Allen v. Feeney Property

CourtVermont Superior Court
DecidedJuly 25, 2024
Docket24-cv-846
StatusPublished

This text of Allen v. Feeney Property (Allen v. Feeney Property) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allen v. Feeney Property, (Vt. Ct. App. 2024).

Opinion

VERMONT SUPERIOR COURT CIVIL DIVISION Windsor Unit Case No. 24-CV-00846 12 The Green Woodstock VT 05091 802-457-2121 www.vermontjudiciary.org

David Allen and Kristey Allen Plaintiffs

v.

Feeney Property Maintenance LLC and Roni Johnson DBA Roni Johnson Landscaping Defendants

Decision on Plaintiffs’ Motion for Preliminary Injunction Decision on Defendant Roni Johnson’s Motion for Writ of Attachment

Plaintiffs David Allen and Kristey Allen own land in Barnard, Vermont. During the fall of 2022, in anticipation of building a residence on the property, they hired defendant Feeney Property Maintenance LLC to perform excavation work and prepare the site on a time-and-materials basis. Defendant Feeney Property Maintenance, in turn, subcontracted with defendant Roni Johnson to perform at least some of the work. A disagreement eventually arose between plaintiffs and defendants, and plaintiffs refused to pay several periodic invoices that had been submitted by defendants. Both defendants thereafter asserted liens against the property for amounts due. Plaintiffs filed the present civil action and requested a preliminary injunction discharging both liens. Both defendants answered the complaint and filed counterclaims for amounts due. Both defendants also filed motions to enforce their mechanics’ liens, although defendant Feeney Property Maintenance LLC subsequently withdrew its request. An evidentiary hearing was held on defendant Johnson’s motion for enforcement of the lien, along with plaintiffs’ motion for a preliminary injunction. Evidence was presented on May 17, 2024 and June 21, 2024. Plaintiffs appeared and represented themselves, and defendants appeared and were represented by Atty. Windish. The following factual findings were established by a preponderance of the credible evidence. Paul Feeney is the principal of defendant Feeney Property Maintenance LLC. Plaintiffs knew Mr. Feeney from the community and had worked with him in the past. In November 2022, they approached him about performing excavation and site-preparation work at the property, including land clearing, stump removal, foundation preparation, driveway construction, an underground electrical conduit, and a septic system. Mr. Feeney provided a verbal estimate of the amount of money and time it would take to complete the work on a time-and-materials basis, and plaintiffs asked him to begin work. Before Mr. Feeney began working on the property, however, plaintiffs changed the location of their house site. Although the change had material consequences for the scope of work, the parties did not discuss whether the change would affect the estimate. Order Page 1 of 7 24-CV-00846 David Allen et al v. Feeney Property Maintenance, LLC et al Mr. Feeney dug some test pits during the spring of 2023, but did not begin work in earnest until the summer, on account of difficult weather and some prior commitments. Mr. Feeney hired Mr. Johnson as a subcontractor to assist with the work, because they had worked together in the past, and because Mr. Johnson had access to large excavation equipment. Defendants began working on the site, and Mr. Feeney submitted period invoices to plaintiffs, which they paid. After at least some work had begun, however, plaintiffs changed the location of the housesite again, moving the house further up the hill. Although the change did not appear dramatic on an overhead map, there was a substantial grade involved, and the change had material consequences from a site-preparation perspective. Defendants had to clear more trees, dig more stumps, adjust the location of the driveway, and adjust the location of the leach filed. The parties did not discuss whether the location change would affect the estimate. By the fall of 2023, plaintiffs felt that the project was proceeding slowly. Plaintiffs also felt that the project was becoming costly, as the amount paid began to approach the amount of the verbal estimate, even though the work was only partly completed. During a conversation in October 2023, Mr. Feeney told plaintiffs that the overall cost would exceed the verbal estimate. At some point during the fall of 2023, plaintiffs attempted to expedite the work by approaching Mr. Johnson directly and asking him to take over the project. He declined, but during the ensuing conversations, plaintiffs arranged for Mr. Johnson to submit his invoices directly to them for payment. After receiving those invoices, plaintiffs began scrutinizing them and comparing them to the invoices submitted by Mr. Feeney, and further comparing them to their own notes and observations. Plaintiffs became convinced that the invoices contained substantial errors and overcharges. Plaintiffs confronted both defendants during a meeting at the Barnard General Store in January 2024. After that meeting, plaintiffs remained unsatisfied, and refused to pay several invoices submitted by both defendants. Mr. Johnson’s invoices became a central issue. They contain only a few lines of information: typically, there is a line identifying the number of hours spent on labor, at a rate of $50 per hour, and a few additional lines of information identifying the number of hours spent on a few different types of heavy equipment, ranging from $75 per hour for a dump truck to $120 per hour for a large excavator. Plaintiffs’ contention is that the number of hours on the invoices are inaccurate. Mr. Johnson’s invoices are complicated, however, in that the number of hours indicated on the invoices does not reflect the number of hours actually spent performing each task, but rather include a series of calculations and adjustments meant to capture the cost of running the equipment and his profit margin. Mr. Johnson explained these calculations during the evidentiary hearing, and the court was persuaded by his explanation. Essentially, he owns the excavation equipment, and charges different rates for the use of the equipment depending upon whether is operating the equipment or someone else is operating the equipment. If he is operating the equipment, he charges for the use of the machine plus his own time. If someone else is operating the equipment, charges only for the use of the machine. Either way, he also charges a markup, for profit. For example, for the use of the large excavator, Mr. Johnson charges $120 per hour if he is the one using the machine, and he charges $90 per hour if someone else is using the excavator. One period of time reflected by the evidence involved Mr. Johnson using the excavator for 0.9 hours, and someone else using the excavator for 19 hours. For this period of time, the use of the excavator was billed 0.9 hours at $120 per hour and 19 hours at $90 per hour, plus a 10% markup for profit, which totals about $2,000. Order Page 2 of 7 24-CV-00846 David Allen et al v. Feeney Property Maintenance, LLC et al Mr. Johnson reflects this information on his invoices, however, by making adjustments to the number of hours, instead of including multiple lines of information. In other words, using the numbers from the above example, he charged $120 per hour for the use of the excavator regardless of who was using the equipment, and accounted for his own time in full, but discounted by 25% the number of hours in which the equipment was used by another operator. He therefore calculated the number of hours as 0.9 plus 14.3 (which is 19 hours * 75%, rounded up), and then multiplied that sum by 1.1 in order to account for his profit markup. Mr. Johnson’s actual invoice, therefore, shows 16.7 hours on the excavator at the rate of $120 per hour, which comes out nearly the same as the different method of calculation above (a few dollars’ difference is attributable to rounding). Mr. Feeney also billed plaintiffs for the time that he and his son spent working on the project. Mr. Feeney billed different rates for his time and for his son’s time, and at least some of their time was spent operating Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brastex Corporation v. Allen International, Inc.
702 F.2d 326 (Second Circuit, 1983)
Birchwood Land Company, Inc. v. Ormond Bushey & Sons, Inc.
2013 VT 60 (Supreme Court of Vermont, 2013)
VanVelsor v. Dzewaltowski
385 A.2d 1102 (Supreme Court of Vermont, 1978)
In Re Rainbow Trust
216 B.R. 77 (Second Circuit, 1997)
Naylor v. Cusson
412 B.R. 646 (D. Vermont, 2009)
Terranova v. Avco Financial Services of Barre, Inc.
396 F. Supp. 1402 (D. Vermont, 1975)
Wharton v. Tri-State Drilling & Boring
2003 VT 19 (Supreme Court of Vermont, 2003)
In Re Ahokas
361 B.R. 54 (D. Vermont, 2007)
CASS-WARNER CORPORATION v. Brickman
229 A.2d 309 (Supreme Court of Vermont, 1967)
Filter Equipment Co. v. International Business MacHines Corp.
458 A.2d 1091 (Supreme Court of Vermont, 1983)
BATTENKILL CONSTRUCTION COMPANY, INC. v. Haig's, Inc.
346 A.2d 213 (Supreme Court of Vermont, 1975)
TROMBLY PLUMBING & HEATING v. Quinn
2011 VT 70 (Supreme Court of Vermont, 2011)
Newport Sand & Gravel Co. v. Miller Concrete Construction, Inc.
614 A.2d 395 (Supreme Court of Vermont, 1992)
VERMONT STRUCTURAL STEEL CORPORATION v. Brickman
236 A.2d 658 (Supreme Court of Vermont, 1967)
Ruggieri-Lam v. Oliver Block, LLC
120 F. Supp. 3d 400 (D. Vermont, 2015)
State v. Glens Falls Insurance
365 A.2d 243 (Supreme Court of Vermont, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
Allen v. Feeney Property, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allen-v-feeney-property-vtsuperct-2024.