Lighting Retrofit International, LLC v. Constellation Newenergy, Inc.

CourtDistrict Court, D. Maryland
DecidedMarch 1, 2023
Docket1:19-cv-02751
StatusUnknown

This text of Lighting Retrofit International, LLC v. Constellation Newenergy, Inc. (Lighting Retrofit International, LLC v. Constellation Newenergy, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lighting Retrofit International, LLC v. Constellation Newenergy, Inc., (D. Md. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

* LIGHTING RETROFIT * INTERNATIONAL, LLC * * Plaintiff/Counter-Defendant, * v. * Civil Case No. 19-cv-02751-SAG * CONSTELLATION NEWENERGY, * INC., et al., * * Defendant/Counter-Plaintiff. * * * * * * * * * * * * * * * * MEMORANDUM OF DECISION Lighting Retrofit International, LLC (“LRI”) brought the instant action against Constellation NewEnergy, Inc. (“Constellation”) and its surety, Liberty Mutual Insurance Company (“Liberty Mutual”). The dispute arises out of a subcontract to update lighting and plumbing fixtures at a federal prison in Florida. LRI seeks damages based on Constellation’s alleged failure to pay LRI in full pursuant to the parties’ subcontract. ECF 1. Constellation filed a counterclaim, asserting that LRI breached the subcontract by, among other things, installing and failing to replace defective lighting products. ECF 53. This Court previously bifurcated the parties’ lighting- and plumbing-related disputes. ECF 49. A bench trial on the lighting-related claims was held on November 14-16, 2022. This Court has considered all the evidence adduced at trial, both testimonial and documentary, as well as the parties’ post-trial briefing. See ECF 128, 129, 130, 131, 132, 134. The Court has also considered LRI’s post-trial motion for leave to amend its Complaint to assert a statute of limitations defense, ECF 133, along with the oppositions to that motion, ECF 135, 136, and LRI’s reply, ECF 137. For the reasons discussed below, this Court concludes that LRI breached its contractual warranty by failing to repair or replace the defective lighting equipment it installed. As a result, Constellation is entitled to judgment on both its breach of contract counterclaim and LRI’s affirmative claims. Liberty Mutual is likewise entitled to judgment on LRI’s claim under the Miller Act, 40 U.S.C. § 3131. Finally, LRI’s post-trial motion to amend its Complaint will be denied.

I. Findings of Fact This Court finds the facts stated herein based on its evaluation of the evidence, including the credibility of the witnesses, and the inferences that this Court has found reasonable to draw from the evidence. 1. On December 17, 2008, Constellation entered into a contract with the federal government to provide “conservation and renewable energy services for Federal facilities.” ECF 117 ¶ 1 (Joint Stipulation of Facts). 2. Pursuant to that contract, Constellation and the Federal Bureau of Prisons (“BOP”) entered into a task order for the implementation of 11 energy conservation measures (“ECMs”) at the Federal Correctional Complex in Coleman, Florida (“FCC Coleman”).

Id. ¶ 2. 3. FCC Coleman consists primarily of four facilities: United States Penitentiary 1 (“Pen 1”); United States Penitentiary 2 (“Pen 2”); Federal Correctional Institution Coleman Low (“FCI Low”); and Federal Correctional Institution Coleman Medium (“FCI Medium”). Id. ¶ 3. 4. At all relevant times, FCC Coleman had 80 high-mast light poles with 728 total light fixtures. Id. ¶ 4. Each pole was between 80 and 100 feet tall. ECF 125 at 39:8-13 (Tr. Testimony of R. Lynch). a. The Subcontract Between Constellation and LRI 5. On December 9, 2014, Constellation and LRI entered into a Blanket Subcontract for Energy Projects and Services (the “Subcontract”). ECF 117 ¶ 5; Jt. Ex. 8. The Subcontract provided that “[a]ll work done pursuant to any Scope of Work [between LRI and Constellation] shall be governed by all the provisions of this Subcontract as if

said scope was set forth in full herein.” Jt. Ex. 8 § 1.0. 6. The Subcontract also contained a warranty provision, id. at § 6.8 (the “warranty provision” or “section 6.8”), which provided in relevant part that: a. “[LRI] warrants that . . . all equipment will be free from defects and installed in accordance with the manufacturer’s specifications . . . .”;

b. “The warranties set forth herein shall continue for a period of one (1) year after the date of Constellation’s final acceptance of the work or [BOP’s] beneficial use, whichever is later . . . .”; and

c. “Unless otherwise provided on the Scope of Work, if the services and materials provided by [LRI] hereunder do not conform to the warranties included herein, then [LRI] will (at its sole cost and expense) do any of the following upon Constellation’s request: (a) re-perform the services, or repair or replace the equipment, in a satisfactory manner that conforms to the terms of this Subcontract, (b) pay Constellation any money damages that Constellation owes as a result of nonconformance and refund the portion of the cost hereunder which is attributable to such nonconformance, (c) if Constellation chooses to correct the breach by re-performing the services or repairing or replacing the equipment, (by itself or through another subcontractor), pay Constellation any expenses Constellation incurs itself or pays to a third party.”

7. Section 7.1 of the Subcontract further stated that LRI would be in material breach if it (i) “refuses or fails to supply . . . proper materials . . .” or (ii) “otherwise is in material breach of any provision of this Subcontract,” unless such breach was cured within three days of receiving notice from Constellation. Id. §§ 7.1.1, 7.1.5 8. In the event of a material breach, section 7.1.5 of the Subcontract provided that Constellation would have the right to pursue any or all of the following remedies: a. “Supply such number of workers and quantity of materials, equipment and other facilities as Constellation deems necessary for the completion of [LRI’s] work; or any part thereof which [LRI] has failed to complete or perform after aforesaid notice, and charge the cost thereof to [LRI]”; or

b. “Contract with one or more additional contractors, to perform such part of [LRI’s] work as Constellation believes will provide the most expeditions [sic] completion of the total work and charge the cost thereof to [LRI]”; or

c. “Withhold payment of any moneys due [LRI] pending corrective action in amounts sufficient to cover losses and compel performance to the extent required by and to the satisfaction of Constellation[.]” Id. § 7.1.5.

9. Additionally, the Subcontract contained an emergency provision, section 7.4 (the “emergency provision”), which provided in relevant part that “[i]n the event of an emergency affecting safety to persons or property” Constellation may, without notice, “furnish those materials, equipment and/or employ such workers or subcontractors, as Constellation deems necessary or desirable to maintain the orderly progress of [LRI’s] work.” Id. § 7.4. In such a scenario, “all costs incurred by Constellation in performing [LRI’s] work, including but not limited to reasonable overhead, profit and reasonable attorneys’ fees and expenses, shall be deducted from any moneys due or to become due [LRI]. [LRI] shall be liable for the payment of any amount by which such expense may exceed the unpaid balance of the price payable hereunder.” Id. 10. Finally, the Subcontract included a retainage provision, § 2.2.3, which stated that the rate of retainage withheld by Constellation “shall be equal to the percentage retained in Constellation payment by [BOP] for [LRI’s] Work, provided the Subcontractor furnishes a bond or other security to the satisfaction of Constellation.” Id. § 2.23. a. Constellation’s contract with BOP did not contain a provision to withhold retainage, Jt. Ex. 1, and LRI posted a bond, Jt. Ex. 14. b. The Scope of Work Between Constellation and LRI 11. On February 26, 2015, pursuant to the Subcontract, Constellation and LRI entered in a Scope of Work (the “SOW”) for “Plumbing and Lighting Improvements for [FCC Coleman].” ECF 117 ¶ 6. The parties revised the SOW on March 24, 2015. Id. 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burgess v. United States
553 U.S. 124 (Supreme Court, 2008)
Ver Brycke v. Ver Brycke
843 A.2d 758 (Court of Appeals of Maryland, 2004)
Cave v. Elliott
988 A.2d 1 (Court of Special Appeals of Maryland, 2010)
I. W. Berman Properties v. Porter Bros.
344 A.2d 65 (Court of Appeals of Maryland, 1975)
Taylor v. NationsBank, N.A.
776 A.2d 645 (Court of Appeals of Maryland, 2001)
President of Georgetown College v. Madden
505 F. Supp. 557 (D. Maryland, 1980)
Antigua Condominium Ass'n v. Melba Investors Atlantic, Inc.
517 A.2d 75 (Court of Appeals of Maryland, 1986)
Sergeant Co. v. Pickett
401 A.2d 651 (Court of Appeals of Maryland, 1979)
Imbesi v. Carpenter Realty Corp.
744 A.2d 549 (Court of Appeals of Maryland, 2000)
David Sloane, Inc. v. Stanley G. House & Associates, Inc.
532 A.2d 694 (Court of Appeals of Maryland, 1987)
McGinty v. Player
396 F. Supp. 2d 593 (D. Maryland, 2005)
Betty Jefferson v. School Board City of Norfolk
452 F. App'x 356 (Fourth Circuit, 2011)
Gary Woodson v. Allstate Insurance Company
855 F.3d 628 (Fourth Circuit, 2017)
Parkway 1046, LLC v. U. S. Home Corporation
961 F.3d 301 (Fourth Circuit, 2020)
Foodbuy, LLC v. Gregory Packaging, Inc.
987 F.3d 102 (Fourth Circuit, 2021)
Nationwide Prop. & Cas. v. Selective Way
248 A.3d 1044 (Court of Appeals of Maryland, 2021)
In the Matter of Judge Nickerson
248 A.3d 298 (Court of Appeals of Maryland, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Lighting Retrofit International, LLC v. Constellation Newenergy, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lighting-retrofit-international-llc-v-constellation-newenergy-inc-mdd-2023.