K.L. Conwell Corp. v. City of Albuquerque

802 P.2d 634, 111 N.M. 125
CourtNew Mexico Supreme Court
DecidedNovember 26, 1990
Docket18984
StatusPublished
Cited by12 cases

This text of 802 P.2d 634 (K.L. Conwell Corp. v. City of Albuquerque) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K.L. Conwell Corp. v. City of Albuquerque, 802 P.2d 634, 111 N.M. 125 (N.M. 1990).

Opinions

OPINION

SOSA, Chief Justice.

On January 11, 1990, the trial court granted the City of Albuquerque’s (City) motion for summary judgment and denied K.L. Conwell Corporation’s (Conwell) equivalent motion. Conwell appeals, seeking reversal of the denial of its motion insofar as liability for breach of contract is concerned and a trial insofar as damages are concerned.

I. FACTS

The undisputed facts leading to the trial court’s ruling and pertinent to this appeal are as follows:

On October 5, 1988, the City issued an advertisement for bids for the construction of the Loma Linda Community Center. By the terms of the bid proposal, sealed bids were to be opened on November 1. Bids were deemed irrevocable for 45 days after the bid opening date. The City was to make an award on the bids within 30 days from the bid opening date, unless the City and an offeror agreed to extend the City’s time for acceptance of a bid beyond the 30-day period. The bid proposal also specified that the offeror had to deliver within 10 days of notification of acceptance by the City of the offeror’s bid, certain documents to the City’s architect. One of these documents pertained to certificates of insurance. The architect was designated by the City to draft the bid proposal specifications and to interpret the requirements of bid documents.

The bid proposal specified that the Subcontractors Fair Practices Act, NMSA 1978, Sections 13-4-31 to -43 (Repl.Pamp. 1988 and Cum.Supp.1990) (the Act), was to be incorporated into the construction contract as Section 8, paragraphs A-H. Paragraph G of Section 8 reads, in pertinent part, as follows:

In the event a hearing is required pursuant to the provisions of the Subcontractors Fair Practices Act and a delay in the work is caused as a result of a subcontractor protesting its substitution, the CONTRACTOR shall not be entitled to an increase in the Contract Sum or Contract Time.

Conwell submitted a sealed bid on November 1. The City and Conwell then agreed to extend to December 8 the time for the City to make an award to Conwell. On December 8, Conwell received an award letter from the City, which provided in pertinent part as follows:

You are hereby notified that the contract for construction of the above referenced project has been awarded to your company * * *. As provided in the Bid Proposal, you are required to execute and deliver each of [certain specified forms] * * * together with the same number of copies of the Certificates of Insurance and all other information and forms that are required by the Contract Documents to [the City’s architect], within ten (10) calendar days of receipt of this Notice of Award.
After the Agreement has been signed and the * * * Certificates of Insurance have been accepted by the City, an executed counterpart of the Contract Documents will be transmitted to you by the consultant. The consultant will prepare, have executed by the city, and deliver to you a Notice to Proceed on the project at the pre-construction conference.

An addendum to the letter award provided, in pertinent part:

One actual original Policy and 6 copies of “Owner’ [sic] and Contractors’ Protective Liability” insurance policy must be included. Coverage must be in an amount not less than $500,000 and must include the City and the Engineering Firm as “Named Insured”. (Architectural Firms do not need to be included as “Named Insured”).

On December 16, eight calendar days after receipt of the letter award, Conwell delivered to the City’s architect the necessary forms along with the certificates of insurance. The architect noted that he had not been named as an insured and asked Conwell to correct the certificate of insurance to include the architect. Conwell did so, returning the certificate to the architect on December 19. Saturday and Sunday fell on December 17 and 18, respectively. By the terms of the bid proposal the 45-day period for bid irrevocability expired on December 16. The City notified Conwell to attend the pre-construction conference scheduled for December 22, and Conwell complied.

Between December 16 and 22, Conwell on three occasions submitted three separate requests to substitute subcontractors on the project. According to the provisions of the Act, subcontractors to be substituted are entitled to notice and hearing, NMSA 1978, Sections 13-4-36, to -43, in order to protest the substitution. According to paragraph 8-G of the contract, quoted above, should such hearings cause a delay, Conwell could not obtain additional time for performance or additional monies for performance of the contract.

On December 27, the City asked Conwell to agree to extend the time for bid irrevocability to January 30, 1989. On January 3, 1989, Conwell responded to the City’s request by asking the City to waive paragraph 8-G of the contract. On January 23, 1989, Conwell received a letter from the City withdrawing its notice of award. The letter stated, in pertinent part:

In essence, the City cannot accept a counter-proposal to the stated terms and conditions of the original contract * * *. The City does not agree to waive [paragraph 8-G] and is therefore unwilling to enter into contract with your firm. In addition you failed to timely submit the correct and complete contract documents with your signature.

Therefore, the City hereby withdraws the previously issued Notice of Award for this contract to K.L. Conwell Corporation.

II. ARGUMENTS ON APPEAL

Conwell’s contentions on appeal are as follows: A legally binding contract was formed on December 8, with Conwell’s receipt of the award letter. Delivery of the various forms and the certificate of insurance to the architect within ten days of December 8 was, in Conwell’s language, a “condition subsequent.” Conwell delivered these documents to the City’s architect on December 16. Thus the so-called condition subsequent was satisfied.

The fact that Conwell had to correct the certificate of insurance was the City’s fault in stating in the award notice that the architect did not have to be named. Thus Conwell’s delivery of the corrected certificate on December 19 was not a failure of the “condition subsequent.” Further, December 18 fell on a Sunday, and Conwell thus had until Monday, December 19, to deliver all documents to the architect, regardless of its correction of the certificate.

Conwell further alleges that its three requests to substitute subcontractors after award of the contract do not constitute a repudiation of the contract. The Act, Con-well points out, explicitly provides for substitution of subcontractors. Nor, Conwell contends, was its request to the City to waive paragraph 8-G of the contract a repudiation of the contract. According to Conwell, it was simply trying to bargain with the City after the City had asked for an extension of time.

Conwell contends that the City erroneously assumed that it was barred by the Act from waiving paragraph 8-G. Conwell points out that there is no requirement similar to paragraph 8-G in the Act and that the City had the prerogative to waive the paragraph.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jay Dee/Mole Joint Venture v. Mayor & City Council
725 F. Supp. 2d 513 (D. Maryland, 2010)
Potter v. PATTERSON UTI DRILLING CO.
2010 NMCA 042 (New Mexico Court of Appeals, 2010)
Gregory Rockhouse Ranch, L.L.C. v. Glenn's Water Well Service, Inc.
2008 NMCA 101 (New Mexico Court of Appeals, 2008)
Ry-Tan Construction, Inc. v. Washington Elementary School District No. 6
93 P.3d 1095 (Court of Appeals of Arizona, 2004)
Gl Capasso Res. v. West Haven Hsg. Auth., No. Cv98-00636525 (Nov. 29, 1999)
1999 Conn. Super. Ct. 14827 (Connecticut Superior Court, 1999)
G L Capasso Res. v. West Haven Hsg., No. Cv98-00636525 (Nov. 24, 1999)
1999 Conn. Super. Ct. 15520 (Connecticut Superior Court, 1999)
Famiglietta v. Ivie-Miller Enterprises, Inc.
1998 NMCA 155 (New Mexico Court of Appeals, 1998)
Wisznia v. State, Human Services Dept.
1998 NMSC 011 (New Mexico Supreme Court, 1998)
Fuentes v. Santa Fe Public Schools
896 P.2d 494 (New Mexico Court of Appeals, 1995)
Planning & Design Solutions v. City of Santa Fe
885 P.2d 628 (New Mexico Supreme Court, 1994)
Divine Construction Co. v. Ohio-American Water Co.
599 N.E.2d 388 (Ohio Court of Appeals, 1991)
K.L. Conwell Corp. v. City of Albuquerque
802 P.2d 634 (New Mexico Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
802 P.2d 634, 111 N.M. 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kl-conwell-corp-v-city-of-albuquerque-nm-1990.