Bunting Graphics, Inc. v. The Whiting-Turner Contracting Company

CourtDistrict Court, D. Maryland
DecidedJanuary 23, 2025
Docket1:19-cv-02323
StatusUnknown

This text of Bunting Graphics, Inc. v. The Whiting-Turner Contracting Company (Bunting Graphics, Inc. v. The Whiting-Turner Contracting Company) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bunting Graphics, Inc. v. The Whiting-Turner Contracting Company, (D. Md. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

) BUNTING GRAPHICS, INC. ) d/b/a Bunting ARCHITECTURAL ) METALS, ) ) Plaintiff/Counter-Defendant, ) ) v. ) ) THE WHITING-TURNER ) Civil Action No. 19-cv-2323-LKG CONTRACTING COMPANY, ) ) Dated: January 23, 2025 Defendant/Counterclaimant. ) ) ) THE WHITING-TURNER ) CONTRACTING COMPANY, ) ) Third-Party Plaintiff, ) ) v. ) ) TRAVELERS CASUALTY AND ) SURETY COMPANY OF AMERICA, ) ) Third-Party Defendant. ) ) MEMORANDUM OPINION I. INTRODUCTION This civil action involves breach of contract, quantum meruit and unjust enrichment claims and counterclaims related to a subcontract for the construction of a high-rise, mixed use building located in Arlington, VA (the “Subcontract”), entered into by Plaintiff, Bunting Graphics, Inc. (“Bunting”), and Defendant, The Whiting-Turner Contracting Company (“Whiting-Turner”). See generally ECF Nos. 1 and 11. The Court held a five-day trial on the parties’ claims and counterclaims from March 18, 2024, to March 22, 2024. ECF Nos. 188, 189, 195, 197 and 199. Following the trial, the parties submitted post-trial briefs. ECF Nos. 212, 213, 214, 220, 221 and 222. The Court heard closing arguments on December 12, 2024. ECF No. 233. For the reasons set forth below, the Court CONCLUDES that: (1) Bunting materially breached the Subcontract, by: (a) failing to timely mobilize to the Project site in May 2018; (b) failing to complete the fabrication of the metal panels in September 2018; and (c) failing to make progress on, or complete, installation of these panels by September 2018 and by January 2019; (2) Whiting-Turner did not materially breach the Subcontract prior to Bunting’s material breaches; (3) Bunting is LIABLE to Whiting-Turner for its material breaches of the Subcontract; and (4) Travelers is also LIABLE to Whiting-Turner for Bunting’s material breaches of the Subcontract, up to the amount of $2,652,500.00. II. FINDINGS OF FACT A. Factual Background Overview Of The Case This case involves a dispute about which party breached the Subcontract for the construction of a high-rise, mixed use building located in Arlington, VA. In this regard, Bunting alleges that Whiting-Turner materially breached the Subcontract by, among other things: (1) wrongfully issuing defective design documents; (2) wrongfully terminating the Subcontract; (3) negligently managing the construction project at issue in this case; (4) interfering with Bunting’s and other subcontractors’ work on that project; (5) wrongfully issuing notices of default to Bunting for its work; (6) wrongfully supplementing Bunting’s work; and (7) failing to pay Bunting in a timely manner, or at all, for its work. See generally ECF No. 1. Whiting-Turner counters that it did not breach the Subcontract and argues that Bunting materially breached the Subcontract by, among other things: (1) failing to submit shop drawings for certain architectural louvers and metal panels; (2) failing to timely complete fabrication of metal panels; (3) failing to timely mobilize to the Project site to begin installation of the metal panels; (4) failing to timely progress installation of the metal panels; and (5) failing to complete installation of metal panels and other Subcontract deliverables. See ECF No. 11 at ¶¶ 6-35. In addition, Whiting-Turner asserts a counterclaim against Third-Party Defendant, Travelers Casualty and Surety Company of America (“Travelers”)—which issued a Performance Bond on behalf of Bunting for the construction project at issue—alleging that Travelers breached that Performance Bond by failing to perform its obligations under the Performance Bond. See id. at ¶¶ 36-42. The Court held a five-day trial on the issue of liability in March 2024. ECF Nos. 188, 189, 195, 197, 199. The Court makes the following findings of fact, based upon the evidence presented at trial: The Project Whiting-Turner is the general contractor under a construction contract with PL Pentagon, LLC (the “Owner”), to construct a high-rise, mixed-use building known as Pentagon Centre Building A, which is located in Arlington, Virginia (the “Project”). ECF No. 213 at 6. The Project is a 25-story building with one level of below-grade parking, one ground-level retail level, six above-grade parking levels, and 18 residential levels containing 440 units. Joint Ex. 1 at WHITINGTURNER008282 (Subcontract at 1); ECF No. 207 at 65:22-23 (testimony of Firas Abdelahad describing number of levels in the Project building); ECF No. 207 at 192:24-193:2 (testimony of John Maguire describing the Project); ECF No. 208 at 233:3-9 (testimony of Joshua Bunting describing residential and parking garage levels of the Project); ECF No. 210 at 192:17-19 (testimony of Eric Krahe describing Levels 8 to 25 of the Project). The Subcontract And Project Schedule In June 2017, Bunting and Whiting-Turner entered into the Subcontract, in the amount of $2,652,500.00, for Bunting to furnish labor, material, equipment and tools to perform the following three primary scopes of work for the Project: (1) thermoplastic core, or ACM panels (“metal panels”); (2) perforated metal screens; and (3) architectural louvers. Joint Ex. 1 at WHITINGTURNER008282 (describing the Subcontract’s subject) and WHITINGTURNER008289 (Subcontract at Art. 10, titled “Subcontract Amount”); ECF No. 208 at 204:10-15 (testimony of Joshua Bunting describing Bunting’s scope of work for the Project). Pursuant to the Subcontract, Bunting was to engineer and specially fabricate the metal panels that were customized for the Project and then install these metal panels. ECF No. 209 at 71:15-16 (testimony of Joshua Bunting stating that the panels were fabricated at Bunting’s facility because they could not store all 3,000 panels on site). A large majority of the 3,000 metal panels were to be installed on Levels 8 to 25 of the Project building. In addition, the perforated metal screens were to be installed on Levels 5 to 8 of the Project and the louvers were primarily to be installed at the ground level. ECF No. 207 at 67:5-9, 22-25 (testimony of Firas Abdelahad describing where the perforated metal screens were to be installed on the west elevation of the Project); ECF No. 209 at 37:4-5 (testimony of Joshua Bunting describing where architectural louvers were to be installed). Pursuant to the terms of the Subcontract, Whiting-Turner agreed to pay Bunting in accordance with the following terms: Payment of amounts due under the Subcontract, shall be made as follows: The Contractor shall, pay to the Subcontractor an amount equal to ninety percent (90%) or such higher percentage as required by applicable law of the value of the work performed by [Bunting] as determined by the Architect and approved by [Whiting- Turner] during any calendar month within fifteen (15) days after payment therefor has been received by [Whiting-Turner] from the Owner, or within such shorter period specified by applicable law, statute or regulation.” Joint Ex. 1 at WHITINGTURNER008284 (Subcontract at Art. 5(a), titled “Payment”); ECF No. 209 at 62:20-63:1 (testimony of Joshua Bunting describing Art. 5(a) of the Subcontract). The Subcontract also required that Whiting-Turner pay Bunting “within 45 days” of the date of each Bunting Payment Application. Joint Ex. 1 at WHITINGTURNER008284 (Subcontract at Art. 5(a)), WHITINGTURNER008306 (Subcontract at Ex. G, § V, titled “Basis and Application for Payment”); ECF No. 209 at 63:9-15 (testimony of Joshua Bunting describing his understanding of Ex. G, § V of the Subcontract). The Subcontract also incorporates the schedule for the Project.1 Joint Ex. 1 at WHITINGTURNER008283 (Subcontract at Art. 4(a)), WHITINGTURNER008291 (Subcontract at List of Exhibits, stating that Exhibit I is incorporated into the Subcontract).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bat Masonry Co. v. Pike-Paschen Joint Venture III
842 F. Supp. 174 (D. Maryland, 1993)
Lazorcak v. Feuerstein
327 A.2d 477 (Court of Appeals of Maryland, 1974)
Institute of Mission Helpers v. Reliance Insurance
812 F. Supp. 72 (D. Maryland, 1992)
Continental Masonry Co. v. Verdel Construction Co.
369 A.2d 566 (Court of Appeals of Maryland, 1977)
Taylor v. NationsBank, N.A.
776 A.2d 645 (Court of Appeals of Maryland, 2001)
Clancy v. King
954 A.2d 1092 (Court of Appeals of Maryland, 2008)
Fromm Sales Co. v. Troy Sunshade Co.
159 A.2d 860 (Court of Appeals of Maryland, 1960)
President of Georgetown College v. Madden
505 F. Supp. 557 (D. Maryland, 1980)
Pumphrey v. Pelton
245 A.2d 301 (Court of Appeals of Maryland, 1968)
Rogers Refrigeration Co. v. Pulliam's Garage, Inc.
505 A.2d 878 (Court of Special Appeals of Maryland, 1986)
Sachs v. Regal Savings Bank, FSB
705 A.2d 1 (Court of Special Appeals of Maryland, 1998)
John B. Robeson Associates, Inc. v. Gardens of Faith, Inc.
172 A.2d 529 (Court of Appeals of Maryland, 1961)
Questar Builders, Inc. v. CB Flooring, LLC
978 A.2d 651 (Court of Appeals of Maryland, 2009)
Bollech v. Charles County, MD
166 F. Supp. 2d 443 (D. Maryland, 2001)
Jay Dee/Mole Joint Venture v. Mayor & City Council
725 F. Supp. 2d 513 (D. Maryland, 2010)
Moore Brothers Co v. Brown & Root Inc
207 F.3d 717 (Fourth Circuit, 2000)
Young Elec. Contractors, Inc. v. Dustin Constr., Inc.
185 A.3d 170 (Court of Appeals of Maryland, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Bunting Graphics, Inc. v. The Whiting-Turner Contracting Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bunting-graphics-inc-v-the-whiting-turner-contracting-company-mdd-2025.