Corinno Civetta Construction Corp. v. City of New York

493 N.E.2d 905, 67 N.Y.2d 297, 502 N.Y.S.2d 681, 1986 N.Y. LEXIS 18058
CourtNew York Court of Appeals
DecidedMay 6, 1986
StatusPublished
Cited by393 cases

This text of 493 N.E.2d 905 (Corinno Civetta Construction Corp. v. City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corinno Civetta Construction Corp. v. City of New York, 493 N.E.2d 905, 67 N.Y.2d 297, 502 N.Y.S.2d 681, 1986 N.Y. LEXIS 18058 (N.Y. 1986).

Opinion

OPINION OF THE COURT

Simons, J.

In Kalisch-Jarcho, Inc. v City of New York (58 NY2d 377), we reaffirmed the rule that contract clauses barring a contractor from recovering damages for delay in the performance of a contract are valid, that they will prevent recovery of damages resulting from a broad range of reasonable and unreasonable conduct by the contractee if the conduct was contemplated by the parties when they entered into the agreement, but that they will not excuse or prevent the recovery of damages resulting from the contractee’s grossly negligent or willful conduct, i.e., conduct which "smacks of intentional wrongdoing” (supra, at p 385). The common legal issue in the four appeals now before us is whether that standard is applicable when the delays caused by the contractee were not contemplated at the time the parties entered into the contract. The Appellate Division, First Department, interpreted the Kalisch-Jarcho decision as holding that the city’s no-damage-for-delay clause barred contractors from recovering [306]*306damages for all delays, contemplated or uncontemplated, and it dismissed the complaint in each action. Our decision in Kalisch-Jarcho did not decide the issue, however, nor did it change the existing rule which provides that damages resulting from uncontemplated delays caused by the contractee may be recovered despite the existence of a broad exculpatory clause relieving the contractee from liability. We now reaffirm that rule. Thus, although we agree with the Appellate Division’s conclusions that plaintiffs in Corinno Civetta and Honeywell failed to establish a prima facie case of liability against the city and that their causes of action for delay damages should be dismissed, we differ with its reasoning. In Catapano and Nab-Tern, however, the city’s moving papers are insufficient to warrant relief and the motions for summary judgment should have been denied.

I

The claim of Corinno Civetta arises out of a contract by which plaintiff was to reconstruct and install approximately 245 feet of combined sewer beneath the west side of Central Park between West 61st Street and Columbus Circle at a price of $207,061. The contract was executed on September 13, 1979 and by its terms was to be completed within 100 consecutive days. Work began on October 1, 1979 but was not completed until December 1980. Plaintiff brought this action seeking to recover various items of damage including damages of $162,-343 resulting from actions by the city which it alleges delayed the project. Trial Term denied the city’s motion for partial summary judgment dismissing the cause of action for delay damages and granted plaintiff’s cross motion for partial summary judgment on the remaining causes of action. The city appealed only the denial of its motion and the Appellate Division reversed, granted the motion, and dismissed the cause of action for delay damages (107 AD2d 610). The remaining causes of action have been settled, thus presenting a final order for review.

In Catapano plaintiff is seeking damages in the amount of $1,850,000 for delays in completing its contract to construct certain sewers in Queens which allegedly were caused by the city. The parties executed the contract in June 1977 for a total contract price in excess of $3,850,000 and work was to commence on August 8, 1977. Sewer construction was scheduled to be completed by September 21, 1978 and street resto[307]*307ration was to be accomplished within an additional 100 consecutive days. The project was not finished, however, until March 2, 1980. The city’s motion for summary judgment dismissing the complaint, or alternatively to strike the complaint under CPLR 3126 for failure to answer interrogatories, was denied by Special Term. On appeal, the Appellate Division modified by granting the city’s motion for summary judgment to the extent of dismissing the second cause of action for delay damages and otherwise affirmed (107 AD2d 640). The parties have stipulated to discontinue the remaining causes of action with prejudice.

The claim in Honeywell arises out of a contract for the installation and maintenance of a system of instrumentation and data logging equipment at the city’s sewage treatment plants at Rockaway, Jamaica, Bowery Bay, and Tallman’s Island at a price of $1,600,000. The contract was executed in August 1973 and provided that installation of the equipment was to be completed in three and one-half years, by February 1977, and that thereafter plaintiff would maintain the system at each of the four plant locations for an additional two years. Plaintiff terminated work at all plants in February 1979, the date originally scheduled for completion of all its contract obligations, with the installation work unfinished. It instituted this action in 1981 seeking damages on a quantum meruit basis for $1,342,000, which represented the difference between what it claimed was the reasonable value of the work performed and the payments already received. The city counterclaimed for the cost of completing the system and consequential damages, alleging abandonment and breach of contract by plaintiff. Following a trial, the jury returned a verdict in favor of plaintiff and against the city for $1,225,845 and judgment was entered on the verdict. The city’s counterclaims were dismissed. The Appellate Division reversed the judgment, dismissed plaintiff’s complaint and affirmed the order dismissing the city’s counterclaims (108 AD2d 125).

The contract in Nab-Tern required plaintiff to perform services as general contractor for the reconstruction of Yankee Stadium at a price of $22,220,000. By its terms, work was to commence on January 11, 1974 and be completed by February 6, 1976. The project was not finished until April 14, 1976. Plaintiff brought this action in 1978 alleging several causes of action including one for delay damages totaling $5,744,267. Special Term denied the city’s motion for partial summary judgment dismissing the fourth cause of action for [308]*308delay damages and granted plaintiff’s cross motion to amend its complaint to allege willful misconduct and gross negligence by defendant in the cause of action for delay damages. The Appellate Division reversed, granted the city’s motion and denied plaintiff’s cross motion (111 AD2d 56). The court then granted plaintiff leave to appeal to this court on a certified question.

Plaintiffs present three legal issues.

First, all four plaintiffs contend that the Appellate Division erred in dismissing their claims for delay damages on the basis of the exculpatory clause contained in the contracts. This is so, they claim, (a) because the rule set forth in Kalisch-Jarcho does not apply to uncontemplated delays and the court failed to consider whether the delays in question were contemplated or uncontemplated, and (b) because even if it is contended that the delays were contemplated when the parties entered into the contracts there are factual questions which must be decided to resolve that issue and to resolve whether the city’s conduct in causing the delays amounted to willful misconduct, bad faith or gross negligence. For its part, the city asserts that under the broad exculpatory clause contained in the contracts, all claims for delay damages are barred unless deliberate and intentional misconduct is established.1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tutor Perini Corp. v. State Univ. Constr. Fund
2025 NY Slip Op 52062(U) (New York Supreme Court, Albany County, 2025)
Henick-Lane, LLC v. Stellar Mgt. Group, Inc.
2025 NY Slip Op 05190 (Appellate Division of the Supreme Court of New York, 2025)
Dematteis/Darcon v. City of New York
2025 NY Slip Op 31516(U) (New York Supreme Court, New York County, 2025)
AWL Indus., Inc. v. New York City Hous. Auth.
2025 NY Slip Op 02402 (Appellate Division of the Supreme Court of New York, 2025)
Facade Tech., LLC v. CNY Constr. 701 LLC
2025 NY Slip Op 02034 (Appellate Division of the Supreme Court of New York, 2025)
Matter of Owen Steel Co., Inc. v. City Univ. of N.Y.
2025 NY Slip Op 00920 (Appellate Division of the Supreme Court of New York, 2025)
E.W. Howell Co., LLC v. Hill Intl., Inc.
2025 NY Slip Op 00719 (Appellate Division of the Supreme Court of New York, 2025)
Graciano Corp. v. Lanmark Group, Inc.
2023 NY Slip Op 05703 (Appellate Division of the Supreme Court of New York, 2023)
Five Star Elec. Corp. v. Silverite Constr. Co., Inc.
2023 NY Slip Op 05224 (Appellate Division of the Supreme Court of New York, 2023)
Lanmark Group, Inc. v. New York City Sch. Constr. Auth.
214 A.D.3d 524 (Appellate Division of the Supreme Court of New York, 2023)
Matter of Tutor Perini Corp. v. City of N.Y. Off. of Admin. Trials & Hearings Contract Dispute Resolution Bd.
2021 NY Slip Op 02620 (Appellate Division of the Supreme Court of New York, 2021)
Five Star Elec. Corp. v. Trustees of Columbia Univ.
2020 NY Slip Op 07493 (Appellate Division of the Supreme Court of New York, 2020)
Federated Fire Protection Sys. Corp. v. 56 Leonard St., LLC
2020 NY Slip Op 06348 (Appellate Division of the Supreme Court of New York, 2020)
Federated Fire Protection Sys., Corp. v. Extell W. 57th St., LLC
2020 NY Slip Op 05134 (Appellate Division of the Supreme Court of New York, 2020)
Framan Mech., Inc. v. State Univ. Constr. Fund
2020 NY Slip Op 2510 (Appellate Division of the Supreme Court of New York, 2020)
WDF Inc. v. Turner Constr. Co.
2019 NY Slip Op 8379 (Appellate Division of the Supreme Court of New York, 2019)
Arnell Constr. Corp. v. New York City Sch. Constr. Auth.
2019 NY Slip Op 7887 (Appellate Division of the Supreme Court of New York, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
493 N.E.2d 905, 67 N.Y.2d 297, 502 N.Y.S.2d 681, 1986 N.Y. LEXIS 18058, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corinno-civetta-construction-corp-v-city-of-new-york-ny-1986.