President of Georgetown College v. Madden

505 F. Supp. 557, 1980 U.S. Dist. LEXIS 14350
CourtDistrict Court, D. Maryland
DecidedSeptember 24, 1980
DocketCiv. K-77-1438
StatusPublished
Cited by49 cases

This text of 505 F. Supp. 557 (President of Georgetown College v. Madden) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
President of Georgetown College v. Madden, 505 F. Supp. 557, 1980 U.S. Dist. LEXIS 14350 (D. Md. 1980).

Opinion

FRANK A. KAUFMAN, District Judge.

The President and Directors of Georgetown College (Georgetown) bring this diversity action 1 sounding in breach of contract and negligence 2 against the architects, structural engineers, general contractor, masonry subcontractor, and surety involved ín the construction of one of Georgetown’s dormitories, Harbin Hall, which was built during the years 1963-66. Georgetown seeks damages for alleged defects in the construction of Harbin Hall, the surface brick of which has undergone spalling, cracking, and bulging. 3 This action was commenced on August 25, 1977.

Motions for summary judgment have been filed by all defendants. The majority of those motions are based on the grounds that this action is barred by limitations. For the purpose of adjudicating those motions, the facts have, for the most part, been stipulated.

In December 1962, Georgetown entered into a contract with two associated architec *562 tural firms, Cooper and Auerbach, and Walton and Madden (architects) 4 for the performance of architectural services relating to a proposed residential dormitory to be located on Georgetown’s campus in Washington, D.C. Among the services to be performed were the inspection of the progress and quality of work during the construction phase of the project and the certification of progress payments to the contractor. In February 1963, the architects executed a letter agreement with the structural engineering firm of Scullen and Marchigiani. On October 24, 1963, Georgetown entered a construction contract with Victor R. Beau-champ Associates, Inc. (Beauchamp) for the construction of Harbin Hall in accordance with the plans and specifications incorporated therein. On the same date, Standard Accident Insurance Company, as surety, and Beauchamp, as principal, executed a performance-payment bond for the benefit of Georgetown in the penal sum of $2,019,-619.00. Defendant Reliance Insurance Co. (Reliance) is the successor in interest to Standard Accident Insurance Co. under that bond.

Under the terms of the construction contract (¶ 34), Beauchamp was permitted, with the approval of Georgetown, to subcontract specialty work according to normal contracting practices, with Beauchamp to remain fully liable for all acts or omissions of any subcontractor. Beauchamp subcontracted the masonry work to Anchor Associates, Inc. (Anchor). All the construction defects now complained of by Georgetown stem from the masonry work performed by Anchor. 5 Anchor completed the allegedly defective masonry work on or before July 24, 1964. As part of progress payment number twelve, dated November 13, 1964, defendant Madden certified the masonry work here in issue. 6

*563 On September 23, 1964, four floors of Harbin Hall were first occupied and used by Georgetown. Certificates of occupancy were issued to Georgetown by the Department of Licenses and Inspections of the District of Columbia on November 17, 1964. Georgetown occupied the remainder of Harbin Hall on or before January 14, 1965, though work still remained to be done at that time. Final certification of the building by the architects and payment of the final installment to Beauchamp took place on June 2,1966. Georgetown first discovered the defective condition which gave rise to the within suit in September 1976.

The construction contract between Georgetown and Beauchamp provides in relevant part:

¶25. Payments to Contractor (a) Not later than the 15th day of each calendar month the Owner shall make a progress payment to the Contractor on the basis of a duly certified and approved estimate of the work performed during the preceding calendar month under this contract, but to insure the proper performance of this contract, the Owner shall retain ten per cent (10%) of the amount of each estimate until final completion and acceptance of all work covered by this contract * * *.
******
(c) All material and work covered by partial payments made shall thereupon become the sole property of the Owner, but this provision shall not be construed as relieving the Contractor from the sole responsibility for the care and protection of materials and work upon which payments have been made or the restoration of any damaged work, or as a waiver of the right of the Owner to require the fulfillment of all of the terms of the contract.
******
¶ 26. Acceptance of Final Payment Constitutes Release
The acceptance of the Contractor of final payment shall be and shall operate as a release to the Owner of all claims and all liability to the Contractor for all things done or furnished in connection with this work and for every act and neglect of the Owner and others relating to or arising out of this work. No payment, however, final or otherwise, shall operate to release the Contractor or his sureties from any obligations under this contract or the Performance and Payment Bond, ******
¶ 40. General Guaranty Neither the final certificate of payment nor any provision in the Contract Documents nor partial or entire occupancy of the premises by the Owner shall constitute an acceptance of work not done in accordance with the Contract Documents or relieve the Contractor of liability in respect to any express warranties or responsibility for faulty materials or workmanship. The Contractor shall remedy any defects in the work and pay for any damage to other work resulting therefrom, which shall appear within a period of one year from the date of final acceptance of the work unless a longer period is specified. The Owner will give notice of observed defects with reasonable promptness.

In addition to the above sections, the contract specified a single sum of $2,019,-619.00 to be paid by Georgetown to Beau-champ to “commence and complete” the construction of Harbin Hall. Other provisions in the contract made time of the essence for the full completion of the project and provided for completion of all required work within a specified time. 7

*564 I. Motion of Reliance Insurance Co. for Summary Judgment

Reliance seeks summary judgment on the grounds that plaintiff’s claim under the performance bond is time-barred. In both Maryland and the District of Columbia, a bond is a specialty to which a twelve year statute of limitations attaches. 8 Md. Code Ann., Cts. & Jud.Proc. Art. § 5-102(a)(2), D.C. Code § 12-301(6). Both Maryland and the District of Columbia have held that, in contract actions, the cause of action accrues and the limitations period runs from the date of the alleged breach and not from the date the harm is discovered.

Related

Hensel Phelps Construction Co. v. Cooper Carry, Inc.
210 F. Supp. 3d 192 (District of Columbia, 2016)
Thomas v. Rowhouses, Inc.
47 A.3d 625 (Court of Special Appeals of Maryland, 2012)
Ely v. Science Applications International Corp.
716 F. Supp. 2d 403 (D. Maryland, 2010)
Whittington v. Dragon Group, L.L.C.
991 A.2d 1 (Supreme Court of Delaware, 2009)
Murray v. Wells Fargo Home Mortgage
953 A.2d 308 (District of Columbia Court of Appeals, 2008)
Maltas v. Maltas
197 F. Supp. 2d 409 (D. Maryland, 2002)
Jordan v. Sandwell, Inc.
189 F. Supp. 2d 406 (W.D. Virginia, 2002)
Rouse-Teachers Properties, Inc. v. Maryland Casualty Co.
750 A.2d 1281 (Court of Appeals of Maryland, 2000)
Burgess v. Square 3324 Hampshire Gardens Apartments, Inc.
691 A.2d 1153 (District of Columbia Court of Appeals, 1997)
Huntley v. Bortolussi
667 A.2d 1362 (District of Columbia Court of Appeals, 1995)
Shadburne-Vinton v. Dalkon Shield Trust
60 F.3d 1071 (Fourth Circuit, 1995)
Shadburne-Vinton v. Dalkon Sheild Trust
60 F.3d 1071 (Fourth Circuit, 1995)
Anne Arundel County v. Fidelity & Deposit Co.
648 A.2d 193 (Court of Appeals of Maryland, 1994)
United States v. Orme
851 F. Supp. 708 (D. Maryland, 1994)
Shadburne v. Dalkon Shield Trust
851 F. Supp. 712 (D. Maryland, 1994)
Van Slyke v. Worthington
628 A.2d 386 (New Jersey Superior Court App Division, 1992)
Gibson v. West Virginia Department of Highways
406 S.E.2d 440 (West Virginia Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
505 F. Supp. 557, 1980 U.S. Dist. LEXIS 14350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/president-of-georgetown-college-v-madden-mdd-1980.