Daniel E. Terreri & Sons, Inc. v. Mahoning County Board of Commissioners

786 N.E.2d 921, 152 Ohio App. 3d 95
CourtOhio Court of Appeals
DecidedMarch 10, 2003
DocketCase No. 00 CA 269.
StatusPublished
Cited by39 cases

This text of 786 N.E.2d 921 (Daniel E. Terreri & Sons, Inc. v. Mahoning County Board of Commissioners) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daniel E. Terreri & Sons, Inc. v. Mahoning County Board of Commissioners, 786 N.E.2d 921, 152 Ohio App. 3d 95 (Ohio Ct. App. 2003).

Opinion

Waite, Presiding Judge.

{¶ 1} This timely appeal and cross-appeal arise out of bench trial in the Mahoning County Court of Common Pleas in which appellants were found to be in breach of two construction contracts. For the following reasons, judgment is reversed as to the breach-of-contract claims and judgment entered for appellants on these claims. The matter is to be remanded for further proceedings as to any amounts appellants may owe under the “termination for convenience” clauses of the contracts. Judgment is also reversed with respect to damages for lost bonding capacity, because appellees did not demonstrate that any other contracts were actually lost or that the parties contemplated lost bonding capacity when entering into these contracts.

{¶ 2} The record reveals that in 1996, Mahoning County became involved in a project to renovate the former Higbee building in downtown Youngstown so that it could be used for government office space. Title to the property was transferred to the county in 1996 to facilitate the project. In June 1996, Terreri Construction Company, Inc. (“Terreri”), put in a .bid to renovate the roof and atrium of the Higbee building (“roof/atrium contract”). At the same time, Terreri and Avila Contracting and Supply Company, Inc. (“Avila Supply”), put in a bid, as a joint venture, on another part of the project calling primarily for demolition work in the Higbee building (“demolition contract”). Terreri and Avila Supply are appellees in this appeal.

{¶ 3} On July 30, 1997, the Mahoning County Board of Commissioners recommended awarding the roof/atrium contract to Terreri at a cost of $1,580,000, and recommended awarding the demolition contract to the Terreri/Avila Supply joint venture at a cost of $578,000. As part of the bidding process, Terreri filed bid guarantees and performance bonds in the amounts of the proposed contracts. There are documents in the record indicating that Terreri could obtain only a maximum of $3,000,000 worth of performance bonds approved by its insurance company. The record does not indicate that appellants were made aware of Terrerf s bonding capacity.

{¶ 4} The parties all signed the contracts on September 18,1997.

{¶ 5} Both appellees sent appellants a letter on October 10, 1997, requesting a notice to proceed and an increase of 15 percent in the contract price. The contracts had provisions that permitted appellees to begin work only after receiving a “notice to commence” from appellants. By letter, appellees threat *100 ened to withdraw their bid if a notice to proceed or an increase in the contract price was not forthcoming by October 31,1997.

{¶ 6} Appellees sent appellants another letter on October 23, 1997, declaring that if appellants issued a notice to proceed, appellants were also agreeing to an “equitable increase” in the contract price. Appellees once again proposed a 15 percent increase and declared that their bid was being withdrawn if no notice to proceed or letter of understanding was received by November 14,1997.

{¶ 7} On December 1, 1997, appellees declared, by letter, that they were withdrawing from the contracts.

{¶ 8} On December 5, 1997, appellants transferred the title of the Higbee building to the Community Investment Corporation (“CIC”), an organization that facilitates public building projects in the city of Youngstown.

{¶ 9} Sometime between December 6, 1997, and January 6, 1998, Mr. Terreri spoke with Gary Kubic, Mahoning County Administrator, about whether the contracts could be assigned to or renegotiated with CIC. Nothing was resolved in this conversation.

{¶ 10} On January 6, 1998, appellants returned $2,000,000 to the state of Ohio that had been earmarked for the project.

{¶ 11} Sometime in early April 1998, the CIC announced that it was not going to renovate the Higbee building and was going to build a smaller version of an office tower on property next to the Higbee building.

{¶ 12} Appellees filed a breach-of-contract complaint on April 17, 1998. Appellees named four defendants: the Board of Mahoning County Commissioners (“board of commissioners”); Gary Kubic (“Kubic”), the county administrator; George Tablack (“Tablack”), Mahoning County Auditor; and Olsavsky-Jaminet Architects (“Olsavsky”). The first three of these defendants constitute the appellants in this appeal.

{¶ 13} Appellees’ first cause of action involved an April 1996 contract for the removal of asbestos in the former Higbee building in downtown Youngstown. The second cause of action alleged a breach of the roof/atrium contract. The third cause of action alleged a breach of the demolition contract. The fourth cause of action alleged that appellants failed to release appellees’ construction bond, which prevented them from pursuing other contracting work and which caused lost profits.

{¶ 14} On May 20, 1999, the trial court filed a judgment entry declaring that count one of the complaint had been settled and dismissing defendant Olsavsky from the case. Count one is not part of this appeal.

*101 {¶ 15} On June 30, 1999, the remaining defendants filed a motion for summary judgment. They argued that (1) the terms of the contracts prohibited appellees from recovering damages due to any delays preventing completion of the contract, (2) appellees alleged no facts indicating the actual amount of lost profits, requiring the dismissal of count four of the complaint, and (3) Mahoning County Auditor Tablack should be dismissed from the suit.

{¶ 16} On August 2, 1999, appellees filed their motion in opposition to summary judgment. Appellees argued that they were not seeking damages for delays, but, rather, damages from being prevented from doing any work on the contracts. Appellees also presented evidence of their profits and losses from 1992-1998.

{¶ 17} On August 16, 1999, appellants filed a reply to appellees’ brief in opposition to summary judgment. Appellants argued that the contracts contained “termination for convenience” clauses that allowed appellants’ to terminate the contracts for no reason upon ten days’ written notice, and, if the contracts so terminated, would create liability only for the percentage of the work already completed plus costs related to the termination. Appellants argued that they were justified in assuming that the termination for convenience clauses were constructively invoked after appellees sent letters stating that they were withdrawing from the contract unless the contract price was increased by 15 percent. Appellants urged the court to use the “termination for convenience” clause as a basis for granting their motion for summary judgment.

{¶ 18} The summary judgment motion was presented to a magistrate. The magistrate denied the motion on August 25, 1999. The magistrate also denied the request to have Auditor Tablack dismissed from the case. Appellants filed objections to the magistrate’s decision. The objections were overruled by the trial court on October 29, 1999. Appellants filed an appeal of that decision with this court, which was designated Appeal Case No. 99 CA 296. On February 16, 2000, this court dismissed the appeal for lack of a final, appealable order, in which we held that the denial of motion for summary judgment is not immediately appealable.

{¶ 19} The case went to bench trial on October 25-27, 2000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bova v. B & J Pools, Inc.
2023 Ohio 1680 (Ohio Court of Appeals, 2023)
Am. Business Invests., L.L.C. v. Shaeena & Allos, L.L.C.
2023 Ohio 739 (Ohio Court of Appeals, 2023)
Nighswander v. Waterstone LSP, L.L.C.
2022 Ohio 971 (Ohio Court of Appeals, 2022)
Phelps v. Community Garden Assn., Inc.
2021 Ohio 3675 (Ohio Court of Appeals, 2021)
Valentine v. Cedar Fair, L.P.
2021 Ohio 2144 (Ohio Court of Appeals, 2021)
Joseph Bros. Co., L.L.C. v. Dunn Bros., Ltd.
2019 Ohio 4821 (Ohio Court of Appeals, 2019)
JDS So Cal, Ltd. v. Dept. of Natural Resources
2018 Ohio 1159 (Ohio Court of Appeals, 2018)
Atlas Noble, LLC v. Krizman Enterprises
692 F. App'x 256 (Sixth Circuit, 2017)
Quest Workforce Solutions, L.L.C. v. Job1USA, Inc.
2016 Ohio 8380 (Ohio Court of Appeals, 2016)
Sunesis Trucking Co., Inc. v. Thistledown Racetrack, L.L.C.
2014 Ohio 2411 (Ohio Court of Appeals, 2014)
Tri-City Assocsiates, LP v. Belmont, Inc.
2014 SD 23 (South Dakota Supreme Court, 2014)
Ohio Bur. of Workers' Comp. v. McKinley
2014 Ohio 1397 (Ohio Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
786 N.E.2d 921, 152 Ohio App. 3d 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daniel-e-terreri-sons-inc-v-mahoning-county-board-of-commissioners-ohioctapp-2003.