R.W. Sidley, Inc. v. United States Fidelity & Guaranty Co.

319 F. Supp. 2d 554, 2004 U.S. Dist. LEXIS 2303, 2004 WL 224597
CourtDistrict Court, W.D. Pennsylvania
DecidedJanuary 12, 2004
DocketCiv.A. 3:01-404J
StatusPublished
Cited by7 cases

This text of 319 F. Supp. 2d 554 (R.W. Sidley, Inc. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.W. Sidley, Inc. v. United States Fidelity & Guaranty Co., 319 F. Supp. 2d 554, 2004 U.S. Dist. LEXIS 2303, 2004 WL 224597 (W.D. Pa. 2004).

Opinion

MEMORANDUM OPINION AND ORDER

GIBSON, District judge.

This case comes before the Court for consideration of Defendant’s Motion for Partial Summary Judgment (Document No. 23) and Plaintiffs Reply in Opposition to Defendant’s Motion for Partial Summary Judgment (Document No. 27). For the following reasons, Defendant’s Motion for Partial Summary Judgment is granted.

I. FACTUAL AND PROCEDURAL BACKGROUND

Plaintiff, R.W. Sidley, Inc., filed this action against the Defendant, United States Fidelity & Guaranty Company (“USF & G”) on' December 28, 2001. (Document No. 1). Plaintiffs claims arise out of a construction project undertaken in Allegheny Township, Altoona, Pennsylvania.

In July of 2000, the general construction contractor, Lawruk Builders, Inc., a Pennsylvania corporation, entered into an agreement with Blair County Convention Center & Sports Facility Authority (“Authority”) for the construction of a project known as the Blair County Convention Center Parking Garage (“Project”). (Document No. 5). Pursuant to the provisions of the agreement and the Public Works Contractors Bond Law of 1967 (“Act”), Lawruk was required to provide a payment bond. (Document No. 7). On July 26, 2000, Lawruk purchased a joint and several Payment Bond (“Bond”) from Defendant, USF & G. (Document No. 7). USF & G acted as a surety on the Project. Id.

• On September 12, 2000, Plaintiff entered into a Subcontract Agreement (“Subcontract”) with Lawruk to supply materials and labor to Lawruk in the nature of precast concrete components and erection thereof in connection with the Project. (Document No. 5). The amount of the Subcontract Agreement between Plaintiff and Lawruk was the sum of $2,476,000.00. (Document No. 5).

Plaintiff contends that the materials supplied for the Project were of good and merchantable quality, and Plaintiff further *556 argues that the precast concrete components were erected in a timely, workmanlike manner. (Document No. 5). Conversely, Defendant alleges that Plaintiff supplied the materials in an untimely manner, and that the materials were not of good mercantile quality necessitating repairs and rework. (Document No. 7).

At the time Plaintiff initiated this civil action, Plaintiff alleged that the remaining balance due Plaintiff from the general contractor, Lawruk, was $503,296.00. (Document No. 5). During the ongoing litigation of this civil action, however, Lawruk issued three separate payments to Plaintiff between May of 2002 and August of 2002. (Document No. 21). The total amount of these payments was $393,465.58. (Document No. 21). Plaintiff argues that Law-ruk owes the remaining balance due on the Subcontract in the amount of $109,830.62. (Document No. 21).

On October of 2001, Plaintiff placed Defendant, USF & G, on notice that Lawruk failed to pay Plaintiff the requested amount alleged owed under the terms of the Subcontract. (Document No. 5). USF & G argues, however, that no sum is presently due Plaintiff because Lawruk incurred substantial backcharges as the result of Plaintiffs unsatisfactory job performance. (Document No. 7). Defendant has argued that no further payments are owing to Plaintiff. (Document No. 22). To date, Lawruk made three subsequent payments to Plaintiff that were withheld as a result of backcharges allegedly incurred by Lawruk. Id. USF & G asserts that the payments not made to Plaintiff represent legitimate backcharges under the Subcontract. Id. Thereafter, Plaintiff initiated this civil action against USF & G.

Plaintiff filed the following claims against USF & G pursuant to the Payment Bond: (1) Plaintiff is entitled to recover the full balance of its Subcontract with Lawruk totaling $109,830.62; (2) Plaintiff is entitled to recover damages for interest on the late payments at the rate of 1.5% per month and its unpaid Applications for Payment pursuant to the terms of the Subcontract between Lawruk and Plaintiff; (3) Plaintiff is entitled to recover a penalty amount at the rate of 1.0% per month on all outstanding amounts due pursuant to the Contractor and Subcontractor Payment Act, 73 P.S. § 501, et seq. (“Act”) and/or the Commonwealth Procurement Code, 62 Pa.C.S.A. § 101, et seq. (“Code”); and (4) Plaintiff is entitled to recover attorneys’ fees incurred in the course of this litigation pursuant to the Act and/or the Code. (Document No. 21).

On July 15, 2003, Defendant filed a Motion for Partial Summary Judgment arguing that Partial Summary Judgment is proper for the following reasons:

First, under Pennsylvania law, [Plaintiff] may not recover from the surety under the payment bond “interest” or “finance charges” based on a provision of the subcontract between [Plaintiff] and the principal contractor, Lawruk. Second, a claim for attorneys’ fees and interest penalties pursuant to the Pennsylvania Contractor and Subcontractor Payment Act is inapplicable to sureties, such as USF & G. Third, a claim for attorneys’ fees and interest penalties pursuant to the Commonwealth Procurement Code is also inapplicable to sureties.

(Document No. 23).

II. DISCUSSION

Fed.R.Civ.P. 56(c) provides that summary judgment may be granted if, drawing all inferences in favor of the non-moving party, “the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any *557 material fact and that the moving party is entitled to a judgment as a matter of law.”

The mere existence of some factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment. A dispute over those facts that might affect the outcome of the suit under the governing substantive law, i.e.,-the material facts, however, will preclude the entry of summary judgment. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Similarly, summary judgment is improper so long as the dispute over the material facts is genuine. Id. In determining whether the dispute is genuine, the court’s function is not to weigh the evidence or to determine the truth of the matter, but only to determine whether the evidence of record is such that a reasonable jury could return a verdict for the nonmoving party. Id. at 248-49, 106 S.Ct. 2505. In summary, the inquiry under a Rule 56 motion is whether the evidence of record presents a genuine dispute over material facts so as to require submission of the matter to a jury for resolution of that factual dispute, or whether the evidence is so one-sided that the movant must prevail as a matter of law.

To demonstrate entitlement to summary judgment, the defendant, as the moving party, is not required to refute the essential elements of the plaintiffs cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scungio Borst & Associates v. 410 Shurs Lane Developers, LLC
146 A.3d 232 (Supreme Court of Pennsylvania, 2016)
Brown v. City of Pittsburgh
543 F. Supp. 2d 448 (W.D. Pennsylvania, 2008)
Imperial Excavating & Paving, LLC v. Rizzetto Construction Management, Inc.
935 A.2d 557 (Superior Court of Pennsylvania, 2007)
Ruthrauff, Inc. v. Ravin, Inc.
914 A.2d 880 (Superior Court of Pennsylvania, 2006)
Electric Man, Inc. v. Charos
2006 VT 16 (Supreme Court of Vermont, 2006)
Fletcher Hill, Inc. v. Crosbie
2005 VT 1 (Supreme Court of Vermont, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
319 F. Supp. 2d 554, 2004 U.S. Dist. LEXIS 2303, 2004 WL 224597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rw-sidley-inc-v-united-states-fidelity-guaranty-co-pawd-2004.