Electric Man, Inc. v. Charos

2006 VT 16, 895 A.2d 193, 179 Vt. 351, 2006 Vt. LEXIS 27
CourtSupreme Court of Vermont
DecidedFebruary 10, 2006
DocketNo. 04-542
StatusPublished
Cited by32 cases

This text of 2006 VT 16 (Electric Man, Inc. v. Charos) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electric Man, Inc. v. Charos, 2006 VT 16, 895 A.2d 193, 179 Vt. 351, 2006 Vt. LEXIS 27 (Vt. 2006).

Opinion

Dooley, J.

¶ 1. Contractor Ernest Salo appeals from a superior court order awarding him only a portion of his attorneys’ fees, pursuant to Vermont’s prompt payment act, 9 V.S.A. § 4007(c), against owners George Charos, John Charos, and Patricia Costello. The case arises out of a contract under which contractor was to remodel owners’ house. Contractor prevailed below on his claims for breach of contract and conversion, and on owners’ claims for defective workmanship, but the superior court did not award him all of his attorneys’ fees. On appeal, contractor argues that the trial court erred when it: (1) separated out the percentage of the total verdict that represented the payment-withholding claim from the claims for [352]*352breach of contract and conversion, and awarded attorneys’ fees under the prompt payment act only for that portion of the fees associated -with the payment-withholding claim; and (2) specifically disallowed attorneys’ fees associated with unsuccessful mandatory and voluntary mediation. We reverse and remand for imposition of a new attorneys’ fee award.

¶ 2. In the spring of 2001, contractor entered into an oral contract with owners to expand owners’ vacation home in Jamaica, Vermont. Contractor was to construct a one-story addition with two bedrooms, a bathroom, and a loft over an existing garage. The parties did not enter into a single, written contract regarding the construction, but instead made plans through a series of conversations and e-mail correspondence. Contractor began work on the project in early summer 2001. As work progressed, owners made periodic payments by check or cash, and contractor used the funds to buy supplies and pay employees. In September 2001, contractor requested additional funds from owners in order to complete the construction. At one point he left owners a ledger sheet marking expenses and payments received, and indicating that his unreimbursed out-of-pocket expenses were $2,600. Owners responded by leaving a message demanding that contractor stay away from the property or risk being arrested for trespass. As a result, contractor was unable to retrieve ladders and building materials he had left on the premises before the falling-out. On January 2, 2002, contractor’s lawyer sent owners a letter detailing the amount contractor claimed was owed to him. The letter claimed a total of $7,231: (1) $3,218 for unreimbursed materials; (2) $3,040 for unreimbursed labor; and (3) $973 for three ladders owned by contractor but kept by owners. Owners paid no additional funds to contractor and eventually hired a new contractor to complete the project with modifications.

¶ 3. Due to the lack of payment by owners, contractor was unable to pay an electrical subcontractor who had worked on the home addition. Subcontractor, who is not a party in this appeal, eventually sued owners for the amount owed and filed a mechanics’ lien on owners’ property. Owners then impleaded contractor as a third-party defendant alleging breach of contract, among other reasons, for defective construction, and claiming compensatory and punitive damages. Contractor answered the third-party complaint and counterclaimed for breach of contract, unjust enrichment, conversion, and violation of Vermont’s prompt payment act, 9 V.S.A. §§ 4001-4009. He sought the amount due under the contract, [353]*353payment for extras, sums for the value of materials and business equipment left on site, as well as interest and attorneys’ fees pursuant to the statute.

¶ 4. Prior to trial, the parties engaged in both court-ordered and voluntary mediation, but neither led to a settlement and there was no agreement that either party would bear the costs associated with the mediation attempts. The case was tried to a jury, and the verdict was for contractor on each of his claims and against owners on each of theirs. The jury awarded contractor $1,000 for breach of contract, $600 for money wrongfully withheld by the plaintiffs in violation of the prompt payment act, and $4,941 for conversion of property, for a total award of $6,541.

¶ 5. In accordance with the favorable verdict, contractor filed a motion seeking attorneys’ fees pursuant to 9 V.S.A. § 4007(c), prejudgment interest on the damages awards for breach of contract and conversion, interest under § 4002(d), penalties under § 4007(b), and attorneys’ fees for bad faith litigation if statutory attorneys’ fees were not awarded. After receiving subsequently ordered affidavits, the trial judge awarded prejudgment interest on the breach-of-contract award, but not on the conversion claim, and declined to award attorneys’ fees based upon bad faith litigation. The court found contractor to be the “substantially prevailing party” within the meaning of § 4007(c), but limited its award of attorneys’ fees and interest under the statute to an amount in proportion to that part of the overall judgment that represented recovery of the wrongfully-withheld contract payment. Finding that the contractor received a total judgment award of $6,541, of which $600, or about 10 percent, was for sums wrongfully withheld in violation of the prompt payment act, the court awarded contractor attorneys’ fees only in the amount of $3,745, or approximately 10 percent, of his claimed $37,445.91 total for attorneys’ fees. The court also noted that part of the attorneys’ fees contractor claimed were for legal services in connection with the mediations and ruled it “[in]appropriate to award costs or fees for mediation to [contractor] because both parties are required to participate in mediation per Court order.” Accordingly, the trial court did not award attorneys’ fees for contractor’s breach-of-contract claims and defenses, or for his conversion claim. Contractor now appeals this limitation on attorneys’ fees under § 4007(c), and appeals the trial court’s specific decision to deny attorneys’ fees for mediation-related expenses.

[354]*354¶ 6. Contractor bases his claim for attorneys’ fees on the prompt payment act, which in relevant part provides that “the substantially prevailing party in any proceeding to recover any payment within the scope of this chapter shall be awarded reasonable attorneys’ fees in an amount to be determined by the court or arbitrator, together with expenses.” 9 V.S.A. § 4007(c). The statute creates an exception to the “American Rule,” which generally provides that parties to litigation are responsible for their own attorneys’ fees regardless of the litigation outcome. Galkin v. Town of Chester, 168 Vt. 82, 91, 716 A.2d 25, 31 (1998). Under the statute, if a party has substantially prevailed as specified in the statute, an award of attorneys’ fees is mandatory. Fletcher Hill, Inc. v. Crosbie, 2005 VT 1, ¶ 12, 178 Vt. 77, 872 A.2d 292. We review the trial court’s ruling on the amount of attorneys’ fees awarded for abuse of discretion. Id. ¶ 3.

¶ 7. Contractor argues that he is entitled to an award of all the attorneys’ fees he incurred, including the fees necessary to meet and defeat owners’ third-party claims, because the wording of § 4007(c) requires it, and because it is impossible to separate the dispute into component parts by cause of action as the trial court attempted. In general, we agree and begin our analysis with the second point.

¶ 8. Although the jury separated its verdict into three components in response to the jury charge and interrogatories, it had substantial flexibility in how it labeled the award, especially because the contract between contractor and owners was oral, with little specificity in its terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patterson & Smith v. Father Lemelson
Vermont Superior Court, 2025
Allen v. Feeney Property
Vermont Superior Court, 2024
Fortney & Weygandt, Inc. v. Lewiston DMEP IX
2022 ME 5 (Supreme Judicial Court of Maine, 2022)
Construction Drilling, Inc. v. Engineers Construction, Inc.
2020 VT 38 (Supreme Court of Vermont, 2020)
J & K Tile Company
2019 VT 78 (Supreme Court of Vermont, 2019)
J&K Tile Co. v. Wright & Morrissey, Inc.
Vermont Superior Court, 2018
Dorr v. Lacoste
Vermont Superior Court, 2016
Post and Beam Equity Group, LLC and Post and Beam of Mt. Snow, LLC
199 Vt. 313 (Supreme Court of Vermont, 2015)
Walsh v. Cluba and Good Stuff, Inc.
2015 VT 2 (Supreme Court of Vermont, 2015)
Amidon v. Amidon
Vermont Superior Court, 2014
King v. Bishop
Vermont Superior Court, 2013
Birchwood Land Company, Inc. v. Ormond Bushey & Sons, Inc.
2013 VT 60 (Supreme Court of Vermont, 2013)
Nystrom and Nystrom v. Hafford
2012 VT 60 (Supreme Court of Vermont, 2012)
Southwick v. City of Rutland
2011 VT 105 (Supreme Court of Vermont, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2006 VT 16, 895 A.2d 193, 179 Vt. 351, 2006 Vt. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electric-man-inc-v-charos-vt-2006.