Bat Masonry Co. v. Pike-Paschen Joint Venture III

842 F. Supp. 174, 1993 U.S. Dist. LEXIS 19746, 1993 WL 555968
CourtDistrict Court, D. Maryland
DecidedMarch 29, 1993
DocketCiv. A. WN-88-1376
StatusPublished
Cited by5 cases

This text of 842 F. Supp. 174 (Bat Masonry Co. v. Pike-Paschen Joint Venture III) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bat Masonry Co. v. Pike-Paschen Joint Venture III, 842 F. Supp. 174, 1993 U.S. Dist. LEXIS 19746, 1993 WL 555968 (D. Md. 1993).

Opinion

OPINION

NICKERSON, District Judge.

This is a breach of contract action for the balance due on a construction subcontract, and for delay damages and acceleration costs. The subcontract at issue was one for masonry work on the Special Process Laboratory [“the Project”] built under contract from the U.S. Army Corp of Engineers. Plaintiff Bat Masonry Company, Inc. [“Bat”], a Virginia corporation, is a masonry subcontractor. Defendants Paschen Contractors, Inc., a Delaware corporation and John B. Pike & Sons, Inc., a New York corporation, formed a joint venture known as Defendant Pike-Paschen Joint Venture III [“Pike-Paschen”] in order to bid and build the Project. Defendants Reliance Insurance Company, St. Paul Fire & Marine Insurance Company, and Seaboard Surety Company are sureties un *176 der a payment bond provided to the Government by Pike-Paschen. Pike-Paschen asserts a counterclaim for breach of contract, seeking compensation for delays in the Project it claims were caused by Bat.

This Court has jurisdiction in the matter under 28 U.S.C. § 1332(a), by way of diversity of citizenship of the parties and the amount claimed. This Court also finds that, as the contract was executed and performed in Maryland, Maryland law applies.

The Court received extensive testimony and exhibits over the course of a 12 day trial. Following the trial, the Court requested that the parties brief the legal issues regarding liability. Upon consideration of the evidence produced at trial 1 and the argument offered by counsel in the post-trial briefs, the Court makes the following conclusions. The findings of facts and conclusions of law herein relate only to the liability issues raised between the parties and leave determination of precise damages recoverable to a later opinion, if that should prove necessary.

The Court concludes that the following areas require examination:

I. The scope of the terms of the contract between the parties and any breaches thereof. This inquiry requires determinations as to: (A) the time of the formation of the contract; (B) the express terms of the contract; and (C) the implied terms of the contract;

II. The question as to whether Pike-Paschen requested Bat accelerate its performance, and if so, whether Bat is entitled to recover the costs of that acceleration under the terms of the contract and the acceleration request;

III.To what extent Pike-Paschen is entitled to damages for any breach of contract on the part of Bat.

This opinion will also briefly discuss the issues relating to damages in order to provide the parties a potential framework for settlement negotiations or for further briefing to this Court.

1. THE CONTRACT TERMS

A. The Time of Contract Formation

The issue of the timing of the formation of the contract is relevant in that it determines, to some extent, the reasonable expectations of the parties under the contract. Bat maintains that it justifiably relied on an April 9, 1986 bar chart schedule provided by PikePaschen in determining its costs of performance and in deciding whether to enter into the contract. Pike-Paschen maintains that the contract was formed months before Bat was supplied with the schedule and, therefore, Bat could not have relied on the bar chart schedule in entering the contract.

The parties entered into preliminary discussions concerning this contract in the summer of 1985. At that time, Bat was provided with drawings of the Project and the general parameters of the masonry work to be performed. Bat submitted a bid but heard nothing for several months. In December 1985 Pike-Paschen contacted Bat and informed Bat that the scope of the Project had changed and requested Bat resubmit a bid based on those changes. In January 1986, Bat submitted a bid in the amount of $1,067,-500.00. Representatives of Bat testified that the bid was based on an assumption that its masons would be able to achieve a production rate of 160 blocks per mason day, a figure that represented its average performance under average conditions. 2

*177 On January 24, 1986, Pike-Paschen sent a “Letter of Intent” to Bat stating that “we propose to award your firm” the masonry work on the Project. (Def.Ex. 2). On January 27, 1986, Bat sent a letter to PikePaschen which stated, “[w]e are pleased to confirm our quote for the masonry work” and then proceeded to list a number of “Qualifications and Clarifications” regarding the work to be performed. (Def.Ex. 3). The letter concluded, “[i]f you have any questions concerning either our Scope of work or our Qualifications, please feel free to contact us.” Id. On February 17, 1986, Pike-Paschen sent Bat an unsigned subcontract dated February 14, 1986, and requested Bat execute the contract and return it to Pike-Paschen. (DefiEx. 8).

Bat did not immediately sign and return the contract. The parties present opposing views as to why Bat delayed. Pike-Paschen contends that the delay was to clear up some confusion regarding the deletion of a wall in Bat’s bid. Bat maintains that it was in the process of evaluating the profitability of the project under the proposed schedule and delayed signing the contract until it could be certain of the timing and sequence of the masonry work.

In making that evaluation, Bat claims it relied on the bar chart provided by PikePaschen at an April 9, 1986 meeting. (Pltf.Ex. 3). The chart clearly showed the exterior masonry work would begin in August 1986 and would be largely completed before November 1986. Sections of walls were to be completed, according to the schedule, as large sections and in an average of 20 working days per section. The evidence also supports the conclusion that the bar chart was a synoptic representation of the masonry portions of the “baseline” Critical Path Method [“CPM”] schedule for the Project.

In May 1986, Bat, convinced that the schedule was workable and the job profitable, finally signed the contract and returned it to Pike-Paschen. Pike-Paschen executed the contract in early June.

Defendants argue that Bat’s January bid constituted an offer for a contract and that the January 24,1986 Letter of Intent constituted an acceptance of that offer. Thus, a contract was formed. Defendants argue that the formality of a signature is not required to form a binding contract, citing Porter v. General Boiler Casing Co., Inc., 284 Md. 402, 396 A.2d 1090 (1979).

Plaintiff argues, and the Court finds, that the contract was not formed until the contract was signed by both parties in June 1986. Although a signature is not required to form a contract, there must be some objective manifestation of the mutual assent of the parties to all material terms of the agreement. Restatement (Second) of Contracts § 18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sadighi v. Daghighfekr
66 F. Supp. 2d 752 (D. South Carolina, 1999)
Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.
972 F. Supp. 922 (E.D. Pennsylvania, 1997)
Sherwood Brands, Incorporated v. Pally Holland, B.V.
105 F.3d 648 (Fourth Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
842 F. Supp. 174, 1993 U.S. Dist. LEXIS 19746, 1993 WL 555968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bat-masonry-co-v-pike-paschen-joint-venture-iii-mdd-1993.