Anthony P. Miller, Inc. v. Wilmington Housing Authority

165 F. Supp. 275, 1958 U.S. Dist. LEXIS 3679
CourtDistrict Court, D. Delaware
DecidedAugust 8, 1958
DocketCiv. A. 1739
StatusPublished
Cited by15 cases

This text of 165 F. Supp. 275 (Anthony P. Miller, Inc. v. Wilmington Housing Authority) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony P. Miller, Inc. v. Wilmington Housing Authority, 165 F. Supp. 275, 1958 U.S. Dist. LEXIS 3679 (D. Del. 1958).

Opinion

LAYTON, District Judge.

The matter in dispute here arises out of a written contract for the construction by the plaintiff of two extensive low rent housing developments, known as Southbridge Extension and Eastlake Extension.

Under the provisions of 31 Del.C. § 4317, the Wilmington HousingAuthority advertised for bids. Paragraph 15 of the instructions to bidders contained the following clause:

“a. The Contracts will be awarded to the responsible bidders submitting the lowest proposal complying with the conditions of the Invitation for Bids, providing his bid is reasonable and it is to the interest of the Local Authority to accept it. * * * The Local Authority, however, reserves the right to reject any and all bids and to waive any informality in bids received whenever such rejection or waiver is in the interest of the Local Authority.”

*277 The bids for both the Southbridge Extension and Eastlake Extension were ■opened on March 12, 1952. Plaintiff was found to be the lowest bidder on the general construction with a price of $1,735,000. James Julian was found to be the lowest bidder for the demolition, .site work and utilities, with a price of $136,736.75. Between the time of the opening of the bids and the awarding of the contract, the Commissioners of the Wilmington Housing Authority received protests from representatives of organized union labor of New Castle County against the award of a contract to this plaintiff, one of the reasons being that although it was a union contractor in its .home town in New Jersey, experience bad shown that it had operated an open, nr non-union, shop on jobs in this county. On March 24, 1957, the Authority awarded the general construction contracts to the plaintiff, and the contracts for demolition, site work and utilities to James Julian.

The following provisions of the contract are important and appear in both the Southbridge Extension and Eastlake Extension contracts.

“5. Other Contracts
“The Local Authority may award other contracts for additional work, and the Contractor shall fully cooperate with such other contractors and carefully fit his own work to that provided under other contracts as may be directed by the Local Authority. The Contractor shall not commit or permit any act which will interfere with the performance of work by any other contractor.
“Where more than one prime contractor is employed on the site it shall be the responsibility of the Local Authority to coordinate the work of all such prime contractors unless otherwise expressly provided herein.” (My emphasis)
*****
“13. Delays — Damages
“a. * * * Provided, That the right of the Contractor to proceed shall not be terminated or the Contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, or of the public enemy, acts of the Government, acts of the Local Authority, acts of another contractor in the performance of a contract with the Local Authority, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes, if the Contractor shall within 10 days from the beginning of any such delay (unless the Local Authority, with the approval of the PHA, shall grant a further period of time prior to the date of final settlement of the Contract) notify the Contracting Officer in writing of the causes of delay, who shall ascertain the facts and the extent of delay, and the Local Authority shall, subject to prior approval of the PHA, extend the time for completing the work when in its judgment the findings of fact of the Contracting Officer justify such an extension, and his findings of fact thereon shall be final and conclusive upon the parties hereto. (My emphasis)
“b. No payment or compensation of any kind shall be made to the Contractor for damages because of hindrance or delay from any cause in the progress of the work, whether such hindrances or delays be avoidable or unavoidable.”
* * * * * *
“20. Requests for Supplementary Information
“a. It shall be the responsibility of the Contractor to make timely requests of the Architect, through the Local Authority, for such large scale and full size drawings, color schemes, and other additional information, not already in his pos *278 session, which he will require in the planning and production of the work. Such requests may be submitted from time to time as the need is approached, but each such request shall be filed in ample time to permit appropriate action to be taken by all parties involved so as to avoid delay. Each request shall be in writing, and shall list the various items and the latest date by which each will be required by the Contractor. The first list shall be submitted within two weeks after Contract award and shall be as complete as possible at that time. The Contractor shall, if requested, furnish promptly any assistance and information which the Architect may require in responding to the requests of the Contractor. The Contractor shall be fully responsible for any delay in his work or to others arising from his failure to comply fully with the provisions of this Section.
“b. The Local Authority shall coordinate these activities between its Architect and the Contractor and shall expedite the flow of information so as to minimize delay in the progress of the development.”

A brief reference to the pleadings is necessary. The complaint contains five causes of action; the first cause is not challenged by this motion.

The second cause of action deals exclusively with the contract for Eastlake Extension, alleging that defendant breached its contract in the following ways:

1. Defendant breached its covenant to coordinate the work of all prime contractors on the Eastlake Extension project, in that:
a. Defendant knew that nonunion and union laborers could not work side by side on building projects in New Castle County without labor disturbances.
b. Defendant awarded a prime contract to James Julian, a nonunion contractor, on the Eastlake Extension project which was to be performed concurrently with plaintiff’s prime contract on the same project.
c. As a result, a strike of plaintiff’s and its subcontractors’ union laborers occurred on the Eastlake Extension project and lasted for a period of 54 days. Plaintiff suffered damage consisting of increased overhead costs, increased labor costs, increased labor and material costs of its subcontractors, and clean up and maintenance work. The amount claimed is $261,797.11.
2. Defendant breached its contract as to Eastlake Extension in that:
a. It failed to maintain an authorized and responsible representative at the project site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Education v. Beka Industries, Inc.
989 A.2d 1181 (Court of Special Appeals of Maryland, 2010)
Calumet Const. Corp. v. Metro. Sanitary Dist. of Greater Chicago
581 N.E.2d 206 (Appellate Court of Illinois, 1991)
State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)
Owen Construction Co. v. Iowa State Department of Transportation
274 N.W.2d 304 (Supreme Court of Iowa, 1979)
Image Carrier Corp. v. Beame
430 F. Supp. 579 (S.D. New York, 1977)
J. A. Jones Construction Co. v. City of Dover
372 A.2d 540 (Superior Court of Delaware, 1977)
Unicon Management Corp. v. City of Chicago
404 F.2d 627 (Seventh Circuit, 1968)
Daniel B. Van Campen Corp. v. Building & Construction Trades Council
195 A.2d 134 (Superior Court of Pennsylvania, 1963)
Lichter v. Mellon-Stuart Co.
196 F. Supp. 149 (W.D. Pennsylvania, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
165 F. Supp. 275, 1958 U.S. Dist. LEXIS 3679, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthony-p-miller-inc-v-wilmington-housing-authority-ded-1958.