Master Plumbing v. Barlow

CourtVermont Superior Court
DecidedJuly 25, 2024
Docket23-cv-5342
StatusPublished

This text of Master Plumbing v. Barlow (Master Plumbing v. Barlow) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Master Plumbing v. Barlow, (Vt. Ct. App. 2024).

Opinion

VERMONT SUPERIOR COURT CIVIL DIVISION Windsor Unit Case No. 23-CV-05243 12 The Green Woodstock VT 05091 802-457-2121 www.vermontjudiciary.org

Master Plumbing and Heating, Inc. Plaintiff

v.

Trevor Barlow and Sheryl Backstrom Defendants

Decision on Motion for Writ of Attachment

Defendants Trevor Barlow and Sheryl Backstrom are the owners of a commercial building in Cavendish, Vermont. Prior to the floods of 2023, defendants contracted with plaintiff Master Plumbing and Heating, Inc. for plumbing renovations at the commercial building. Shortly after the work began, the building was devastated by floodwaters, and defendants asked plaintiff to assist with repairing the heating system. After plaintiff performed at least some work on a time-and-materials basis, defendants paid two invoices but refused to pay more. Plaintiff asserted a lien against the property and filed the present civil action to enforce the lien. 9 V.S.A. § 1924. Generally, the purpose of the mechanic’s lien is to permit contractors and subcontractors to “secure the payment” for their home-improvement work on real property. 9 V.S.A. § 1921(a); Newport Sand and Gravel Co. v. Miller Concrete Constr., Inc., 159 Vt. 66, 69 (1992). A contractor or subcontractor may assert the lien by giving written notice to the property owner and by filing a written memorandum with the town clerk within a specified period of time. 9 V.S.A. §§ 1921(b) & 1923; In re Cusson, 412 B.R. 646, 654 (D. Vt. 2009). A contractor must thereafter commence a civil action and obtain an attachment “[w]ithin 180 days from the time of filing such memorandum.” 9 V.S.A. § 1924; Filter Equipment Co., Inc. v. International Business Machines Corp., 142 Vt. 499, 501–02 (1983); Cusson, 412 B.R. at 654; In re APC Construction, Inc., 132 B.R. 690, 694 (D. Vt. 1991). An attachment of real property is intended to be an “extraordinary remedy.” Brastex Corp. v. Allen International, Inc., 702 F.2d 326, 332 (2d Cir. 1983); Ruggieri-Lam v. Oliver Block LLC, 120 F.Supp.3d 400, 405 (D. Vt. 2015); Terranova v. AVCO Financial Services of Barre, Inc., 396 F.Supp. 1402, 1406–07 (D. Vt. 1975). Except under circumstances not present here, orders of approval are issued only after notice and an opportunity for a hearing, at which the moving party bears the burden of persuading the court that there is “a reasonable likelihood that the [movant] will recover judgment, including interests and costs, in an amount equal to or greater than the amount of the attachment over and above any liability insurance, bond, or other security shown by the [non-moving party] to be available to satisfy the judgment.” Vt. R. Civ. P. 4.1(b)(2); Ruggieri-Lam, 120 F.Supp.3d at 405; Troy Boiler Works, Inc. v. Long Falls Paperboard, LLC, 2021 WL 8694355 at *7 (D. Vt. Aug. 13, 2021). A Order Page 1 of 4 23-CV-05243 Master Plumbing and Heating, Inc. v. Trevor Barlow et al finding of a “reasonable likelihood” of success on the merits is intended to be “a realistic conclusion by the court on the basis of affidavits and other evidence presented at the hearing as to the actual probability of recovery by the [movant],” and the court must consider any modifying evidence and affirmative defenses offered by the non-moving party. Vt. R. Civ. P. 4.1, Reporter’s Notes—1973 Amendment; Ruggieri-Lam, 120 F.Supp.3d 400, 405–09 (D. Vt. 2015); Vermont Federal Credit Union v. Richter, No. 2013-354, 2014 WL 3714629 (Vt. Feb. 2014) (unpub. mem.); Wellford v. Eissmann, No. 747-10-09 Wrcv, 2010 WL 2259084 (Vt. Super. Ct. Mar. 9, 2010) (Eaton, J.); The McKernon Group, Inc. v. Felten, No. 737-10-08 Wrcv, 2009 WL 6356593 (Vt. Super. Ct. Jan. 16, 2009) (Eaton, J.). Here, the credible evidence presented at the motion hearing established the following facts. As mentioned, defendants contracted with plaintiff to perform plumbing renovations at a commercial building, but the 2023 floods devastated the building shortly after the work began. In particular, the floods ruined the heating system. During the chaotic aftermath of the floods, defendants talked with plaintiff’s representatives about installing a new heating system at the building. Plaintiff’s representatives made at least some representations that the cost of a new heating system would be reasonable, and that financial assistance was potentially available from Efficiency Vermont. Firm plans were not made, however, and plaintiff did not provide a formal estimate. Instead, plaintiff began work on the new heating system on a time-and-materials basis, and promised to provide an estimate when it became available. Plaintiff thereafter performed some wall penetrations and began preparing the building for a new system. Plaintiff submitted two invoices to defendants in the amount of $19,412.50, which defendants paid. Plaintiff then continued working, and submitted more invoices for an additional $39,609.04. At that point, defendants repeated their request for an estimate, and were told by plaintiff’s representative that the cost would be in the “ballpark” of $165,000. Defendants found this unreasonable, and further discovered that plaintiff had not contacted Efficiency Vermont, and that Efficiency Vermont would provide only limited financial assistance for the project. Defendants ordered plaintiff to stop work and refused to pay the outstanding invoices. Defendants then found a different contractor to install a different heating system for the price of about $50,000. Plaintiff thereafter asserted its lien and filed the present action for collection of the invoiced amounts. At issue is whether plaintiff has shown a “reasonable likelihood” that it will prevail at trial on its claim for breach of contract. Plaintiff offered evidence sufficient to establish that the parties entered into a time-and-materials contract for the installation of a heating system, that plaintiff performed work on that contract, that plaintiff submitted an invoice pursuant to the contract in the amount of $39,609.04, and that defendants refused to pay the amounts due. A claim for breach of a construction contract is established by that evidence. VanVelsor v. Dzewaltowski, 136 Vt. 103, 105–06 (1978); Cass-Warner Corp. v. Brickman, 126 Vt. 329, 336–37 (1967). Defendants argue that no contract was formed because the estimate was never provided and accepted, that the work performed by plaintiffs was in anticipation of a contract rather than in performance of it, and that the risk of contract failure in this situation should have been borne by plaintiff, rather than by defendants. It is generally true that contracts are not formed until there has been a meeting of the minds on the essential terms of the bargain, Sweet v. St. Pierre, 2018 VT 122, ¶¶ 13–15, 209 Vt. 1, and it is possible that, at a merits hearing, the court might see the evidence differently. Based upon the evidence presented at the attachment hearing, however, plaintiffs established by a preponderance of the evidence that the essential terms of a time-and-materials contract Order Page 2 of 4 23-CV-05243 Master Plumbing and Heating, Inc. v. Trevor Barlow et al were agreed upon, and that they involved the installation of a heating system for the cost of materials plus agreed-upon rates for time. 1 Bruner & O’Connor on Construction Law § 2:29. Although the terms of the contract were sparse, the court was persuaded by the chaotic circumstances surrounding the formation of the agreement, and by the evidence that defendants paid the first two invoices submitted by plaintiff for its work. For these reasons, even after taking defendants’ modifying evidence into account, Felten, No. 737-10-08 Wrcv, 2009 WL 6356593, the court finds that plaintiff has established a “reasonable likelihood” that it will prevail at trial on its claim for breach of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brastex Corporation v. Allen International, Inc.
702 F.2d 326 (Second Circuit, 1983)
Birchwood Land Company, Inc. v. Ormond Bushey & Sons, Inc.
2013 VT 60 (Supreme Court of Vermont, 2013)
VanVelsor v. Dzewaltowski
385 A.2d 1102 (Supreme Court of Vermont, 1978)
Naylor v. Cusson
412 B.R. 646 (D. Vermont, 2009)
Terranova v. Avco Financial Services of Barre, Inc.
396 F. Supp. 1402 (D. Vermont, 1975)
CASS-WARNER CORPORATION v. Brickman
229 A.2d 309 (Supreme Court of Vermont, 1967)
Filter Equipment Co. v. International Business MacHines Corp.
458 A.2d 1091 (Supreme Court of Vermont, 1983)
BATTENKILL CONSTRUCTION COMPANY, INC. v. Haig's, Inc.
346 A.2d 213 (Supreme Court of Vermont, 1975)
TROMBLY PLUMBING & HEATING v. Quinn
2011 VT 70 (Supreme Court of Vermont, 2011)
Newport Sand & Gravel Co. v. Miller Concrete Construction, Inc.
614 A.2d 395 (Supreme Court of Vermont, 1992)
Ruggieri-Lam v. Oliver Block, LLC
120 F. Supp. 3d 400 (D. Vermont, 2015)
Fletcher Hill, Inc. v. Crosbie
2005 VT 1 (Supreme Court of Vermont, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Master Plumbing v. Barlow, Counsel Stack Legal Research, https://law.counselstack.com/opinion/master-plumbing-v-barlow-vtsuperct-2024.