J. Koury Steel Erectors, Inc. of Massachusetts v. San-Vel Concrete Corp.

387 A.2d 694, 120 R.I. 360, 1978 R.I. LEXIS 668
CourtSupreme Court of Rhode Island
DecidedJune 28, 1978
Docket76-418-Appeal
StatusPublished
Cited by33 cases

This text of 387 A.2d 694 (J. Koury Steel Erectors, Inc. of Massachusetts v. San-Vel Concrete Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Koury Steel Erectors, Inc. of Massachusetts v. San-Vel Concrete Corp., 387 A.2d 694, 120 R.I. 360, 1978 R.I. LEXIS 668 (R.I. 1978).

Opinion

*361 Bevilacqua, C.J.

This is an appeal from a judgment of the Superior Court finding that the plaintiff had failed to *362 establish the essential elements of a valid and enforceable contract. The trial was conducted before a judge sitting without a jury. The plaintiff has now appealed to this court.

The controversy arises out of a construction project known as the “New Bedford Parking Garage.” In April 1974, Douglas Cringan, the contract manager for defendant San-Vel Concrete Corporation (San-Vel), forwarded invitations to bid to various steel erectors including plaintiff J. Koury Steel Erectors, Inc. of Massachusetts. At that time, San-Vel was interested in bidding on a subcontract for the supply and erection of precast concrete components to be used in said project.

On April 12, 1974, John E. Koury, president of plaintiff corporation, telephoned a bid to San-Vel in the amount of $170,000. Four days later, on April 16, Cringan telephoned Mr. Koury and informed him that his bid was very low. Subsequently, plaintiff submitted a revised bid for the sum of $200,000 which was included by San-Vel in its bid to the general contractor Peabody Construction.

Mr. Koury testified that on April 16, 1974 Cringan informed him that if San-Vel received the job, plaintiff would be awarded the steel construction work. Cringan’s version of the conversations contradicted the statements made by Mr. Koury. Cringan stated that he lacked the authority to award any contracts since such power was vested in Mr. Roy, president of San-Vel. A deposition taken from Mr. Roy corroborated his testimony. It is uncontro-verted that sometime later, Cringan apprised Mr. Koury of a so-called “piece” change in the construction specifications and plaintiff reduced its revised bid to $190,000. On August 20, 1974, Cringan requested a meeting with plaintiff to discuss sequencing 1 the work and materials for the project. A sequencing meeting was held on September 13, 1974 at which time plaintiff requested that defendant perform some *363 dry-packing and grouting. Cringan testified that the sequencing meeting with plaintiff was insignificant because he had conducted similar meetings with several other bidders.

In a conversation with Cringan on September 19, 1974, Mr. Koury confirmed his bid of $190,000, and also confirmed that defendant would perform all the dry-packing and grouting work. The parties however did not agree upon a price for that work. Instead, Cringan told Mr. Koury that he would “get back” to him. Mr. Koury testified that he made several unsuccessful attempts to contact Cringan in order to discuss the progress of the negotiations. On October 14, 1974, Cringan told Mr. Koury that he was no longer responsible for the sub-contracting and informed him that the contract had been awarded by Mr. Roy to General Gansett Steel Erectors Corporation for $177,500. Cringan denied accepting plaintiff s bid and avowed that his dealings with plaintiff typified ordinary negotiation sessions.

After reviewing all the evidence and drawing the reasonable inferences therefrom, the trial justice found the testimony of Mr. Koury to be incredible and unpersuasive. The plaintiff admits in its brief that Mr. Koury only “thought” or “felt” he had the job. The trial justice commented that a notation in Mr. Koury’s handwriting addressed to Edward Prescott, an estimator for plaintiff, stating “Ed — we’ve got the job 99% (sure) (till we see con tract/)” belied Mr. Koury’s statement that he was convinced that he had been awarded the contract. The trial justice did not believe Mr. Koury’s explanation that he did not trust anyone until a written contract was actually signed. He did, however, believe the testimony of Mr. Cringan, defendant’s witness, particularly noting Cringan’s statement that he had never told Mr. Koury or Mr. Prescott that plaintiff would receive the job or that its bid would be accepted.

I

The plaintiff contends that the trial justice was clearly wrong, that he overlooked and misconceived material evi *364 dence presented by plaintiff and afforded undue weight to defendant’s evidence. We find no merit in this argument. It is well settled that where parties have submitted their cause to a trial justice sitting without a jury, the findings of fact of the trial justice will be given great weight. Rego Displays, Inc. v. Fournier, 119 R.I. 469, 379 A.2d 1098 (1977); Flynn v. Burkhardt, 118 R.I. 69, 371 A.2d 1057 (1977), and will not be disturbed on appeal unless it can be shown that such findings are clearly wrong or that the trial justice misconceived or overlooked material evidence. Rehab v. Lemenski, 115 R.I. 576, 350 A.2d 397 (1976); Barattini v. McGovern, 110 R.I. 360, 292 A.2d 860 (1972). This same rule applies to inferences drawn by the trier of fact. Coutanche v. Larivierre, 107 R.I. 1, 164 A.2d (1970).

In the instant case the testimony is in conflict. The trial justice specifically rejected the testimony of Mr. Koury and Mr. Prescott and accepted as truthful and reliable the testimony of Cringan and Mr. Roy. The plaintiffs argument on appeal is essentially that the testimony of its witnesses rather than that of defendant’s should have been believed. That argument may be properly addressed to the factfinder at trial. However, it is inapropriate in appellate proceedings. Fournier v. Ward, 111 R.I. 467, 306 A.2d 802 (1973); Marstan Corp. v. Centreville Realty Co., 106 R.I. 36, 256 A.2d 26 (1969).

II

The plaintiff also alleges that the trial justice erred in failing to find that defendant had entered into an express or an implied contract with plaintiff during 1974. 2 We disagree. The distinction between an express or an implied contract is not based upon legal effect but upon the way in which *365 mutual assent is manifested. 1 Williston, Contracts §3 (3d ed. 1957). In an expressed contract the terms and conditions of the contract are assented to orally or in writing by the parties.

In Bailey v. West, 105 R.I. 61, 249 A.2d 414 (1969), this court held that the elements of a contract “implied in fact” are as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dolan v. McQuaide
79 A.3d 394 (Court of Special Appeals of Maryland, 2013)
Haviland v. Simmons
45 A.3d 1246 (Supreme Court of Rhode Island, 2012)
Providence Metallizing Co. v. Tristar Products, Inc.
717 F. Supp. 2d 227 (D. Rhode Island, 2010)
The Cadillac Lounge v. McAteer, Pc
Superior Court of Rhode Island, 2007
Opella v. Opella
896 A.2d 714 (Supreme Court of Rhode Island, 2006)
Mills v. Rhode Island Hospital
828 A.2d 526 (Supreme Court of Rhode Island, 2003)
Rhode Island Insurers' Insolvency Fund v. Leviton Manufacturing Co.
763 A.2d 590 (Supreme Court of Rhode Island, 2000)
Stanley-Bostitch, Inc. v. Regenerative Environmental Equipment Co.
697 A.2d 323 (Supreme Court of Rhode Island, 1997)
Marshall Contractors, Inc. v. Brown University
692 A.2d 665 (Supreme Court of Rhode Island, 1997)
Grossman's, Inc. v. Genuario, 92-157 (1996)
Superior Court of Rhode Island, 1996
Chester v. aRUSSO
667 A.2d 519 (Supreme Court of Rhode Island, 1995)
Shell v. K.E.M.
First Circuit, 1995
Kaskiewicz v. East Bay Ins., Ltd.
641 A.2d 48 (Supreme Court of Rhode Island, 1994)
Computer Shoppe, Inc. v. State
780 S.W.2d 729 (Court of Appeals of Tennessee, 1989)
Daley v. Solomon
559 A.2d 648 (Supreme Court of Rhode Island, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
387 A.2d 694, 120 R.I. 360, 1978 R.I. LEXIS 668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-koury-steel-erectors-inc-of-massachusetts-v-san-vel-concrete-corp-ri-1978.