People Ex Rel. Wells Newton Co. v. . Craig

133 N.E. 419, 232 N.Y. 125, 1921 N.Y. LEXIS 484
CourtNew York Court of Appeals
DecidedNovember 22, 1921
StatusPublished
Cited by51 cases

This text of 133 N.E. 419 (People Ex Rel. Wells Newton Co. v. . Craig) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
People Ex Rel. Wells Newton Co. v. . Craig, 133 N.E. 419, 232 N.Y. 125, 1921 N.Y. LEXIS 484 (N.Y. 1921).

Opinion

Hogan, J.

October 25th, 1915, relator entered into a contract with the board of education of the city of New York, through its committee on buildings, for the installation of a heating and ventilating apparatus in Evander Childs High School, borough of The Bronx, New York city, the same to be completed within one hundred twenty days.

Due to defaults of contractors having in charge the construction of the building, relator was prevented from proceeding with the work under its contract within the time prescribed therein, and for a period of upwards of two years subsequent thereto. About June, 1918, the relator still deprived of opportunity to complete its contract, appreciating that the continued defaults on *129 the part of the city had resulted in serious damages to it, announced to the board of education that it refused to continue the work under its contract and refused to longer be bound thereby unless the city and board of education would enter into a binding agreement with it to pay its claim then and theretofore asserted by it for extra expense incidental to the delays caused it in the carrying out of the contract in the previous prosecution of the work thereunder and in completion of the further work covered thereby.

July 3d, 1918, the vice-president of the board of education addressed a communication to the attorney for relator in which he stated that no disposition existed on the part of the board of education to treat the situation other than with a spirit of fairness to relator, but in so doing it was essential that the board should act with caution so as to preserve its rights against the sureties of defaulting construction contractors, further that he was prepared to submit a resolution to the board of education reciting the facts and complications that had arisen, providing for a continuation of the work by the relator under the terms of the then contract until completion, that the board of education acknowledged that the relator would have a claim for extra expenses incidental to the carrying out of the contract, the amount of which was not definable at that time, “ said extra expenses arise because of certain delays and the enhanced prices of labor and materials due to present day extraordinary conditions;” that' upon completion of the work to be performed under the existing contract the board of education will entertain a claim in detail and settle the same either (1) by agreement, (2) by arbitration, or (3) by judicial decision on agreed state of facts,. íf you will assent I will offer the requisite resolution.”

Upon receipt of such communication relator indorsed upon the same its acceptance of the terms proposed and *130 an agreement to immediately resume work. Thereafter and on the same day, July 3d, 1918, the board of education adopted a resolution, the preamble of which recited the contract of October 25th, 1915, between it and the relator; that relator had been paid thereon the sum of $50,823, leaving a balance of work in a state of performance or being performed amounting to $23,947; that completion of the work thereunder had been delayed by reason of the failure of the original construction contractor to perform the work required under his contract and such contractor had been declared in default and his contract terminated in the interest of the board; that the construction work had been relet three times due to defaults, and the interests of the board demand the completion of the High School building without further delay. The resolution adopted was in substance that work under the contract with relator be continued until completion; that the board of education acknowledges that- by reason of continuation of the contract by relator, the latter will have a claim for extra expense, the amount of which is not definable at this time, the said extra expense arising out of delays on the part of other contractors and the enhanced prices of labor and materials due to present day extraordinary conditions; that the board of education upon completion of the work required to be performed under the existing contract, will entertain a claim in detail and settle the' same by either one of the following methods: (1) By agreement; (2) by arbitration, or (3) by judicial decision on an agreed state of facts; that the work called for under the contract be proceeded with without delay under the direction of the superintendent of school buildings.

Relator thereupon resumed work under its contract and fully completed the same in May, 1920, notwithstanding additional delay caused by defaults of construction contractors, and thereupon employed two several certified public accountants to make an exami *131 nation and audit of its books of account relating to the contract with the board of education. The payrolls for labor, the bills for purchase of materials, etc., of relator were compared with its books and found to be correct and a detailed statement of the same rendered by the accountants to relator. The statement together with supporting tabulations or schedules of cost was submitted to the board of education.

The statement prepared by the accountants fixed the total direct cost to relator $105,480.69, plus overhead of $18,986.52, or a total of $124,467.21, and added thereto as a profit for doing the work ten per cent, amounting to $12,446.72, making in the aggregate $136,913.93.

In June following, the board of education requested and relator furnished to it affidavits of the public accountants who had made the examination and audit for relator. Such affidavits made reference to the statement already made and further stated that the rates and charges for labor and materials agreed with the rates and charges appearing on the payrolls, records and books of account of relator; that the rates charged for labor were the rates actually paid; that the prices charged for materials were the prices actually paid for the same; that no interest charges had been made for money used; that the profits and overhead expenses were reasonable. The affidavits were supported by an affidavit of the president of relator.

The claim was referred to the auditor of the board of education who made further inquiry as to correctness of the same. On July 12th one of the accountants made a further report to such auditor in which was contained a detailed statement of the wages paid by relator to various classes of mechanics during the various years from the time the work commenced in October, 1915, to the completion of the same in 1920. Accompanying the statement there was furnished the auditor of the board of education a detailed statement of rates of *132 compensation paid to mechanics, etc., which rates appeared in a schedule prepared by the Building Trades Association, also, a like statement furnished by Heating and Piping Contractors of the city of New York.

On July 22d, 1920, the auditor of the board of education submitted a report to the president of the board, in which he recited at length all the foregoing facts in detail and submitted all documents relating thereto, and stated that from the evidence which the bureau had secured, it seemed that the total direct cost plus overhead was $124,467.21, and plus 10% for profit, $136,913.93, and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kowalska v. Board of Education
260 A.D.2d 546 (Appellate Division of the Supreme Court of New York, 1999)
Corinno Civetta Construction Corp. v. City of New York
493 N.E.2d 905 (New York Court of Appeals, 1986)
Kalisch-Jarcho, Inc. v. City of New York
448 N.E.2d 413 (New York Court of Appeals, 1983)
Kush v. City of Buffalo
89 A.D.2d 786 (Appellate Division of the Supreme Court of New York, 1982)
Board of Education v. Nyquist
83 A.D.2d 217 (Appellate Division of the Supreme Court of New York, 1981)
H & J Floor Covering, Inc. v. Board of Education
66 A.D.2d 588 (Appellate Division of the Supreme Court of New York, 1979)
Board of Education v. Goldin
94 Misc. 2d 574 (New York Supreme Court, 1978)
Herbert G. Martin, Inc. v. City of Yonkers
54 A.D.2d 971 (Appellate Division of the Supreme Court of New York, 1976)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
New Again Construction Co. v. City of New York
76 Misc. 2d 943 (New York Supreme Court, 1974)
County of Erie v. Board of Trustees
62 Misc. 2d 396 (New York Supreme Court, 1970)
Peckham Road Co. v. State
32 A.D.2d 139 (Appellate Division of the Supreme Court of New York, 1969)
Kahn v. Becker
27 A.D.2d 436 (Appellate Division of the Supreme Court of New York, 1967)
Ace Stone, Inc. v. Township of Wayne
221 A.2d 515 (Supreme Court of New Jersey, 1966)
Lanza v. Wagner
183 N.E.2d 670 (New York Court of Appeals, 1962)
A. Kaplen & Son, Ltd. v. Housing Authority of Passaic
126 A.2d 13 (New Jersey Superior Court App Division, 1956)
Daniman v. Board of Education
119 N.E.2d 373 (New York Court of Appeals, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
133 N.E. 419, 232 N.Y. 125, 1921 N.Y. LEXIS 484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/people-ex-rel-wells-newton-co-v-craig-ny-1921.