Marshall Contractors, Inc. v. Brown University

692 A.2d 665, 1997 R.I. LEXIS 116, 1997 WL 164159
CourtSupreme Court of Rhode Island
DecidedApril 3, 1997
Docket94-505-Appeal
StatusPublished
Cited by33 cases

This text of 692 A.2d 665 (Marshall Contractors, Inc. v. Brown University) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marshall Contractors, Inc. v. Brown University, 692 A.2d 665, 1997 R.I. LEXIS 116, 1997 WL 164159 (R.I. 1997).

Opinion

OPINION

BOURCIER, Justice.

The plaintiff, Marshall Contractors, Inc. (Marshall), appeals from the entry of final judgment in the Superior Court in favor of the defendant, Brown University (Brown). The Superior Court litigation, tried before a jury, concerned a dispute over payment for the construction of the Paul Bailey Pizzitola Memorial Sports Facility on Lloyd Avenue in the city of Providence. In this appeal Marshall alleges a number of trial court errors. Because we conclude that the trial justice erred in finding that a contract, implied-in-fact, “on the essential terms of the contract” had resulted from ongoing contract negotiations between the parties, we reverse the trial court judgment and need not address Marshall’s other claims of error. The facts pertinent to our conclusion are as noted.

I

On April 11, 1986, Brown’s director of physical planning, Carol Wooten (Wooten), *666 requested Marshall, along with three other general contractors, to submit design and construction proposals for a new university sports complex facility to replace its time honored but age weaiy Marvel Gymnasium. At that time Brown estimated that the basic building’s construction cost would be $4.5 million.

On August 5, 1986, Marshall submitted its design/build proposal to Brown with a bare construction cost of $4,627,134 or $61.50 per square foot in accordance with the scope of work then outlined in Marshall’s proposal. Marshall’s proposal was selected by Brown, and on May 12,1987, Brown authorized Marshall to proceed with formal design development of its proposal. In addition, Brown authorized Marshall to commence site work and to relocate utilities at the budding site although no formal contract had yet been executed in order to accommodate the project’s so-called fast track construction schedule plan.

The formal design development work resulted eventually in the final design construction plans for the project and, on October 19, 1987, Brown, in a letter from E.F. Wallace, director of its department of purchases, informed Marshall of Brown’s intention to enter into a contract with Marshall for the base construction sum of $6,988,114. On November 11, 1987, Brown in a letter from its associate director of physical planning, Edward J. Luppi, authorized Marshall to proceed with the construction of the new sports facility and reflected changes in the construction plans that increased the contract basis of compensation to $7,157,051.

In that letter of intent Luppi notified Marshall that

“[w]e would also like to list the items accepted or agreed upon since the Letter of Intent, whose value added to the 19 October letter will become the contract basis of compensation. Any changes from this point forward shall become a Change Order to the forthcoming contract.”

That November 11, 1987 final letter of intent also noted that there would be a “forthcoming” formal contract for the project based on the $7,157,051 figure.

Unfortunately, no forthcoming -written construction contract, ready for signature execution, ever emerged from the ongoing contract negotiations between the parties because of their constant disagreement over what the “scope” of the project included, was intended to be, or how it was to be defined. Resolution and agreement on that scope of project item was central to the contract negotiations especially in light of Brown’s November 11, 1987 letter of intent fixing a $7,157,051 limit on the project cost.

Complicating the continuing disagreements between the parties during the ongoing construction were the varied, but many change orders that were submitted by Marshall for work it claimed was not included in the scope of the project as well as billings by Marshall for “extras” that it believed were also not included within that scope. The crucial importance in all of that scope jousting is that each party had its own separate belief of what the project scope actually encompassed, and that mutual misunderstanding was never mutually resolved.

Marshall, apparently dismayed by the ongoing project scope disagreements, and expecting to resolve the ongoing dispute over what constituted the scope of the project, forwarded Brown a document entitled “Standard Form of Agreement Between Owner and Design/Builder” for Brown’s approval. That proposed agreement was intended to be the formal contract for the project, and included what Marshall believed to be the definition of the scope of the project. Brown, however, rejected the proposed form contract as submitted, and instead proposed changes therein relating to overtime labor costs, time of payments due for work, and most significantly, the form contract’s definition of scope of the project. The parties, while each wanting to execute a formal contract, could simply not agree upon what certainly had to be one of its most important provisions, namely, the scope of the project, in light of Brown’s stated monetary limitation on what it wanted to spend for the total project. Despite that inability of the parties to reconcile their differences over the terms to be included in the project contract, construction nonetheless continued without interruption. As that con- *667 struetion neared completion, Marshall, on January 17, 1989, wrote to then university president Howard Swearer (Swearer) in an attempt to resolve the scope-billing disagreements that had by that time accumulated to close to $1 million. Marshall, in its letter, advised Swearer that the projected final cost to Brown would be $8,674,811, of which $881,499 involved disputed work change orders that Brown had claimed were all included within the original scope of the project. Marshall requested to meet with Swearer and resolve the scope of project and billing problems. All attempts to do so, however, met with little, if any, success. Finally, on November 3, 1989, Marshall filed a civil action against Brown in the Providence County Superior Court seeking to recover for the construction costs that it believed were not included within the original scope of the project.

In its civil action, Marshall sought recovery for the cost of construction work furnished during the construction of the sports facility that it believed was not originally included in the scope of the project. It alleged in its three count complaint, claims for unjust enrichment (count 1), quantum meruit (count 2), and “wilful and intentional bad faith and coercion” (count 3). Brown, answering Marshall’s complaint, asserted that a contract had in fact materialized between the parties in which they had mutually agreed to a lump sum of $7,157,051 for the scope of the project and that it had complied with its financial obligations required by that contract. Marshall, in its complaint, requested a trial by jury. It got what it requested, but it did not get what it expected, and as a result its appeal from the final judgment in favor of Brown is now before us.

II

Prior to the commencement of the jury trial on Marshall’s complaint in the Superior Court, the parties on April 9, 1993 met with the trial justice and agreed that the first disputed issue that should be litigated was whether any contract had in fact been agreed upon by the parties. For that specified purpose, the trial justice bifurcated the trial, taking up first, without a jury, the question of whether a contract had come into existence between the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wild Horse Concepts, LLC v. Hasbro, Inc.
Supreme Court of Rhode Island, 2023
Choi v. Brown University
D. Rhode Island, 2021
Biller v. S-H OPCO Greenwich Bay Manor
961 F.3d 502 (First Circuit, 2020)
Haddad v. Bryant University
D. Rhode Island, 2019
Mathew M. Cote v. John Aiello
148 A.3d 537 (Supreme Court of Rhode Island, 2016)
In re IDC Clambakes, Inc.
510 B.R. 678 (D. Rhode Island, 2014)
Haviland v. Simmons
45 A.3d 1246 (Supreme Court of Rhode Island, 2012)
Washburn v. Trombino's Folly
Superior Court of Rhode Island, 2011
Drumm v. CVS Pharmacy, Inc.
701 F. Supp. 2d 200 (D. Rhode Island, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
692 A.2d 665, 1997 R.I. LEXIS 116, 1997 WL 164159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marshall-contractors-inc-v-brown-university-ri-1997.