R.E. Schweitzer Constr. Co. v. Univ. of Cincinnati

2010 Ohio 2649
CourtOhio Court of Claims
DecidedMay 18, 2010
Docket2007-02114
StatusPublished

This text of 2010 Ohio 2649 (R.E. Schweitzer Constr. Co. v. Univ. of Cincinnati) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.E. Schweitzer Constr. Co. v. Univ. of Cincinnati, 2010 Ohio 2649 (Ohio Super. Ct. 2010).

Opinion

[Cite as R.E. Schweitzer Constr. Co. v. Univ. of Cincinnati, 2010-Ohio-2649.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

R.E. SCHWEITZER CONSTRUCTION CO.

Plaintiff

v.

UNIVERSITY OF CINCINNATI

Defendant Case No. 2007-02114

Judge Clark B. Weaver Sr.

DECISION

{¶ 1} Plaintiff brought this action alleging breach of contract. The case proceeded to trial on the issues of liability and damages. {¶ 2} In June 2004, plaintiff was awarded a contract for a construction project entitled “Demolition, Disassembly & Site Restoration for Pavilions- Phase 1” which involved the removal of four temporary tent-like structures and their associated foundations, utilities, and other improvements. The contract provided that plaintiff would retain salvage rights to the removed structures. {¶ 3} Shortly after the contract was executed, but before plaintiff had commenced work, defendant inquired as to whether plaintiff would relinquish its salvage right to the largest structure (tent), which had served as a temporary dining hall, so that the tent could be relocated to defendant’s Clermont County Campus (CCC) for use as a gymnasium. On June 25, 2004, Robert Schweitzer, plaintiff’s vice president and project manager, responded by e-mail to advise Peter Luken, defendant’s project manager, that the tent was available and that plaintiff proposed to perform the demolition, transportation, and reinstallation work for a total of $494,850. (Plaintiff’s Exhibit 58.) Luken testified that defendant wanted to preserve the warranty on the tent which existed through the tent manufacturer, Sprung Instant Structures, Inc. (SIS). {¶ 4} According to meeting notes that were prepared by Paul Bellman, the project manager for defendant’s associate architect, THP, Limited, Inc. (THP), on July 1, 2004, the relocation of the tent to CCC was “under review.” (Plaintiff’s Exhibit 9.) On July 15, 2004, during another project meeting, Bellman announced that the relocation project was “a go.” {¶ 5} On August 16, 2004, plaintiff obtained a written quote from SIS to provide a “technical consultant” who would be available on site during the dismantling and reconstruction of the tent. (Plaintiff’s Exhibit 13.) The quote states that the consultant would “provide information about membrane and/or parts installation and, if applicable, assembly and erection of the structure”; however, the consultant would not be authorized “to perform any other services.” Schweitzer testified that the consultant would not perform any of the work disassembling or erecting the tent and that the role of the consultant would be to “witness” the work and to offer advice. On August 25, 2004, Bellman confirmed that participation by SIS was necessary for maintenance of the warranty. (Plaintiff’s Exhibit 51.) SIS subsequently advised plaintiff that it would continue to honor the warranty if plaintiff engaged Florida Exposition Services (FES), a contractor experienced in the erection and disassembly of SIS tents, to perform the work. (Plaintiff’s Exhibit 16.) {¶ 6} On September 1, 2004, Schweitzer provided defendant with a “breakdown” of the quote that it had previously submitted for the removal and transportation of the tent. (Plaintiff’s Exhibit 17.) The breakdown showed that the cost associated with consulting was $37,000, that the value of the structure was $79,000, and that the charge for salvage and removal of the tent was $89,661. Plaintiff’s cost proposal also included amounts for “set up” costs related to the relocation at CCC; however, defendant subsequently solicited public bids for the site work and re-erection at CCC, which was eventually awarded to another firm under a separate contract. {¶ 7} On September 30, 2004, plaintiff submitted a change order proposal to THP which showed that FES had been hired as a demolition subcontractor at a cost of $50,906 plus $2,545.30, which represents a five percent markup, for a total of $53,451.30. Defendant eventually approved the change order proposal in all respects except for the costs related to FES, which defendant rejected as “double-dipping” inasmuch as demolition work was included in the scope of the original contract. (Plaintiff’s Exhibit 29.) Schweitzer signed the change order to receive payment on the undisputed amount, noting that the change order represented only a “partial accord and satisfaction” for the work. (Defendant’s Exhibit B.) {¶ 8} In January 2005, plaintiff submitted its claim pursuant to Article 8 of the contract.1 Pursuant to R.C. 153.12 (B) and 153.16 (B), plaintiff’s administrative remedies were deemed to have been exhausted 120 days after the claim was submitted under Article 8. {¶ 9} As an initial matter, defendant contends that plaintiff’s complaint was not timely filed and is barred by the statute of limitations. The court notes that on August 27, 2007, the court issued an entry denying defendant’s motion for summary judgment based upon the statute of limitations. The court determined that plaintiff had timely filed its complaint within two years after April 12, 2005, the date that plaintiff’s administrative remedies were deemed to have been exhausted pursuant to R.C. 153.12(B) and 153.16(B). {¶ 10} The evidence adduced at trial is not materially different from the evidence that was submitted in connected with the motion for summary judgment. In the entry denying summary judgment, the court found that “the only reasonable conclusion to be drawn from the undisputed evidence is that plaintiff’s complaint was timely filed.” Based upon the evidence submitted at trial and for the reasons set forth in the entry denying

1 Article 8 provides as follows:

“8.1.1 Whenever the Contractor intends to seek additional compensation or mitigation of Liquidated Damages, whether due to delay, extra Work, additional Work, breach of Contract, or other causes arising out of or related to the Contract or the Project, the Contractor shall follow the procedures set forth in this Article. To the fullest extent permitted by law, failure of the Contractor to timely provide such notice shall constitute a waiver by the Contractor of any claim for additional compensation or for mitigation of Liquidated Damages.

“8.1.2 The Contractor shall make a claim in writing filed with the Associate and prior to Contract Completion, provided the Contractor notified the Associate, in writing, no more than ten (10) days after the initial occurrence of the facts, which are the basis of the claim.” summary judgment, the court finds that plaintiff’s complaint was timely filed. See Painting Co. v. Ohio State Univ., Franklin App. No. 09AP-78, 2009-Ohio-5710, ¶13-15. (“Under the terms of R.C. 153.12(B) and 153.16(B), plaintiff’s cause of action for breach of contract accrued * * * when the 120-day period lapsed after plaintiff’s appeal to the State Architect, regardless of whether the State Architect subsequently issued a final decision on the validity of plaintiff’s claims.”) {¶ 11} In its action for breach of contract, plaintiff seeks to recover both the balance of the original contract amount that was not paid to plaintiff and compensation for additional work FES performed which was itemized in the change order request but not approved in the change order that defendant issued. Defendant asserts that the change order fairly compensated plaintiff for any additional work and that plaintiff is barred from pursuing additional compensation for that work by accepting compensation under the change order. Defendant further asserts that plaintiff is not entitled to payment of any balance that might otherwise have been owed under the original contract inasmuch as plaintiff has failed to submit prevailing wage documents that are required for payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2010 Ohio 2649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/re-schweitzer-constr-co-v-univ-of-cincinnati-ohioctcl-2010.