Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.

972 F. Supp. 922, 1997 U.S. Dist. LEXIS 12917, 1997 WL 532505
CourtDistrict Court, E.D. Pennsylvania
DecidedAugust 22, 1997
Docket2:94-cv-03489
StatusPublished
Cited by12 cases

This text of 972 F. Supp. 922 (Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc., 972 F. Supp. 922, 1997 U.S. Dist. LEXIS 12917, 1997 WL 532505 (E.D. Pa. 1997).

Opinion

MEMORANDUM AND ORDER

JOYNER, District Judge.

INTRODUCTION

This diversity action concerns the construction of the Exhibit Hall building of the Pennsylvania Convention Center (“PCC”) in Philadelphia, Pennsylvania. Dick Enterprises, Inc. (“Dick” or “Dick Enterprises”) served as the general contractor and entered into a contract with the owner of the PCC, the Pennsylvania Convention Center Authority (“PCCA”). 1 Plaintiff Allied Fire and Safety Equipment Company (“Allied”) was the subcontractor for installation of the fire protection systems in the Exhibit Hall. Plaintiff brought this complaint against Dick Enterprises and its sureties, American Casualty Company (“ACC”) of Reading, Pennsylvania, and Continental Casualty Company (“CCC”), asserting claims for breach of contract, quasi-contract recovery, negligence and loss of bonding capacity. 2

Dick Enterprises then filed a Third-Party Complaint against the PCCA, and the PCCA in turn filed a Fourth-Party Complaint against several design professionals who were hired for the project. 3

After the parties conducted discovery, Dick Enterprises filed a summary judgment motion to dismiss the complaint filed against it by Allied. Defendant PCCA also filed a summary judgment motion to dismiss the Third-Party Complaint filed against it by Dick Enterprises. This memorandum resolves both motions.

BACKGROUND

In October 1990, the PCCA instituted a competitive bidding process in order to award the General Construction Contract (“the Prime Contract”) for the construction of the Exhibit Hall Building of the PCC. Ultimately, Defendant Dick Enterprises was awarded the Prime Contract, a voluminous document which includes specifications for the work of the various subcontractors as well as Articles containing General’and Supplementary Conditions.

Dick Enterprises then engaged Allied as the subcontractor responsible for the sprinkler and fire safety systems, and they executed a subcontract (the “Subcontract”) around April 4, 1991. The Subcontract in turn contained Articles and also incorporated certain sections of the Prime Contract, although, Allied did not execute a contract with the PCCA. Allied did, however, execute a performance bond with Fireman’s Fund Insurance Company (“Fireman’s Fund”), and Fireman’s Fund became Allied’s surety for the project.

On April 1, 1991 Dick retained a firm to serve as scheduling consultant. Dick then gave the schedule to Allied and the other subcontractors, and after several drafts and input from the various subcontractors, the initial schedule was issued by Dick on August 28, 1991. Work commenced on the project sometime thereafter.

At some point problems began to develop on the construction site and the project fell behind schedule. These problems apparently escalated, and in January 1993 Dick declared Allied to be in default and subsequently engaged another subcontractor to *926 complete the job. Alied then declared bankruptcy in June 1993 and remained in bankruptcy until April 1994.

Ater the bankruptcy proceedings ended, Alied filed this action against Dick, and Dick then asserted claims for indemnification against the PCCA.

DISCUSSION

I. Summary Judgment Standard

This Court is authorized to grant summary judgment “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). Thus, the Court’s task is not to resolve disputed issues of fact, but to determine whether there exist any material factual issues to be tried. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 2509-10, 91 L.Ed.2d 202 (1986). The summary judgment standard requires the moving party to show that it is so one-sided that it should prevail as a matter of law. Id. at 252, 106 S.Ct. at 2512. Nevertheless the non-moving party must raise more than a scintilla of evidence in order to overcome a summary judgment motion. Williams v. Borough of West Chester, 891 F.2d 458, 460 (3d Cir.1989). Further, the non-moving party cannot survive a summary judgment motion by relying on unsupported assertions. Id.

II. Dick Enterprises’s Motion for Summary Judgment

A. Count I — Breach of Contract

Dick Enterprises argues that summary judgment should be granted in its favor on Alied’s breach of contract claims because (a) Alied lacks standing to assert these claims because they were assigned to a third party, (b) Alied’s claims are barred because Alied failed to comply with the Prime Contract’s notice provisions, (c) Allied’s claims are arbitrable and therefore non-justiciable in this forum, and (d) Alied’s claim for sleeve-installation costs are barred because the contracts clearly require Alied to install sleeves.

Alied in turn argues that (a) it has standing to litigate these claims because it, inter alia, did not assign its rights under the contracts, and, in any event, it received ratification of this lawsuit from Fireman’s Fund, its purported assignee, (b) Dick Enterprises breached the contracts by causing delays and failing to schedule the work in an orderly fashion, (c) Dick Enterprises waived its right to insist that Alied adhere to the Prime Contract’s notice provisions when it breached the Subcontract, (d) Dick Enterprises delayed the arbitration proceeding even when Alied was willing to arbitrate, and Dick therefore waived its right to arbitration, (e) Alied was not responsible to install the sleeves, and Dick Enterprises’ insistence that it do so was a breach of contract, and (f) Dick improperly withheld funds from Allied claiming that they were liquidated damages. Each of these arguments is addressed below.

1. Allied’s Standing to Sue for Breach of Contract

In sharp contrast to the vigor with which it argues for summary judgment on other grounds, Dick Enterprises devotes a couple of pages to claiming that Alied does not have standing to assert any claims against it in this action. Dick Enterprises argues that Alied assigned its rights under the contracts to Fireman’s Fund in an indemnification agreement, and therefore that Fireman’s Fund is the only party entitled to sue under the contract.

Alied responds by first denying that it assigned its claims to Fireman’s Fund, and then by claiming that in any event, Fed. R.Civ.P. 17(a) allows for ratification by the real party in interest. Alied then claims that Fireman’s Fund ratified Allied’s commencement of this action in its settlement with Alied. See Pi’s. Sur-reply Mem. in Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
972 F. Supp. 922, 1997 U.S. Dist. LEXIS 12917, 1997 WL 532505, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-fire-safety-equipment-co-v-dick-enterprises-inc-paed-1997.