LBL SKYSYSTEMS (USA), INC. v. APG-America, Inc.

514 F. Supp. 2d 704, 2007 U.S. Dist. LEXIS 35457, 2007 WL 1437698
CourtDistrict Court, E.D. Pennsylvania
DecidedMay 7, 2007
DocketCivil Action 02-5379
StatusPublished
Cited by4 cases

This text of 514 F. Supp. 2d 704 (LBL SKYSYSTEMS (USA), INC. v. APG-America, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LBL SKYSYSTEMS (USA), INC. v. APG-America, Inc., 514 F. Supp. 2d 704, 2007 U.S. Dist. LEXIS 35457, 2007 WL 1437698 (E.D. Pa. 2007).

Opinion

MEMORANDUM

JAN E. DUBOIS, District Judge.

I. INTRODUCTION

This is a breach of contract action arising out of the construction of a new terminal and renovation of the adjacent terminal at the Philadelphia International Airport. In July 2002, plaintiff LBL Skysystems (USA), Inc. (“LBL”), a contractor, sued one of its subcontractors, defendant APG-Ameriea, Inc. (“APG”) for breach of contract. Also named as a defendant was *706 APG’s surety, Sentry Select Insurance Company (“Sentry”). APG filed several counterclaims against LBL, including a counterclaim for violation of Pennsylvania’s Contractor and Subcontractor Payment Act (“CASPA”), 73 P.S. § 50.1, et seq, and impleaded LBL’s sureties, XL Specialty Insurance Company (“XL”) and NAC Reinsurance Company (“NAC”).

Presently before the Court are LBL’s Motion for Attorney Fees and Expenses and APG’s Memorandum on CASPA dated February 16, -2007 requesting interest, penalty fees, and attorney fees. Both LBL and APG claim such entitlement to fees and other expenses under CASPA. For the reasons that follow, the Court concludes that neither LBL nor APG is entitled to recover attorneys fees or other damages under CASPA.

II. BACKGROUND

A. Facts and Procedural History

The facts and procedural history of this case have been described extensively in two prior opinions, LBL Skysystems (USA), Inc. v. APG-America, Inc., 2005 WL 2140240, 2005 U.S. Dist. LEXIS 19065 (E.DPa. Aug. 31, 2005) (“Liability Opinion”) and LBL Skysystems (USA), Inc. v. APG-America, Inc., 2006 WL 2590497, 2006 U.S. Dist. LEXIS 65142 (E.D.Pa. Sept. 6, 2006) (“Damages Opinion”), and will only be repeated as necessary to resolve LBL’s pending motion and APG’s request for attorneys fees and other CAS-PA damages.

LBL filed a Complaint against APG on July 25, 2002, alleging, inter alia, that APG breached the subcontract between APG and LBL (“the Subcontract”). On August 29, 2002, LBL filed an Amended Complaint against APG and Sentry, APG’s surety on the Subcontract. APG filed its Amended Answer, Affirmative Defenses, and Counterclaims to Plaintiffs Amended Complaint on September 20, 2002, which was later amended (with consent of the parties) on October 8, 2003 to properly implead LBL’s sureties XL Specialty Insurance Company and NAC Reinsurance Corporation.

The original dispute between the parties centered on the scope of APG’s work under the Subcontract. The parties agreed that APG was required to supply and install insulated metal panels for all areas of the project, but disagreed as to APG’s responsibility for supplying and installing certain steel necessary to support the panels. APG first challenged the scope of its work by letter dated April 4, 2002, and began reducing its labor force on the project on or about May 6, 2002. The dispute, and APG’s resulting workforce reduction, ultimately led LBL to terminate the subcontract on June 27, 2002 because of APG’s refusal to supply and install support steel that LBL determined was within APG’s scope of work.

In the Amended Complaint, LBL claimed that because the support steel was within the scope of APG’s responsibilities under the Subcontract, APG’s refusal constituted a breach of contract. On this ground, LBL sought damages from APG for LBL’s cost to complete the work. In response, APG argued that the steel was not within the scope of the Subcontract, and that APG was wrongfully terminated by LBL.

APG raised additional issues in its counterclaims, claiming, inter alia, that LBL (1) breached the contract, (2) failed to process APG’s Change Order Requests (“CORs”), 1 and (3) wrongfully withheld payments from APG in violation of CAS-PA. In these three overlapping Counter *707 claims, APG alleges that LBL “failed and refused to make payments to APG for all work performed to date,” Defs, APG America, Inc., Amended Answer, Affirmative Defenses and Counterclaims to Pl.’s Amended Compl. (“APG Counterclaims”) ¶ 125, including so-called “additional work,” or work that was beyond the scope of the Subcontract for which APG submitted CORs. See id. ¶¶ 129, 139, 140.

Payments to APG were largely controlled by a Funds Agreement. The Court explained this arrangement in the Liability Opinion as follows:

LBL initially failed to- obtain payment bonds required under the Prime Contract, causing delays in payments to APG. As a result, on October 17, 2000, LBL and APG entered into the Funds Agreement under which a third party, the Funds Administrator received all payments for APG and LBL directly from the Owner [US Airways] and then disbursed those payments to LBL and APG. Under the Funds Agreement, LBL did not receive any funds that U.S. Airways had earmarked for disbursal to APG; those payments were made by the Funds Administrator to APG.

LBL Skysystems (USA), Inc., 2005 WL 2140240, at *15, 2005 U.S. Dist. LEXIS 19065, at *44. However, “as a direct result of APG’s actions” challenging the scope of the Subcontract, the Funds Administrator ceased disbursing funds to LBL and LBL began funding its own work, and APG’s work, on March 15, 2002. LBL Ex. 278.

B. Liability Opinion: August 31, 2005 Memorandum, Findings of Fact and Conclusions of Law

Following a bench trial, on August 31, 2005, the Court issued a Memorandum, Findings of Fact and Conclusions of Law, the Liability Opinion. In that Opinion, the Court concluded that APG materially breached the Subcontract with LBL. Specifically, the Court found that:

The support steel at issue was within APG’s scope of work under the Subcontract. APG’s failure to furnish and install the disputed support steel was a breach of the Subcontract. The provision of the Prime Contract that required the Contractor, LBL, to continue to work in the event of a dispute with the Owner, U.S. Airways, was incorporated into the Subcontract. APG was required to continue work on the Philadelphia Airport Project notwithstanding its disputes with LBL. LBL’s termination of APG complied with the termination provisions of the Subcontract.

LBL Skysytems (U.S.A.), Inc., 2005 WL 2140240, at *23, 2005 U.S. Dist. LEXIS 19065, at *65-66.

APG’s claim to payments allegedly owed by LBL was also addressed by the Court. The Court concluded that the Funds Agreement was a “pay-if-paid” contract that shielded LBL from liability to APG unless LBL was paid, and therefore LBL was only liable to APG “to the extent that it failed to pass any of APG’s CORs on to the Owner and the CÓRs are determined to be meritorious” and “to the extent that LBL received funds from the Owner for work performed by APG.” Id. at 2005 WL 2140240, *33, 2005 U.S. Dist. LEXIS 19065, *95-96.

With respect to APG’s CASPA claim the Court ruled that “LBL cannot be liable to APG under CASPA for work performed by APG while the Funds Agreement was in place.” Id. at 2005 WL 2140240, *34, 2005 U.S. Dist. LEXIS 19065, *99-100. The *708

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Management Consultants v. Sea-z
Superior Court of Pennsylvania, 2017
Waller Corp. v. Warren Plaza, Inc.
95 A.3d 313 (Superior Court of Pennsylvania, 2014)
Zimmerman v. Harrisburg Fudd I, L.P.
984 A.2d 497 (Superior Court of Pennsylvania, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
514 F. Supp. 2d 704, 2007 U.S. Dist. LEXIS 35457, 2007 WL 1437698, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lbl-skysystems-usa-inc-v-apg-america-inc-paed-2007.