Ruthrauff, Inc. v. Ravin, Inc.

914 A.2d 880, 2006 Pa. Super. 352, 2006 Pa. Super. LEXIS 4482
CourtSuperior Court of Pennsylvania
DecidedDecember 8, 2006
StatusPublished
Cited by68 cases

This text of 914 A.2d 880 (Ruthrauff, Inc. v. Ravin, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruthrauff, Inc. v. Ravin, Inc., 914 A.2d 880, 2006 Pa. Super. 352, 2006 Pa. Super. LEXIS 4482 (Pa. Ct. App. 2006).

Opinion

OPINION BY

BENDER, J.:

¶ 1 In these consolidated appeals, Ru-thrauff, Inc. (“Ruthrauff’), the subcontractor plaintiff in this construction litigation, sought to obtain $55,940.00, which it alleged that defendant, Ravin, Incorporated (“Ravin”), wrongfully withheld as retain-age under a contract for, inter alia, installation of an infrared tube heating system above bleachers in an ice skating rink in Allegheny County known as the Castle Shannon Ice Castle. 1 The trial court awarded Ruthrauff the amount it sought, but refused to award interest on the re-tainage, attorneys’ fees, expenses, and penalties under the Contractor and Subcontractor Payment Act, 73 P.S. §§ 501-516 (the “Act”). Ravin, the general contractor on the ice rink construction project, in a breach of contract counterclaim filed against Ruthrauff based on its dissatisfaction with the heating system above the bleachers, sought to obtain $34,500.00, which represented the cost of replacing the system. The trial court granted Ravin relief on its counterclaim.

*883 ¶ 2 In its appeal, Ruthrauff claims that the trial court erred by granting Ravin relief on its counterclaim for costs of replacing the heating system, and that the trial court erred by refusing to grant interest on the retainage, attorneys’ fees, expenses, and penalties as per the Act. Ra-vin, on the other hand, filed a cross appeal in which it asserts that the trial court erred by finding that Ruthrauff was entitled to recover, under theories of unjust enrichment and quantum meruit, for additional work it performed outside the warranty period.

¶ 3 For the following reasons, we conclude that the trial court erred by finding in Ravin’s favor on its counterclaim to recover the cost of the replacement heating system above the bleachers. Further, we find that the trial court erred by denying an interest award on the retainage to Ruthrauff under the Act, but did not err by denying a penalty award under the Act. 2 Finally, we affirm the trial court’s decision finding in Ruthrauff s favor on its unjust enrichment claim against Ravin.

¶ 4 A factual and procedural history follows. Ralph Paul Murovich, a shareholder of the general contractor, Ravin, is also a partner of Ice Castle’s owner, a development company called Tymaco, Incorporated. N.T. Trial, 4/5-6/05, at 244. In planning to build the Ice Castle ice skating rink, which was constructed in 2000, Muro-vich brought in John Burley, of Burley’s Rink Supply, Inc., as the rink designer. Burley specialized in equipment related to maintaining the ice surfaces. Id. at 246-47. Burley, who also had his own ice rink in Johnstown, was slated to install the ice making system at the Ice Castle. Quinn Deposition, 10/7/03, at 18 (entered into evidence at trial).

¶ 5 Murovich and Ravin’s vice president, Regis Mark Quinn, visited Burley’s Johns-town rink prior to construction and observed the heaters over the bleachers. N.T. at 299; Quinn Deposition at 18, 21. Burley told Murovich that he had a “good heating system for over the bleachers.” N.T. at 300.

¶ 6 Ravin hired its own engineer, Gerald A. Herron, for the Ice Castle project. 3 Herron testified that Ravin hired him to perform electrical and mechanical design for the Ice Castle based on the design of Burley’s ice rink. Herron Deposition, 10/6/03, at 9, 83 (entered into evidence at trial). Herron admitted that he was instructed by Ravin to “copy the Burley rink” design. Id. at 15, 83. Accordingly, Herron obtained Burley’s drawings and based his electrical and mechanical design for the Ice Castle on Burley’s drawings. Id. at 20-21.

If 7 Herron obtained the specifications for the infrared heaters to be placed above the bleachers from Burley. Id. at 83. Thus, the specifications for the heaters originated from Burley, see infra, who had the same heaters in his Johnstown rink. Id. at 13-15, 89. Indeed, Burley, whom Herron considered to be an expert, also initially told Herron that the heaters above the bleachers in his rink worked “just fine” and that those were the heaters that Her-ron needed at the Ice Castle. Id. at 89, 95-96.

¶ 8 Pursuant to Burley’s rink design, Herron made preliminary drawings of the *884 ice rink, dated May 22, 2000. Additionally, he drew-up preliminary schedules, also dated May 22, 2000, in which he specified the same infrared heater over the bleachers that Burley had at his rink. Particularly, the schedules specified a gas “infrared tube heater,” manufactured by “Enerco or equal,” model number “ER150,” 150,000 BTUs, 120 volts, with a length of 51-feet, 10-inches. N.T. at 57, 96, 107, 301, 389; Preliminary Schedules, 5/22/00, M-4; Herron Deposition at 40. Specifics were indicated for the flue and gas connection also. Preliminary Schedules, M-4. Additionally, the schedules indicated “maximum of four burners on 1/20A circuit[,]” “thermostat at rink level[,]” “maintain manufacturer’s clearances[,]” and other keyed notes.

¶ 9 Despite these specificities with regard to the type of heater to be installed on the preliminary schedules, the preliminary floor plan drawings of the rink did not indicate the number, location, or configuration of these heaters. Preliminary First Floor Plan B, 5/22/00; N.T. at 96. In other words, the heaters were absent from the floor plan layouts. Id.; N.T. at 250.

¶ 10 In June of 2000, based on Herron’s preliminary drawings and the preliminary schedules, Ruthrauff submitted a bid to Ravin for HVAC, 4 plumbing, and fire protection work on the Ice Castle project. N.T. at 28, 56, 316. Specifically with regard to HVAC work, Ruthrauff proposed to “[f|urnish and install complete HVAC system per plans and speciftcations.” Ruthrauff HVAC Proposal, 6/27/00 (emphasis added). Ray Gajski, Ruthrauffs HVAC project manager, testified that Ruthrauff did not decide on the number, make, or model of heaters to be installed, as these were already specified by Ravin’s engineer, Herron. N.T. at 61.

¶ 11 Ruthrauff won the work it bid upon for the Ice Castle construction project. In addition to other HVAC, plumbing, and fire alarm work, Ravin’s vice president, Quinn, admitted that Ruthrauff was hired to furnish and install the heaters above the bleachers. Quinn Deposition at 31. Indeed, Quinn sent a letter of intent to Ruthrauff, dated July 12, 2000, in which he indicated that Ravin intended to enter into a contract for HVAC, plumbing, and fire protection work with Ruthrauff. Quinn’s letter indicated that the “scope of work shall be defined in the construction drawings and specifications” provided by Murovich Associates, Herron, and Burley’s Rink Supply.

¶ 12 Nevertheless, despite the magnitude of this construction project, Ruthrauff and Ravin did not enter into a separate written construction contract. Rather, at trial, Ravin, via Murovich’s testimony, agreed that the “contractual” documents in this case included Ruthrauffs June 27, 2000 HVAC proposal letter, see supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alston, C. v. Joseph, T.
Superior Court of Pennsylvania, 2025
Grit Drexel v. Crescent Abstract
Superior Court of Pennsylvania, 2025
Edwards, W. v. Checkers Drive-in
Superior Court of Pennsylvania, 2023
Smith v. USAA Casualty Company
E.D. Pennsylvania, 2022
Artisan Builders, Inc. v. Jang, S.
2022 Pa. Super. 36 (Superior Court of Pennsylvania, 2022)
Schoenholtz D. & M. v. Half Moon Land Co., LLC
Superior Court of Pennsylvania, 2020
Gamesa Energy USA, Aplt. v. Ten Penn Center
Supreme Court of Pennsylvania, 2019
Charter Homes at Mill Creek v. Charlan Group
Superior Court of Pennsylvania, 2019
Oliphant-Johns, C. v. Good Deal Remodeling
Superior Court of Pennsylvania, 2019
Saltzer, M. v. Rolka, D. & Loube, R.
Superior Court of Pennsylvania, 2018
Bank of New York Mellon v. Butterline, M.
Superior Court of Pennsylvania, 2018
Williams Pontiac Co. v. Patriot Buick Pontiac
Superior Court of Pennsylvania, 2018
Gamesa Energy United States, LLC v. Ten Penn Ctr. Assocs., L.P.
181 A.3d 1188 (Superior Court of Pennsylvania, 2018)
Gamesa Energy USA v. Ten Penn Center
Superior Court of Pennsylvania, 2018
P.S.M. v. A.R.M.
Superior Court of Pennsylvania, 2018
United Environmental Group, Inc. v. GKK McKnight, LP
176 A.3d 946 (Superior Court of Pennsylvania, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
914 A.2d 880, 2006 Pa. Super. 352, 2006 Pa. Super. LEXIS 4482, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruthrauff-inc-v-ravin-inc-pasuperct-2006.