City of Orlando v. Murphy

84 F.2d 531, 1936 U.S. App. LEXIS 4524
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 15, 1936
Docket8048
StatusPublished
Cited by25 cases

This text of 84 F.2d 531 (City of Orlando v. Murphy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Orlando v. Murphy, 84 F.2d 531, 1936 U.S. App. LEXIS 4524 (5th Cir. 1936).

Opinion

HOLMES, Circuit Judge.

This was a suit for damages in the sum of $800,000 resulting, as alleged, from the breach of a contract with reference to an extensive paving program contemplated for certain streets in the city of Orlando, Fla. It was filed against the city by the appellee, as assignee of the contractors. The declaration was in nine counts. After a demurrer based on twenty-seven grounds was overruled, pleas were filed in sets; the first consisting of thirty pleas, the second of two dozen, and yet another of thirteen. Sets of pleas were met by demurrers and motions to strike, and, finally, the issues remaining were submitted to a jury, which returned a verdict for the plaintiff. Upon appeal by the city, the petition therefor contained two hundred and forty-four assignments of error, which have been classified and reduced in this court to twenty-four specifications. As we think the case turns upon a construction of the contract, we shall state in our own way the essential facts upon which our decision is based without attempting to deal separately with the numerous assignments argued by the parties. In so doing, we shall assume the validity of the contract, although it is assailed by the city on the ground of ultra vires, (1) because the assessment should be against the abutting property and not upon the abutting property owners, and (2) because, before the total costs of the improvement can legally be assessed against the abutting property, there must be a determination by the city council of the benefits to the particular property. Citing Atlantic Coast Line R. Co. v. City of Lakeland, 94 Fla. 347, 115 So. 669; Brown v. City of St. Petersburg, 111 Fla. 718, 153 So. 140, 141. A decision of these questions is unnecessary in view of the construction we have placed upon the contract. Owing to the course of the pleadings, we shall also pretermit rulings upon several other questions raised' in the.’ briefs.

The contract was made on' October 10, 1925, under authority- of an Act of the Legis- *533 Iature of the State of Florida, the principal purpose of which was to provide an additional method of financing local improvements by the city of Orlando. Chapter 10974 (No. 952), Laws of Florida, Special Acts of 1925, vol. 2, pp. 3468-3478. Under the act, the city was authorized to make improvements to its streets and alleys, to be paid for, wholly or in part, by the property owners thereby benefited. It was authorized to issue bonds to an amount not exceeding 70 per centum of the estimated cost, pledging its faith and credit for the payment of the bonds; the amount of the costs to be raised by special assessments against the property. In the event these assessments were not collected sufficiently to pay the principal and interest on the bonds, the amount thereof was to be levied and collected as a general tax, provided the aggregate of bonds payable by general taxation should not exceed the amount of the unpaid assessments. The act permitted a sale of the bonds, but provided that they should not be delivered except as the work progressed (section 1). Originally the bonds could be sold at not less than par (section 7), but subsequently the act was amended to allow their sale at 95 cents on the dollar (Acts Fla. 1925 Ex. Sess., c. 11661, § 2). The proceeds derived from the sale of the bonds and from the prompt payment of all special assessments were to constitute a fund for the payment of any contract made under the act, and said fund was to be used to pay for the work as it progressed, was completed, and accepted.

Proceeding under authority of the act, the city council of Orlando, on August 15, 1925, adopted a resolution that it was to the best interests of the city to make the improvements mentioned therein; instructed the clerk to advertise for bids from contractors for the work and materials; and provided that the improvements be made wholly at the cost of the property owners thereby benefited. Advertisement having been made, the council voted to award a contract to Murphy & Prior, assignor of appellee, for the construction of paving, curbing, and gutters at an estimated cost of $2,769,881.50. On October 10, 1925, the council approved the form of the contract to be made, and authorized the mayor and clerk to execute the same, which was done. On October 14, by resolution, the council estimated the total cost of the improvements to be covered by the contract at $2*927,000, and provided that all of said amount be assessed against the property benefited by the improvements. On November 24, 1925, in a proceeding instituted for that purpose, a final decree was entered validating the issuance of $2,050,000 of bonds, or 70 per centum of the estimated total cost. Under the law, the remaining bonds (30 per cent.) necessary to pay the cost were to be issued upon “final completion” of the work, less the amount of such special assessments as had been levied and collected in the meantime. The aggregate of the bonds for which the full faith and credit of the city might be pledged was expressly forbidden to exceed the amount of the unpaid assessments. Other debts to be paid by general taxation were not authorized by the act. In order that benefits and bonded indebtedness should proceed pari passu, it was provided that bonds should not be delivered except as the work progressed. Section 1.

By the terms of the contract thus entered into, the city agreed to pay 85 per cent, of the value of the completed work and materials furnished by the contractors, reserving 15 per cent, as partial security for the faithful performance of the contract. The supervision of the execution of the contract was vested wholly in the city engineer, who was authorized to increase or decrease the approximate quantities of work and materials, given in the instructions to bidders, which were stipulated in the contract to be merely for the comparison of bids. If such alterations increased or diminished the quantities, the contract rates were to be paid' for the actual quantities used. The contractors agreed to furnish and deliver all materials, and to do and perform all the work, in strict conformity to the specifications which were made a part of the contract. They were to commence work within four weeks from the date thereof and to prosecute it diligently without avoidable interruption so as to complete the program within the period of two years named in the proposal. A failure in this respect gave the city the option to abrogate the contract. If the work were not finished within the time named, the contractors would forfeit to the city from the final payment of 15 per cent, such reasonable engineering expenses as were incurred by reason of the delay. In case of delay attributable to any act or neglect of the city, the period' allowed to do the work was extended for a corresponding length of time. The duty to indicate the points of beginning and order of procedure of the work, so as to keep the contractors fully employed, was devolved upon the engineer, who was also requir *534 ed to determine the amount, quality, and acceptability of the work and materials, and to determine all questions or differences of opinion that might arise as to the interpretation of the plans and1 specifications. The plans and drawings prepared by the engineer “for the work when contemplated,” or which might thereafter be prepared in accordance with the agreement, “showing more particularly the work to be done,” were stipulated to be the controlling part of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JRD Management Corp. v. Dulin
883 So. 2d 314 (District Court of Appeal of Florida, 2004)
F.M. v. Palm Beach County
912 F. Supp. 514 (S.D. Florida, 1995)
K.L. Conwell Corp. v. City of Albuquerque
802 P.2d 634 (New Mexico Supreme Court, 1990)
Goldbloom v. JI KISLAK MORTG. CORP.
408 So. 2d 748 (District Court of Appeal of Florida, 1982)
Police Protective Ass'n of Casper v. City of Casper
575 P.2d 1146 (Wyoming Supreme Court, 1978)
Shuford Development Company v. Chrysler Corporation
449 F.2d 429 (Fifth Circuit, 1971)
Southern Gulf Utilities, Inc. v. Boca Ciega Sanitary District
238 So. 2d 458 (District Court of Appeal of Florida, 1970)
St. Regis Paper Company v. Aultman
280 F. Supp. 500 (M.D. Georgia, 1967)
Cunningham Brothers, Inc. v. City of Waterloo
117 N.W.2d 46 (Supreme Court of Iowa, 1962)
Housing Authority of City of Dallas v. Hubbell
325 S.W.2d 880 (Court of Appeals of Texas, 1959)
Lynn W. Storm and Maxine Storm v. United States
243 F.2d 708 (Fifth Circuit, 1957)
United States v. E. C. Nickel
243 F.2d 924 (Tenth Circuit, 1957)
United States v. Gordon
205 F.2d 658 (Fifth Circuit, 1953)
Northern Pac. Ry. Co. v. United States
70 F. Supp. 836 (D. Minnesota, 1946)
State Ex Rel. Watson v. Dade County Roofing Co.
22 So. 2d 793 (Supreme Court of Florida, 1945)
In re Central of Georgia Ry. Co.
47 F. Supp. 786 (S.D. Georgia, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
84 F.2d 531, 1936 U.S. App. LEXIS 4524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-orlando-v-murphy-ca5-1936.