Grossman's, Inc. v. Genuario, 92-157 (1996)

CourtSuperior Court of Rhode Island
DecidedMarch 19, 1996
DocketNos. KC 92-157, KC 92-158
StatusPublished

This text of Grossman's, Inc. v. Genuario, 92-157 (1996) (Grossman's, Inc. v. Genuario, 92-157 (1996)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grossman's, Inc. v. Genuario, 92-157 (1996), (R.I. Ct. App. 1996).

Opinion

DECISION
These two matters were consolidated and heard by the Court without a jury. Rule 52(a) of the Rules of Civil Procedure requires the court sitting without a jury to find the facts specially, and to separately state its conclusions of law thereon. Decision, reserved pending the filing and review of proposed findings of fact and post-trial memoranda, is rendered herein.

FACTS AND PROCEDURAL HISTORY
Both of these matters relate to materials provided for and construction upon a premises located on Sandy Lane in Warwick, a site owned by defendant Serafino Genuario (hereinafter referred to as Genuario) and chosen by him, at least in part, for relocation of his photography studio (hereinafter referred to as the construction site). Civil action number KC 92-157 is a petition to enforce a materialman's lien for the sum of $18,282.78 filed by Grossman's, Inc. (hereinafter referred to as Grossman's) against Genuario for construction materials delivered by Grossman's to the construction site. Jurisdiction is pursuant to General Laws 1956 (1984 Reenactment) § 34-28-10. Civil action number KC 92-158 is a contract claim for the same amount, $18,272.78, owed to Grossman's by the defendant contractor Frank A. Tortolani (hereinafter referred to as Tortolani) for the same construction materials delivered by Grossman's and accepted by Tortolani at the construction site. After these two matters were consolidated, Tortolani crossclaimed against Genuario for the sum of $30,699.33 on theories of breach of contract and quantum meruit. In April of 1995, by agreement of the parties, Genuario, pursuant to G.L. § 34-28-17, deposited the sum of $25,178.58 in cash in the Registry of Court in return for Grossman's release of the Notice of Lis Pendens. Jurisdiction is pursuant to G.L. 1956 (1985 Reenactment) § 8-2-14.

After thorough review of the evidence and testimony, the Court finds the following facts:

1. Tortolani is a general contractor with over twenty-five (25) years experience in residential and commercial renovation and new construction.

2. On or about November 1, 1990, Tortolani submitted a proposal to Genuario for certain construction work.

3. The fair and reasonable cost of the construction was $108,260.00.

4. On or before August 1, 1991, Genuario filled out a Building Permit Application, delivered and paid for it. The Application was for $108,000.00 of construction work.

5. On or about August 1, 1991, Tortolani commenced work at the construction site.

6. At no time during the project did Genuario have the funds available to complete the construction project.

7. The agreement between Tortolani and Genuario provided for two progress payments of $40,000.00 and a final payment for the balance.

8. On or about August 30, 1991, Genuario tendered a check in the sum of $40,000.00 to Tortolani.

9. During the course of construction, which proceeded from August through October, Tortolani performed extra construction work, not encompassed by the original proposal, at the request of, and for the benefit of Genuario.

10. Tortolani and Genuario discussed the extra work some time in early November when Tortolani requested the second $40,000 payment.

11. After Tortolani showed Genuario his log and list of extra work, Genuario, in response, directed that no further extra work be done.

12. In early November, Genuario admitted to Tortolani that he did not have the funds to complete the project.

13. On or about November 8, 1991, Genuario agreed upon an alternate payment plan of $10,000.00 per week for four weeks.

14. Pursuant thereto, on or about November 8, 1991, Genuario tendered a check to Tortolani in the sum of $10,000.

15. When the next weekly installment, due on or about November 15, 1991, was not paid, Tortolani removed his workers from the site and stopped performance.

16. As a result of a meeting between Genuario and Tortolani in late November, Genuario tendered a check to Tortolani in the sum of $16,400.00 comprising approximately $15,000.00 for extra work performed, plus a $1,400.00 payment on a second revised payment schedule of $1400.00 per week.

17. There were insufficient funds at Citizens Bank when Tortolani tried to cash said check.

18. On November 15, 1991, Genuario stopped payment on the check and terminated Tortolani's services.

19. Tortolani expended or incurred the following amounts for labor and materials at the construction site:

    Materials:

Other than Grossman's $ 8,821.15 Grossman's 19,270.70 _________ TOTAL MATERIALS $28,091.85

Subcontractor Paid:

Dan Robataille (Ex. T-M) $ 500.00 Joe Kenney (Ex. T-N) 300.00 Jim Facer (Ex. T-O) 1,900.00 ________ TOTAL PAID SUBCONTRACTORS $ 2,700.00

Labor Paid:

N.E.E.D. Payroll (Ex. T-P) $ 12,609.00 Carl Smith (checks 2 wks) (Ex. T-Q) 970.00 Carl Smith (cash 1st 2 wks.) 800.00 _________ $ 14,379.00

Overtime Paid:

Carl Smith $ 924.50 Joe Kenney 639.50 ________ $ 1.564.00

TOTAL PAID LABOR AND OVERTIME $15,943.00

TOTAL RENTAL (Heavy Equipment): $ 6,160.00 _________ TOTAL JOB COST $52,894.85

20. Tortolani is entitled to reasonable profit and overhead calculated on a percentage of his costs.

21. A reasonable overhead allowance is twenty (20%) percent of cost; a reasonable profit margin of ten (10%) percent.

22. Tortolani is owed for work performed in the sum of $19,821.20 calculated as follows:

    Total Job Cost:                          $52,894.85
        Overhead @ 20%                        10,578.97
                                              _________
                                             $63,473.82
    Profit @ 10%                               6,347.38
                                              _________
                                             $69,821.20
    Less: Payments made                       50,000.00
                                              _________
                                             $19,821.20

23. Tortolani was wrongfully terminated from the job by Genuario.

24. Tortolani is entitled to the profit he would have earned if he had been allowed to complete the project.

25. The reasonable profit on the balance of the work is $6,637.37 calculated as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rhode Island Turnpike & Bridge Authority v. Bethlehem Steel Corp.
379 A.2d 344 (Supreme Court of Rhode Island, 1977)
Smith v. Boyd
553 A.2d 131 (Supreme Court of Rhode Island, 1989)
J. Koury Steel Erectors, Inc. of Massachusetts v. San-Vel Concrete Corp.
387 A.2d 694 (Supreme Court of Rhode Island, 1978)
Art Metal Construction Co. v. Knight
185 A. 136 (Supreme Court of Rhode Island, 1936)
Field v. Consolidated Mineral Water Co.
55 A. 757 (Supreme Court of Rhode Island, 1903)
F. D. Mckendall Lumber Co. v. Didonato
82 A.2d 403 (Supreme Court of Rhode Island, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
Grossman's, Inc. v. Genuario, 92-157 (1996), Counsel Stack Legal Research, https://law.counselstack.com/opinion/grossmans-inc-v-genuario-92-157-1996-risuperct-1996.