Lighting Retrofit International, LLC v. Constellation Newenergy, Inc.

CourtDistrict Court, D. Maryland
DecidedFebruary 8, 2024
Docket1:19-cv-02751
StatusUnknown

This text of Lighting Retrofit International, LLC v. Constellation Newenergy, Inc. (Lighting Retrofit International, LLC v. Constellation Newenergy, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lighting Retrofit International, LLC v. Constellation Newenergy, Inc., (D. Md. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

* LIGHTING RETROFIT * INTERNATIONAL, LLC * * Plaintiff/Counter-Defendant, * v. * Civil Case No. 19-cv-02751-SAG * CONSTELLATION NEWENERGY, * INC., * * Defendant/Counter-Plaintiff. * * MEMORANDUM OPINION

Lighting Retrofit International, LLC (“LRI”) commenced this action against Constellation NewEnergy, Inc. (“Constellation”) for claims related to Constellation’s alleged breach of the parties’ subcontract to upgrade lighting and plumbing fixtures at a federal prison in Florida. ECF 1. Constellation counterclaimed, asserting that LRI breached the subcontract. ECF 53. The Court previously held a bench trial focused exclusively on the parties’ lighting-related disputes and entered judgment in favor of Constellation on March 1, 2023. ECF 138. Since then, the case has proceeded on the parties’ plumbing-related disputes and now pending are the parties’ motions for partial summary judgment, ECF 177, 180, and Constellation’s motion to exclude LRI’s proffered expert opinions, ECF 174. The matters have been fully briefed, see ECF 192, 194, 202, 209, 212, 213, and no hearing is necessary, see Loc. R. 105.6 (D. Md. 2023), but the Court at this juncture resolves only Constellation’s motion to exclude. For the following reasons, the Court DENIES Constellation’s motion. I. FACTUAL BACKGROUND The following facts are not in dispute. In December, 2008, Constellation contracted with the federal Bureau of Prisons (“BOP”) to provide “conservation and renewable energy services for Federal facilities.” ECF 180-5 at 6.1 Pursuant to that contract, Constellation and BOP entered into a task order for the installation of several energy conservation measures (“ECMs”) at the Coleman Correctional Complex (“FCC Coleman”) in Coleman, Florida. ECF 67. Two ECMs became relevant to this litigation: ECM-1, which involved upgrades to the lighting system at FCC

Coleman, and ECM-2, which involved upgrades to the facility’s plumbing system. See id. at 7. On or about December 9, 2014, LRI and Constellation executed a subcontract for “energy projects and services,” at FCC Coleman (the “Subcontract”). ECF 185-3 at 2. Constellation and LRI later executed a detailed scope of work (“SOW”) for ECM-1 and ECM-2. See ECF 185-4. As relevant here, the SOW provided that LRI would retrofit various water fixtures and install I-CON electronic control valves at FCC Coleman with a centralized control station within certain housing units. Id. at 2–6. The SOW valued the Subcontract at $5.1 million and set a completion date for all lighting and plumbing work by December 18, 2015. Id. at 8. After BOP submitted several change orders, the value of the Subcontract grew to over $12.5 million, and the completion date became March 31, 2019. See ECF 185-8; ECF 185-9; ECF 185-10; ECF 185-11; ECF 180 at Ex. 12.2

In mid-2015, LRI commenced work at FCC Coleman. ECF 64 ¶ 18. Myriad issues related to lighting and plumbing work arose soon thereafter. See id. ¶ 19; ECF 185-1 at 6. Constellation and LRI failed to resolve many of them, and LRI eventually left the job site. See ECF 178-2 at 21:2–6 (Dep. Testimony of E. Elam). On October 23, 2019, Constellation sent LRI a notification of breach with respect to ECM-2, for among other reasons, failing “to furnish the labor, materials, equipment, and services necessary to install the [I-CON] control system . . . in strict accordance

1 This Court uses the ECF page numbers in the header at the top of the page.

2 The fifth and final change order was executed on November 12, 2018. ECF 180 at Ex. 12. with the SOW and Subcontract requirements.” ECF 185-1 at 3. Constellation also demanded that LRI cure “numerous outstanding issues” identified in a field operation report (“FOR”) log that Constellation received from BOP. Id. at 4. In response, LRI claimed that it completed 99% of the plumbing work and disavowed responsibility for the FOR-related issues Constellation identified

in its letter. ECF 185-2 at 2–4. As a result of this impasse, Constellation hired a new subcontractor, ECM Holding Group, LLC a/k/a Aqua (“Aqua”), on May 15, 2020, to complete the remaining ECM-2 work. ECF 203- 1. Constellation paid Aqua over $2 million for the time and materials Aqua expended to complete the work and now seeks to recover those payments from LRI, plus a 15% markup for overhead and a 10% markup for profit.3 ECF 180-8 at 2, 8. II. PROCEDURAL HISTORY After this Court entered judgment in favor of Constellation for the parties’ lighting-related disputes, ECF 138, the parties re-opened discovery on the plumbing-related issues. While that discovery was ongoing, the Court issued a Consent Order resolving LRI’s remaining affirmative

claims. ECF 169. The remaining plumbing disputes relate solely to Constellation’s amended counterclaim and LRI’s defenses thereto. Pursuant to Federal Rules of Civil Procedure 26(a)(2)(C) and 26(e)(1), Constellation disclosed David Benham as a hybrid fact and expert witness on the plumbing-related issues on November 10, 2023, ECF 192-1, and LRI disclosed Jeff Sammons, Dan Ruse, and Eric Elam as rebuttal hybrid witnesses on November 24, 2023, ECF 176-1. Constellation now seeks to exclude the opinions of LRI’s three proffered experts ahead of trial, contending that LRI’s Rule 26(2)(A)(C) rebuttal disclosure (1) contains inadmissible legal

3 Though not relevant for this motion, Constellation also seeks $4,768,500 in liquidated damages. ECF 180-16. conclusions about the parties’ Subcontract; (2) proffers expert analysis that relies on secondhand knowledge of the facts of this case or inadmissible hearsay; and (3) does not comply with Rule 26(a)(2)(C)(ii) because it fails to identify which expert will testify to which of over thirty-nine opinions set forth in the disclosure.4 ECF 175. Without addressing the Rule 26 deficiency, LRI

contends that its disclosure simply responds to the same kinds of legal conclusions and factual recitations that LRI alleges are in Constellation’s expert disclosure.5 The Court begins first with Constellation’s Rule 26(a)(2) argument. III. LEGAL STANDARD A party must disclose to its adversary the identity of any witness it plans to call at trial for the presentation of evidence. FED. R. CIV. P. 26(a)(2)(A). A witness that is retained solely to provide expert testimony must prepare and sign a detailed written report. Id. 26(a)(2)(B). A party must also disclose a rebuttal witness whose testimony is “intended solely to contradict or rebut evidence on the same subject matter identified by another party under Rule 26(a)(2)(B) or (C)…” FED. R. CIV. P. 26(a)(2)(D)(ii). This disclosure must be made within 30 days after the other party’s

disclosure, or in accordance with a stipulation or court order. Id. Where a witness is not required to provide a written report, the disclosure need only state: (i) the subject matter on which the witness is expected to present expert testimony evidence under

4 Constellation contends that it will be prejudiced because it “will be forced to spend significant time and money preparing to cross-examine three experts . . . without any way of knowing which of the three experts holds which opinion” and “during trial, Constellation cannot possibly know whether to object that a particular expert’s testimony was undisclosed.” ECF 212 at 4.

5 LRI did not file a motion to exclude Constellation’s expert disclosure. Though a court “may consider the admissibility of expert testimony sua sponte,” this Court sees no reason to do so here with respect to Constellation’s expert, David Benham. Dillard v. Smith, 558 F. Supp. 3d 308, 313 n.2 (W.D. Va. 2021) (quoting Lewis v. CITGO Petroleum Corp., 561 F.3d 698, 704 (7th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Lewis v. Citgo Petroleum Corp.
561 F.3d 698 (Seventh Circuit, 2009)
Fleur Bresler v. Wilmington Trust Company
855 F.3d 178 (Fourth Circuit, 2017)
Johnny Timpson v. Anderson County Disabilities
31 F.4th 238 (Fourth Circuit, 2022)
Dorsey v. TGT Consulting, LLC
888 F. Supp. 2d 670 (D. Maryland, 2012)
Coryn Group II, LLC v. O.C. Seacrets, Inc.
265 F.R.D. 235 (D. Maryland, 2010)
Sullivan v. Glock, Inc.
175 F.R.D. 497 (D. Maryland, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Lighting Retrofit International, LLC v. Constellation Newenergy, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lighting-retrofit-international-llc-v-constellation-newenergy-inc-mdd-2024.