CASS-WARNER CORPORATION v. Brickman

229 A.2d 309, 126 Vt. 329, 1967 Vt. LEXIS 193
CourtSupreme Court of Vermont
DecidedFebruary 7, 1967
Docket370, 371
StatusPublished
Cited by18 cases

This text of 229 A.2d 309 (CASS-WARNER CORPORATION v. Brickman) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CASS-WARNER CORPORATION v. Brickman, 229 A.2d 309, 126 Vt. 329, 1967 Vt. LEXIS 193 (Vt. 1967).

Opinion

Keyser, J.

Cass-Warner Corporation brought suit (No. 370) to recover a balance claimed to be due for labor and materials furnished to defendants, Brickmans, for the construction of a marina. Thereafter, the Brickmans brought a counter-suit (No. 371) seeking damages for alleged improper and defective work done by Cass-Warner “under an agreement.” The cases were consolidated for trial by agreement of counsel. Hearing was by court. Findings of fact were made by the trial court applicable to both cases. Each party has appealed, claiming the evidence does not support certain specified findings of fact on which the single judgment order pertaining to both cases is founded.

The work to be done consisted principally of dr edging, the harbor to deepen the channel, the construction of a bulkhead to retain the dredged material and the construction, upon piling, of a dock leading from the bulkhead into the lake. There is no dispute concerning the *331 work being done or the equipment and materials being furnished by Cass-Warner at the request of the Brickmans under an oral agreement. Cass-Warner claims the contract provided that it was to do the work upon a time and materials basis, billing weekly at an agreed fixed rate for labor and machines and at a cost plus ten per cent for materials.

Cass-Warner declared on the common counts and filed specifications of its claim which included a copy of each weekly invoice rendered to the Brickmans. The evidence shows work began on May 2, 1964 but ceased on June 23, 1964 at the direction of the Brickmans because they did not have the money to continue the work. At that time the bulkhead was constructed but not completely filled nor aligned, the dock had not been completed and the harbor only partially dredged. There is no dispute but that the Brickmans had paid the invoices for the first three weeks ending May 23, aggregating $7,918.32 and had not paid the invoices of June 3, 8, 15 and 23 amounting to $15,320.80.

In their counter-suit the Brickmans allege Cass-Warner Corporation “entered into an agreement whereby, in return for payment therefor, by the plaintiffs,” it agreed to design and construct a 300-foot bulkhead, dredge certain areas placing the material behind the bulkhead and drive pilings along the face of a pier for a landing platform. They also allege the bulkhead was inadequate and must be reconstructed or reinforced, the dredging was not done to the depths agreed upon, and the pilings were driven in an irregular and uneven manner and claimed the reasonable value of the work, if properly performed and completed, would have been $10,400.00, They make no claim in their writ that the agreement provided the work was to be done as a completed job for a total fixed price, payable in installments.

Cass-Warner’s declaration is in general assumpsit on the common counts with specifications based on the contract it claims was made with the Brickmans. Such procedure in this case is proper under the circumstances disclosed by the record.

In the case of Boville v. Dalton Paper Mills, 86 Vt. 305, 85 Atl. 623 the declaration was in assumpsit and consisted of the common counts and one special count alleging an express contract, partial performance by plaintiff, and a breach by defendant preventing further performance. Upon motion by defendant that plaintiff elect which count he would stand on, the plaintiff elected to proceed under the common counts. The evidence tended to show a contract for doing *332 the work covered by plaintiff’s specifications at agreed prices; payment to be made on the 15th of each month for work done the previous month; and failure of defendant to pay as agreed. The court there said:

“It is the uniform holding of our cases that one may recover under the common counts for work done under a special contract which he has been compelled to abandon by the nonperformance of the other party. Of these cases reference may be had to Chamberlain v. Scott, 33 Vt. 80; Davis v. Streeter, 75 Vt. 214, 54 Atl. 185.”

Here, the action of Cass-Warner is not to recover damages for an unwarranted breach of contract for a completed project. Rather, it is a suit to recover for the work actually performed and materials actually furnished at the express request of the Brickmans, the same to be paid for each week under rates agreed to by the parties. See Curtis v. Smith, 48 Vt. 116, 119, 120.

In Peist v. Richmond, 97 Vt. 122 Atl. 420, Judge Powers said: “This right of abandonment is, not infrequently, spoken of as the right of rescission. . . . (I)t differs from the right of rescission in that the contract may still be resorted to by the party not in default for the recovery of his damages. (Citing cases).”

Moreover, any objection to the action being in general, rather than special, assumpsit is one that can be waived, and was waived by not being made on trial, for it does not go to' the jurisdiction, but only to a matter of pleading and practice. This also applies to the form of action. Valiquette v. Clark Bros. Coal Min. Co., 83 Vt. 538, 543, 77 Atl. 869.

The pivotal issue raised by the appeal of Cass-Warner Corporation is whether the work was agreed to be done on a time and materials basis and, if so, whether the court properly used the “reasonable value” for the work done in determining plaintiff’s damages.

These issues bear heavily on the first finding of the court which reads:

“1. There being no controversy relative to the specifications submitted in the case of Cass-Warner v. Brickman, Docket No. 10,024, the court finds that the specifications submitted by the plaintiff in that case are proper and that, in fact, have not been fully paid, and that there is a balance due therein of $15,320.80 as of June 3, 1964.”

*333 (From the record it is very obvious that the date should be June 23, not June 3 as shown in the foregoing finding, and we so treat it.)

Findings of fact must stand if there is any evidence fairly and reasonably tending to support them. 12 V.S.A. §2385. This court must affirm the findings if there is any credible evidence to support them. The weight of the evidence, the credibility of the witnesses and the persuasive effect of the testimony lies solely with the trier of facts. Smith v. Lentini, Extr., 125 Vt. 526, 528, 220 A.2d 291.

Finding No. 1 is a general finding by the court made at the very outset of its Findings of Fact. A general finding in favor of one party or another is a finding of every special fact necessary to sustain it and conclusive as to such facts, if there is evidence to support a finding of their existence. 5A C.J.S. p. 476, §1656(5), note 10; Platt v. Woodland, 121 Kan. 291, 246 P. 1017. Rain v. Balph, Old, 293 P.2d 359, 360-361; Smart v. Billings, 169 Old.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Master Plumbing v. Barlow
Vermont Superior Court, 2024
Allen v. Feeney Property
Vermont Superior Court, 2024
ALBERINO v. Balch
2008 VT 130 (Supreme Court of Vermont, 2008)
Marshall Contractors, Inc. v. Brown University
692 A.2d 665 (Supreme Court of Rhode Island, 1997)
In Re Estate of Adams
587 A.2d 958 (Supreme Court of Vermont, 1990)
State v. Parker
583 A.2d 1275 (Supreme Court of Vermont, 1990)
Greene v. Rainbow Properties, Ltd.
496 A.2d 178 (Supreme Court of Vermont, 1985)
LaRose v. Department of Employment Security
431 A.2d 1240 (Supreme Court of Vermont, 1981)
Gardner v. West-Col, Inc.
392 A.2d 383 (Supreme Court of Vermont, 1978)
Grady v. Union School District No. 32
367 A.2d 690 (Supreme Court of Vermont, 1976)
Williams v. Carter
285 A.2d 735 (Supreme Court of Vermont, 1971)
State Highway Board v. Jackson
276 A.2d 620 (Supreme Court of Vermont, 1971)
In Re Proceedings Concerning a Neglected Child
276 A.2d 14 (Supreme Court of Vermont, 1971)
In Re Heath
266 A.2d 812 (Supreme Court of Vermont, 1970)
Forcier v. Grand Union Stores, Inc.
264 A.2d 796 (Supreme Court of Vermont, 1970)
Pioneer Credit Corporation v. Carden
245 A.2d 891 (Supreme Court of Vermont, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
229 A.2d 309, 126 Vt. 329, 1967 Vt. LEXIS 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cass-warner-corporation-v-brickman-vt-1967.