the Service. Also included within the prospectus is a minimum opening bid price, a figure that becomes important both in terms of the award and any subsequent resale attempt. The minimum bid price is the higher of the appraised rate (calculated by the Forest Service from cost data), the regulatory minimum rate for a given species, or the cost of essential reforestation, plus fifty cents per thousand board feet (mbf), known as the KV cost.3 The contract may also provide “purchaser credits” which are intended to compensate the contractor for building roads on the site. As the roads are built, the contractor will receive a credit against the contract price above base rates it owes to the Forest Service. The amount of credit awarded per mile of road completed is set out in the contract. The prospectus also sets the length of time the contractor will be allowed to perform the contract and speaks to the timing of contractor payments for timber.

Interested parties are invited to bid based on the information provided in the prospectus and the bidders’ own examination of the site. The terms laid out in the prospectus are not open to negotiation. Our predecessor court has held that Forest Service timber contracts are contracts of adhesion. See Everett Plywood Corp. v. the United States, 227 Ct.Cl. 415, 418, 651 F.2d 723 (1981).

The “What” Sale

The “What” sale was advertised on August 7, 1980. It is located in the Quilcene Ranger District of the Olympic National Forest in western Washington state. The sale cruise estimated 5,700 mbf of merchantable timber and an estimated 600 mbf of per acre materi[817]*817al (“PAM”). There were eight units to be clearcut and one unit to be thinned. The total advertised value of the sale was $328,109. The sale called for construction of 1.86 miles of new roads and reconstruction of 1.74 miles of existing roads. The purchaser road credit could not exceed $370,501.

The agency conducted bidding on September 9, 1980. Seaboard’s was the highest of four bids, at $925,828. In addition to the requirement to cut and pay for all timber at bid rates, Seaboard had to pay deposits for slash disposal ($24.56 per mbf) and road maintenance by the Forest Service ($3.79 per mbf). The contract length was 31 months, of which 18.5 months fell within the normal operating season of April 1 through November 30. Nine months of operating season fell after the required road completion date of November 1,1981. The parties subsequently agreed to an extension to March 31, 1985 under the agency’s SOFT II extension policy.4 A second modification was agreed to in connection with litigation Seaboard and other timber companies had initiated. The contract eventually expired on December 28, 1985.

At the time the contract terminated, Seaboard had partially performed. It had constructed all of the specified roads and had harvested 323 mbf of timber from the road rights-of-way. Seaboard had not cut any other timber in the nine harvesting units, however. On January 15,1986, the contracting officer notified Seaboard by letter that the contract had terminated uncompleted, and that the remaining timber would be resold in accordance with the terms of the contract.

The contract sets out at Provision B9.4, “Failure to Cut,” the formula for calculation of damages triggered by Seaboard’s failure to cut the timber:

Damages due ... shall be the amount by which Current Contract Value[,] plus the cost of resale, less any effective Purchaser Credit remaining at the time of termination, exceeds the resale value at new Bid Rates. If there is no resale, damages shall be determined by subtracting the value established by said appraisal from the difference between Current Contract Value and Effective Purchaser Credit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Ohio v. United States
Federal Claims, 2022
Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
Precision Pine & Timber, Inc. v. United States
75 Fed. Cl. 80 (Federal Claims, 2006)
Lassiter v. United States
60 Fed. Cl. 265 (Federal Claims, 2004)
Coady Corp. v. Toyota Motor Distributors, Inc.
361 F.3d 50 (First Circuit, 2004)
Westchester Fire Insurance v. United States
52 Fed. Cl. 567 (Federal Claims, 2002)
Capital Development Co. v. United States
49 Fed. Cl. 178 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
48 Fed. Cl. 814, 2001 U.S. Claims LEXIS 32, 2001 WL 280246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-lumber-co-v-united-states-uscfc-2001.