Jay Dee/Mole Joint Venture v. Mayor & City Council

725 F. Supp. 2d 513, 2010 U.S. Dist. LEXIS 142131, 2010 WL 2948193
CourtDistrict Court, D. Maryland
DecidedJuly 26, 2010
DocketCivil JFM-08-1595
StatusPublished
Cited by14 cases

This text of 725 F. Supp. 2d 513 (Jay Dee/Mole Joint Venture v. Mayor & City Council) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jay Dee/Mole Joint Venture v. Mayor & City Council, 725 F. Supp. 2d 513, 2010 U.S. Dist. LEXIS 142131, 2010 WL 2948193 (D. Md. 2010).

Opinion

OPINION

J. FREDERICK MOTZ, District Judge.

Jay Dee/Mole Joint Venture (“JDM”) 1 sued the Mayor and City Council of Baltimore and the Baltimore City Department of Public Works 2 (“DPW”) (collectively “the City”) for damages arising from the City’s alleged breach of a public construction contract. The City counterclaimed for breach of contract, liquidated damages, and promissory estoppel. Both JDM and the City have moved for summary judgment on JDM’s claims and on the City’s counterclaims for breach of contract and liquidated damages. Discovery has been completed, and the parties have filed dis-positive motions. 3

*517 I.

In October 2006, the City issued a Notice of Letting seeking bids for the Lower Stony Run Interceptor Project (“LSR Project”) as governed by Sanitary Contract No. 839R (“Contract 839R”). (Def.’s Am. Answer, Aff. Defenses, and Counter Claims ¶ 11; Pl.’s Jay Dee/Mole Joint Venture’s Mot. for Summ. J. on Counts I and II of Pl.’s Compl. (“Pl.’s Mot.”), Ex. IB at NOL-1-2.) The LSR Project was to replace and construct thousands of feet of sewer lines. This work necessitated significant tunnel construction and excavation work, which required a “tunnel boring machine” (“TBM”) at a rental cost of around $1 million. (Pl.’s Mot., Ex. IB at NOL-2, CD-99-100; Mekkaoui Decl. ¶ 13.)

a.The LSR Project and Contract 839R

Contract 839R included hundreds of pages of rules, regulations, and specifications, a few of which are particularly relevant for these motions: {See generally Pl.’s Mot., Ex. IB.)

(1)Various Minority-Owned Business Enterprise and Women-Owned Business Enterprise participation requirements, including: {Id., Ex. IB at MWBE-1-2.)
a. Assigning ten percent of the work to City-certified MBE subcontractors and another ten percent to City-certified WBE subcontractors
b. Providing that “any unjustified failure to comply with MBE and WBE participation requirements is a material breach of contract”
c. Requiring submission of “copies of all executed agreements with the MBE and WBE firms .... prior to the issuance of a notice to proceed”
d. “The Minority and Women’s Business Opportunity Office must approve substitution of an MBE or WBE specified at bid opening. Any unjustified failure to comply with this requirement is a material breach of contract.” 4
(2) As the result of a consent decree with the U.S. Environmental Protection Agency, all work necessary for sewer functionality was required to be completed by February 28, 2009 (Pl.’s Statement of Undisputed Material Facts (“SUMF”) ¶ 10.) (The City eventually modified Contract 839R to push back this deadline to April 28, 2009)
(3) Obligating the contractor to “mobilize” prior to construction — that is, “furnish[ ] ... all work, materials and operations required for the assembly and setting up for the project, including but not limited to”: moving personnel to the project site, construction of the necessary sanitary facilities, obtaining permits, submitting plans and timetables to the engineer, etc. (PL’s Mot., Ex. IB at CD-1-2.)
a. “When the Contractor has established the necessary facilities as specified [in the mobilization requirements], fifty percent (60%) of the total bid price for [mobilization] will be payable on the first monthly estimate. The remaining fifty percent (50%) of the bid price shall be *518 pro-rated in equal monthly payments for the duration of the Contract.”
(4) Obligating the contractor to undertake certain preliminary steps before commencing work on the project, such as: (Id., Ex. IB at CD-1-2, SC-36.)
a. Mobilization (described above)
b. Attending an orientation with city officials, generally within three days of the Notice of Award
c. Drafting a “time-scaled network graphic” within fifteen days of the orientation
(5) Providing that “[cjosts incurred by the Contractor for insurance, bond, permit fees, royalties, security, mobilization, etc.,” when properly detailed in the schedule of payments and documented to the Engineer, shall be paid in the first monthly voucher (Id., Ex. 1C at §§ 10.04-8,10.04-76(d).)
(6) Creating “just cause” for annulment of the award — and if the award is annulled providing that the contractor shall forfeit the bid bond as liquidated damages — if the contractor fails to do the following within thirty days of being awarded the contract: (Id., Ex. IB at SC-14.)
a. Execute a formal contract
b. Furnish the Performance Bond
c. Provide all insurance policies (or certified copies)

On December 6, 2006, JDM submitted the lowest bid for the LSR Project at $40,856,259. The second lowest bidder was Carp Seca Corp. (“Carp Seca”). (Id., Ex. IE.) Within days, the Minority and Women’s Business Opportunity Office (“MWBOO”) determined that JDM’s bid complied with the Minority-Owned Business Enterprise (“MBE”) and Women-Owned Business Enterprise (“WBE”) (collectively “M/WBE”) participation requirements. (Id., Ex. 5E.)

Along with its bid, JDM deposited a $817,125 bond (two percent of its bid). According to a document entitled “Bid Bond” (“Bid Bond Document”), signed by JDM on November 29, 2006, the bond was to be returned to JDM under two sets of circumstances: (1) if JDM’s bid was rejected, or (2) if JDM’s bid was accepted and JDM “execute[d] and deliver[ed] a Contract ... (properly completed in accordance with said Bid), and ... furnish[ed] a bond for [its] faithful performance of said Contract ... and ... in all other respects perform[ed] the Agreement created by the acceptance of said bid.” (Defi’s Response to Pl.’s Mot. for Summ. J. and Def.’s Cross Mot. for Summ. J. (“Def.’s Mot.”), Ex. 7 at BB-1-2.)

JDM submitted dozens of pages detailing its bid. JDM enclosed Statements of Intent between JDM and the M/WBEs— including K-0 Construction, Inc. (“K-O”) and R & R Utility Contractors, Inc. (“R & R”) — with whom it had agreed to subcontract to comply with Contract 839R’s M/WBE requirements. JDM represented that its subcontract with K-0 would satisfy over ninety-five percent of the MBE requirement and that its subcontract with R & R would satisfy over ninety percent of the WBE requirement. All Statements of Intent required both JDM and the subcontractor to attest that they “agree[d] to enter into a contract for the work/service indicated above for the dollar amount or percentage indicated....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
725 F. Supp. 2d 513, 2010 U.S. Dist. LEXIS 142131, 2010 WL 2948193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jay-deemole-joint-venture-v-mayor-city-council-mdd-2010.