Anne Arundel County v. Fidelity & Deposit Co.

648 A.2d 193, 336 Md. 282, 1994 Md. LEXIS 129
CourtCourt of Appeals of Maryland
DecidedOctober 6, 1994
DocketNo. 11
StatusPublished

This text of 648 A.2d 193 (Anne Arundel County v. Fidelity & Deposit Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anne Arundel County v. Fidelity & Deposit Co., 648 A.2d 193, 336 Md. 282, 1994 Md. LEXIS 129 (Md. 1994).

Opinion

RODOWSKY, Judge.

In this appeal we hold that the one year statute of limitations under the Little Miller Act applies only to claims on payment bonds and does not apply to claims on performance bonds.

The appellant, Anne Arundel County, Maryland (the County), owns and operates the Cattail Creek Sewage Pumping Station. On or about February 26, 1986, a sixteen inch, cast iron pipe, force main on the discharge side of the pumping station ruptured, causing erosion and other damage. The pumping station and its associated mains had been constructed for the County by Dunton, Inc. under a contract dated August 24, 1976. Also on that dáte the appellee, Fidelity & Deposit Company of Maryland (F & D), as surety, and Dun-ton, Inc., as principal, jointly and severally bound themselves to the County, as obligee, under a bond conditioned on the performance of the pumping station construction contract. To recover its costs of clean up and repair, the County filed this action on June 6, 1988 against F & D and others. The claim against F & D alleges breach of the performance bond.

Approximately four years later F & D moved for summary judgment, contending that the State statute relating to security for construction contracts of state and local subdivisions (the Little Miller Act or LMA) required that the County’s performance bond claim have been filed “within 1 year after the [County] finally accepts the work performed under the contract.” Maryland Code (1985, 1988 Repl.Vol.), § 17-109(b) of the State Finance and Procurement Article (FP). Work under the pumping station contract had been conditionally accepted by the County on or about November 16, 1977, subject to a one year maintenance period. The County con[285]*285tended that the one year period provided by FP § 17—109(b) applied only to payment bonds and that the twelve year period of limitations for suits on certain specialties was applicable.1 The circuit court agreed with F & D’s construction of the LMA and granted summary judgment dismissing F & D from the case.

The circuit court also certified the judgment in favor of F & D as final, pursuant to Maryland Rule 2-602. After the County had appealed to the Court of Special Appeals, this Court granted the County’s petition for certiorari prior to the consideration of the matter by the intermediate appellate court. We also granted leave to the State of Maryland to file a brief as amicus curiae.

The ground of decision by the circuit court on summary judgment presents an issue of construction of the Little Miller Act, FP §§ 17-101 through 17-110. Understanding the issue requires us to present a considerable portion of the statute. The LMA “applies only to security for a construction contract,” § 17-102(b), that is let by a “public body,” meaning, in general, the State or a local government. § 17-101(d). “Before a public body awards a construction contract exceeding $50,000, the contractor shall provide payment security and performance security that meet the requirements of § 17-104 of this subtitle.” § 17—103(a)(1). “ ‘Payment security’ means security to guarantee payment for labor and materials ... under a contract for construction.” § 17-101(b). “ ‘Performance security’ means security to guarantee the performance of a contract for construction.” § 17-101(c). The security [286]*286may be a bond executed by a surety company, cash, or other security satisfactory to the public body. § 17-104.

Under the LMA the term “supplier” is defined to mean “a person who supplies labor or materials.” § 17-101(e). Section 17-108, dealing with an action by a supplier, reads:

“(a) In general.—Subject to subsection (b) of this section, a supplier may sue on payment security if the supplier:
(1) supplied labor or materials in the prosecution of work provided for in a contract subject to this subtitle; and
(2) has not been paid in full for the labor or materials within 90 days after the day that the person last supplied labor or materials for which the claim is made.
(b) Payment owed by subcontractor.—(1) A supplier who has a direct contractual relationship with a subcontractor or sub-subcontractor of a contractor who has provided payment security but no contractual relationship with the contractor may sue on the security if the supplier gives written notice to the contractor within 90 days after the labor or materials for which the claim is made were last supplied in prosecution of work covered by the security.
(2) A notice under this subsection:
(i) shall state with substantial accuracy the amount claimed and the person to whom the labor or material was supplied; and
(ii) shall be sent by certified mail to the contractor at the contractor’s residence or a place where the contractor has an office or does business.
(c) Certification of security.—(1) On request by a person who submits an affidavit verifying that the person has supplied labor or materials but has not been paid or is being sued under this section, the Comptroller or the officer in charge of the office where the payment security or evidence of security is required to be filed shall issue:
(i) a certified copy of the payment bond; or
(ii) for other security, a certified statement of the security-
[287]*287(2) The person requesting certification shall pay a reasonable fee, set by the Comptroller or other officer required to issue the certification, to cover costs of preparation.
(3) A certification under this section is prima facie evidence of the contents, execution, and delivery of payment security.”

Venue, limitations, and costs are addressed in § 17-109 which reads:

“(a) Venue.—An action under this subtitle shall be filed in the appropriate court of the county where:
(1) the contract was executed and performed; or
(2) the contractor has its principal place of business.
(b) Limitations period.—An action under this subtitle shall be filed within 1 year after the public body finally accepts the work performed under the contract.
(c) Costs.—An obligee named in a bond or a trustee for any other security is not liable for any costs in connection with an action under this subtitle.”

In the action before us F & D, relying on § 17—109(b), submits that a suit on a performance bond is “[a]n action under this subtitle.” F & D points to the requirement in § 17-103(a) that the contractor provide both payment security and performance security on public construction contracts over $50,000, from which F & D concludes that an action is “under this subtitle” if it claims breach of the condition of any bond required by the subtitle. The circuit court considered that construction to be the plain meaning of the statute.

F & D’s reading of the statute finds support in a dicta statement, concerning an earlier codification of the LMA, made by this Court in United States Fidelity & Guar. Co. v. Hamilton & Spiegel, Inc., 241 Md.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

President of Georgetown College v. Madden
505 F. Supp. 557 (D. Maryland, 1980)
United States Fidelity & Guaranty Co. v. Hamilton & Spiegel, Inc.
215 A.2d 735 (Court of Appeals of Maryland, 1966)
Atlantic Sea-Con, Ltd. v. Robert Dann Co.
582 A.2d 981 (Court of Appeals of Maryland, 1990)
Board of Education v. Lange
32 A.2d 693 (Court of Appeals of Maryland, 1943)
American Fidelity Co. v. State Ex Rel. Short & Walls Lumber Co.
97 A. 12 (Court of Appeals of Maryland, 1916)
Buffalo Cement Co. v. McNaughton
35 N.Y.S. 453 (New York Supreme Court, 1895)
Union Railway Storage Co. v. McDermott
55 N.W. 606 (Supreme Court of Minnesota, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
648 A.2d 193, 336 Md. 282, 1994 Md. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anne-arundel-county-v-fidelity-deposit-co-md-1994.