Seaboard Lumber Co. v. United States

45 Fed. Cl. 404, 1999 U.S. Claims LEXIS 284, 1999 WL 1128970
United States Court of Federal Claims·Decided November 22, 1999·No. No. 429-89C·Published·Cited by 4 cases

Opinion

OPINION

BRUGGINK, Judge.

This dispute arises out of a timber sale contract between the United States Forest Service and plaintiff, Great Western Lumber Company. After the contract expired without performance, the agency issued a final decision asserting reprocurement damages. Plaintiff brings this action pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 601-613 (1994), seeking to overturn that decision on the ground that the contract was illegal from the outset and should have been canceled. The government counterclaim attempts to enforce the final decision. The case was transferred to this judge on February 4, 1999. The matter is pending on cross motions for summary judgment. The matter has been fully briefed and orally argued. As explained below, the court concludes that the contract was not illegal and that plaintiff was not relieved of its duty to perform. Defendant’s motion for summary judgment is thus due to be granted as to liability. The motion is denied in part, however, as damages on defendant’s counterclaim cannot yet be determined.

FACTS1

The relevant facts are undisputed. Great Western was second highest bidder at the 1979 auction of the Headwaters Timber Sale. [406]*406The timber was situated in the Mount Baker-Snoqualmie National Forest in the state of Washington. Plaintiff agreed to accept the high bid price and other terms of the sale after the original high bidder was disqualified. By the original terms of the contract, by March 31, 1984, plaintiff was to cut, remove, and pay for timber estimated to be 5,600 thousand board feet (MBF). The Forest Service later adjusted the contract termination date to July 31, 1987 to compensate for delays in road construction on the site. The contract expired uncompleted on July 31, 1987. Except for right-of-way clearing during road work, no timber was cut. The Forest Service found plaintiff in breach and assessed damages after resale of $328,983.47 pursuant to contract clause B9.4.

DISCUSSION

Plaintiff filed its defensive claim pursuant to the CDA. That act gives this court jurisdiction over plaintiffs claim because a timber sale contract is an express contract for the disposal of personal property as contemplated by the CDA. See 41 U.S.C. § 602(a); Mendenhall v. Kusicko, 857 F.2d 1378, 1379 (9th Cir.1988) (per curiam); Spectrum v. United States, 764 F.2d 891, 893 n. 3 (D.C.Cir.1985).

Breach—road building

Under contract clause C5.101, the Forest Service was to have completed road work on the subject property by September 30, 1981. Paragraph C5.101 provided that where “the actual date of road completion is one year or more after the [contractual completion date for road construction] Purchaser may request a rate redetermination.” Paragraph C5.101 also required that the purchaser request any rate redetermination within 30 days after notification that road work was completed. On October 25, 1983 the Forest Service issued its notification that roads built for the Headwaters Timber Sale had been completed. Plaintiff elected to request a rate redetermination, however it did not do so until March 19, 1985, almost 15 months later.

Plaintiffs notice was thus plainly untimely. It relies, however, as discussed below, on a body of law dealing with defective notice to argue that, because the government was not harmed and was aware of the operative facts, plaintiffs late notice should be honored. Plaintiff claims that the requested adjustment in rates payable for the Headwaters timber sale would more than offset the damages the government claims and would have permitted Great Western to perform without a loss. Plaintiff characterizes the government’s refusal to lower the rates as “a breach which, in effect prevented plaintiffs performance.” (P.’s Cross Mot. Summ. J. at 6).

Defendant counters that contract clause B6.ll precludes constructive notice to the Forest Service. It states: “[n]otices by either party as to action taken or to be taken by the other respecting this contract shall be made in writing.” Defendant also notes that the request for rate determination is discretionary on plaintiffs part, based on its assessment of the business climate. Under some circumstances, therefore, plaintiff might have elected not to seek rate redeter-mination, although that is unlikely in this case, as the market for timber had deteriorated.

The court agrees with defendant that the notice was untimely and therefore ineffectual. Hoel-Steffen Const. Co. v. United States, 197 Ct.Cl. 561, 456 F.2d 760 (1972), and its progeny, upon which plaintiff relies, are inapposite because they deal with notice of a different sort, given for a different reason. The plaintiff in Hoel-Steffen was one of three contractors working to build the Saint Louis Gateway Arch. All three contractors needed to work in the narrow confines of the north leg of the arch. Hoel-Steffen claimed that its installation of ductwork was delayed when the government gave priority of access to the other two contractors, causing Hoel-Steffen to incur extra costs. Our predecessor court described the inquiry at issue as “whether the contractor put the Government on notice of the government conduct complained about, so that the procurement official could begin to collect data on the asserted increase in cost, and could also evaluate the desirability of continuing the delay-causing conduct.” Id. at 571, 456 F.2d at 766. It concluded that “the proof demonstrated that the defendant [407]*407knew or should have known that it was called upon to act.” Id. at 572, 456 F.2d at 767.

Plaintiff also relies on Russell Construction, AGBCA No. 379, 74-2 BCA ¶ 10,911 and R.R. Tyler, AGBCA No. 381, 77-1 BCA ¶ 12,227, and other cases citing Hoelr-Steffen to support a liberal treatment of notice requirements. Russell and Tyler involved Forest Service contracts to construct steel reinforced concrete bridges. In both cases the contractors encountered site conditions different than anticipated, which led to delays and additional expense. Contract terms called for timely written notice of a dispute, in Russell, and timely written notice of a claim based on a change order, in Tyler. The Board of Contract Appeals in Russell found that the Contracting Officer was aware that the contractor was claiming a differing site condition, despite the lack of formal written notice. In Tyler the Board found that the government had constructive, if not actual, notice of the bases for appellant’s objections and that they might give rise to a claim for extra compensation.

The purpose of notice in these cases was to permit the government to resolve, for example, differing site conditions short of the necessity of a claim, or to mitigate costs to the contractor of a government-caused delay. What they have in common is the government’s independent ability to react to knowledge of facts. Whether notice is constructive or written, therefore, is not critical.

Free access — add to your briefcase to read the full text and ask questions with AI

Seaboard Lumber Co. v. United States, 45 Fed. Cl. 404, 1999 U.S. Claims LEXIS 284, 1999 WL 1128970 (uscfc 1999).

45 Fed. Cl. 404 (Seaboard Lumber Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gazpromneft-Aero Kyrgyzstan LLC v. United States
132 Fed. Cl. 202 (Federal Claims, 2017)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Seaboard Lumber Co. v. United States
48 Fed. Cl. 814 (Federal Claims, 2001)