corna/kokosing v. South-Western City, Unpublished Decision (12-19-2002)

CourtOhio Court of Appeals
DecidedDecember 19, 2002
DocketNo. (REGULAR CALENDAR)
StatusUnpublished

This text of corna/kokosing v. South-Western City, Unpublished Decision (12-19-2002) (corna/kokosing v. South-Western City, Unpublished Decision (12-19-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
corna/kokosing v. South-Western City, Unpublished Decision (12-19-2002), (Ohio Ct. App. 2002).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, Corna/Kokosing Construction Company, appeals from a judgment of the Franklin County Court of Common Pleas granting the summary judgment motion of defendant-appellee, South-Western City School District Board of Education ("the board"), on plaintiff's claim for breach of contract. Plaintiff assigns a single error:

{¶ 2} "The trial court erred in granting summary judgment to the defendant on the basis that the contract required plaintiff to seek pre-bid approval to use an un-named manufacturer of curtain wall materials."

{¶ 3} Because the trial court did not err in granting the board's summary judgment motion on plaintiff's breach of contract claim, we affirm.

{¶ 4} Plaintiff's action for breach of contract arises out of a construction project where the board, acting for the South-Western City School District, accepted bids for the construction of the South-Western New Career Academy in Grove City ("the project"). The project manual prepared for the project included instructions to the bidders, as well as contract specifications, conditions, and requirements. The specifications for the building's glazed aluminum curtain wall system, which forms the building's exterior glass window wall, specified that one of four named curtain wall manufacturers be used. (Section 08920, Part 2.1.A.)

{¶ 5} Plaintiff is a general contractor who bid on the general trades contract for the project. Prior to submitting any bids, plaintiff invited the Blakley Corporation ("Blakley") to bid as a subcontractor on furnishing and installing the curtain wall system for the project. Blakley requested the project manual prior to bidding the job. Blakley did not seek pre-bid approval to use a manufacturer other than those listed in the contract specifications, and its bid did not specify which curtain wall manufacturer it intended to use. In formulating its curtain wall bid, however, Blakley used a price quotation from United States Aluminum, who was not one of the curtain wall manufacturers specified in the contract and whose price quotation was considerably lower than that of the manufacturers named in the specifications. Blakely later explained it had "assumed" United States Aluminum was or would be approved for the curtain walls because it was a specified manufacturer for another component of the project. Blakley submitted the lowest bid for the work and, after plaintiff was deemed the lowest responsible bidder on the general trades contract, entered into a subcontract with plaintiff to furnish and install the curtain wall system.

{¶ 6} On being advised that Blakley intended to use the United States Aluminum curtain wall system rather than one of the manufacturers named in the contract specifications, Michael Dingeldein, the principal architect on the project for the project's architectural firm, expressed concern that Blakely had not sought pre-bid approval to use United States Aluminum's system. He also questioned whether the United States Aluminum system met the contract specifications.

{¶ 7} The architect met with Blakley and United States Aluminum on November 8, 2000, to determine if the United States Aluminum curtain wall system could meet the specifications for the project. Although Blakley and the manufacturer presented some drawings and information regarding the United States Aluminum product, the architect was unconvinced the proposed curtain wall system complied with the project's specifications. The architect nevertheless afforded Blakley an opportunity to present any additional materials on or before November 13, 2000, to show United States Aluminum's ability to meet the product specifications. Blakley failed to submit the additional information by November 13, 2000, as requested, but did fax some information on November 15, 2000, the day the school district, the architect, and the construction manager had a scheduled meeting to discuss the project. Despite its tardiness of submission, the architect reviewed the additional information Blakley submitted but remained unconvinced the proposed product complied with the contract specifications for the following reasons: (1) the proposed system would not have been fabricated and assembled at the manufacturer, as the specifications required, (2) the windows of the proposed system were of a lower rating or grade than the specifications, and (3) evidence did not show that the proposed system would be "thermally broken." The board accordingly rejected Blakley's use of the United States Aluminum curtain wall system on the project.

{¶ 8} Plaintiff subsequently filed the instant action on behalf of Blakley, alleging the board breached its contract with plaintiff, and accordingly with Blakley as its subcontractor, by wrongfully refusing to accept the United States Aluminum curtain wall system. The board moved for summary judgment contending (1) plaintiff failed to seek pre-bid approval of the United States Aluminum system as required by Sections 1.05 and 1.08 of the project manual's Instructions to Bidders, (2) plaintiff failed to carry its contractually imposed burden of convincing the architect that the United States Aluminum system met the curtain wall specifications, and (3) plaintiff should not be rewarded for using the quotation of an unspecified and unapproved manufacturer on the project where other bidders followed the rules and used the more expensive manufacturers listed in the specifications.

{¶ 9} The parties agreed a valid and enforceable contract existed, and the trial court determined it was memorialized in the project manual. Finding the contract and its terms to be clear and unambiguous, the trial court further found plaintiff failed to comply with the explicit provisions concerning pre-bid approval and substitution, as outlined in Sections 1.05 and 1.08 of the agreement's "Instructions to Bidders." Specifically, the trial court concluded that, although the contract required it, plaintiff did not seek pre-bid approval to substitute United States Aluminum as the curtain wall manufacturer in place of one of the four designated curtain wall manufacturers listed in the contract's product specifications. Concluding plaintiff had not substantially performed or tendered performance under the contract, the trial court ruled that plaintiff could not maintain an action for breach of contract against the board. The trial court accordingly granted summary judgment in favor of the board without addressing the remaining reasons the board advanced in support of summary judgment.

{¶ 10} Plaintiff appeals, asserting the trial court erred in construing the contract to require Blakley to seek pre-bid approval to use a curtain wall manufacturer not listed in the contract specifications. Plaintiff contends the trial court failed to give effect to other provisions in the contract that provide for post-bid approval of proposed substitutions.

{¶ 11} Appellate review of summary judgments is de novo, under which the appellate court stands in the shoes of the trial court and conducts an independent review of the record. Advanced Analytics Laboratories, Inc. v. Kegler, Brown, Hill Ritter, L.P.A.,148 Ohio App.3d 440, 2002-Ohio-3328, at ¶ 33.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coventry Township v. Ecker
654 N.E.2d 1327 (Ohio Court of Appeals, 1995)
McConnell v. Hunt Sports Enterprises
725 N.E.2d 1193 (Ohio Court of Appeals, 1999)
Allied Erecting & Dismantling Co. v. Uneco Realty Co.
765 N.E.2d 420 (Ohio Court of Appeals, 2001)
Luntz v. Stern
20 N.E.2d 241 (Ohio Supreme Court, 1939)
Thomas v. Matthews
113 N.E. 669 (Ohio Supreme Court, 1916)
Security Sewage Equipment Co. v. McFerren
237 N.E.2d 898 (Ohio Supreme Court, 1968)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)
Worth v. Huntington Bancshares, Inc.
540 N.E.2d 249 (Ohio Supreme Court, 1989)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Vahila v. Hall
674 N.E.2d 1164 (Ohio Supreme Court, 1997)
State ex rel. Grady v. State Employment Relations Board
677 N.E.2d 343 (Ohio Supreme Court, 1997)
Geis Construction Co. v. Board of Education
131 N.E.2d 878 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
corna/kokosing v. South-Western City, Unpublished Decision (12-19-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornakokosing-v-south-western-city-unpublished-decision-12-19-2002-ohioctapp-2002.