DiGioia Bros. Excavating, Inc. v. Cleveland Department of Public Utilities

734 N.E.2d 438, 135 Ohio App. 3d 436
CourtOhio Court of Appeals
DecidedNovember 29, 1999
DocketNo. 75081.
StatusPublished
Cited by12 cases

This text of 734 N.E.2d 438 (DiGioia Bros. Excavating, Inc. v. Cleveland Department of Public Utilities) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DiGioia Bros. Excavating, Inc. v. Cleveland Department of Public Utilities, 734 N.E.2d 438, 135 Ohio App. 3d 436 (Ohio Ct. App. 1999).

Opinion

Porter, Administrative Judge.

Defendant-appellant, city of Cleveland, Department of Public Utilities, Division of Water, appeals from the jury verdicts and judgment awarding $604,602 to plaintiff-appellee, DiGioia Brothers Excavating, Inc., arising from installation of a water main on Hilliard Boulevard in Rocky River and Westlake, Ohio. The city claims that the trial court erred in directing a liability verdict in favor of plaintiff and not in favor of defendant and in failing to properly instruct the jury on disputed issues. We find merit in the appeal, reverse and enter judgment in part for the city, and remand the remaining issues for a new trial.

This action arises out of a breach-of-contract claim filed October 2, 1996, by DiGioia Brothers against the city, asserting that specific omissions of utility-interference references in the construction drawings resulted in damages for delay and that additional costs were incurred for pavement-replacement work not required by the contract.

In 1991, the city’s water department implemented a multimillion-dollar program for the rehabilitation of the Crown Waterworks including the pump station and the water mains located on the west side of Cleveland beginning at Clague Road and 1-90. Phase I involved the installation of a new underground water main beginning at the pump station at Clague Road and continuing west along Hilliard Boulevard. This was the new water main on which DiGioia Brothers worked, a stretch covering about three miles. Phase I needed to be completed before the winter of 1996 so that the Crown Waterworks Pump Station could be taken off line for a major rehabilitation. The new water main was designed to connect with other pump stations to supply fresh water during rehabilitation of the Crown facility.

Phase I of the Crown Project was designed by the engineering firm of Stilson & Associates under contract with the city. Stilson was required to identify the location of existing underground field utilities within the right of way. Stilson hired various MBE engineering firms to compile the necessary information to *441 plot the existing underground field utilities. Based upon that information, Stilson designed the installation of the new water main at specified depths and locations along mile markers in order to avoid the preexisting underground field utilities. In 1995, DiGioia was the successful low bidder.

The contract between the parties included the detailed specifications and construction drawings created by Stilson reflecting the underground utilities that DiGioia Brothers would have to work around. The contract called for DiGioia’s work to be completed by November 1, 1995, for a fixed contract price of $5,491,300, which included a contingency allowance of $400,000. DiGioia’s successful bid was $250,000 under the next closest bid.

At trial, one of DiGioia’s principal claims was that twenty-six underground utility interferences were either not shown on the construction drawings or were shown in the wrong location and that this adversely affected the contractor’s performance, causing -a total delay of four and one half weeks during the seven-month project. The contract plans indicated four hundred fifty-five other utility interferences that were properly identified, including water lines, gas lines, sanitary sewer lines and storm sewer lines, i e., approximately ninety-five percent of the utilities ultimately found were correctly shown on the drawings.

The contract contained a detailed process for change orders at General Condition B-34. Mutually agreed change orders were issued for those undisclosed twenty-six utility interferences encountered, and $90,000 was allowed from the $400,000 contingency fund for the cost of doing this extra work. DiGioia never provided the city with any written correspondence or objections to the disposition of these change orders.

At trial, DiGioia claimed that it had been only partially compensated for the utility interferences and had been verbally assured by John Wood, the city’s project manager, that it might obtain additional compensation for loss of productivity upon completion of the contract. The city contended that Wood had no authority to depart from the contract procedures. DiGioia never sought recovery through the change-order process for lost productivity associated with the utility interferences.

John Wood testified that he did not have authority to authorize additional payment and that he could only recommend that a claim be considered. Wood had discussions with his superior, Sal Provenzano, at SVMT, the city’s program management consultant, over lost productivity. Provenzano determined that the only delay that was meaningful according to the contract was completion delay, i.e., extension of performance time (a day of extension for each day of delay), not additional compensation. A preconstruction meeting held on February 22, 1995, established rules for communication on the project, including a rule not to accept verbal directions on changes in the work.

*442 General Condition B-6 of the contract provided that in the case of any delay beyond the contractor’s control, it was not entitled to assert against the city any claim other than for an extension of time in which to perform the work. Specifically, Section 01914, Part 1.01, Paragraph C of the contract provided that the cost of changing the position of underground utilities “shall not be an obligation of the Contractor under this Contract, but no claim for damage due to delay or any other cause by any change in location of the structures herein mentioned will be considered or allowed by the City.” DiGioia also acknowledged that in the contract the city did not guarantee the accuracy of the information on utility interferences appearing in the contract drawings. Section 01916(A) stated that “no claim by the Contractor will be entertained by the City which claim is based on the failure to have indicated correctly any sewer or appurtenance.”

DiGioia’s project manager, Bruce Tuttle, who also estimated the bid for DiGioia, testified that he expected to encounter utility interferences not shown on the designer’s plans. He acknowledged that as a matter of course there are utility interferences in every project that are not shown on the designer’s plan drawings and that the contractor needs to estimate the amount of unknown but anticipated utility interferences, incorporate that estimate into the bid, and be responsible for that assumption. He had estimated that six utility interferences would be encountered and opined that the twenty-six interferences was an extreme amount.

DiGioia achieved substantial completion of the contract on time, i.e., by November 1, 1995. DiGioia was also required by the contract to supply a certificate of substantial completion on which to list all outstanding claims. The certificate of substantial completion stated, “The acceptance of substantial completion payment shall constitute a waiver of all claims by the Contractor as unsettled at the time of the Application for Substantial Completion, and except for retainage sum due at final acceptance.” On the certificate, DiGioia listed three outstanding claims: for additional pavement quantity, for improper crew deductions made by SVMT from the amount claimed by DiGioia on the authorized change orders related to utility interferences, and for additional test stations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
734 N.E.2d 438, 135 Ohio App. 3d 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/digioia-bros-excavating-inc-v-cleveland-department-of-public-utilities-ohioctapp-1999.