South Burlington School District v. Calcagni-Frazier-Zajchowski Architects, Inc.

410 A.2d 1359, 138 Vt. 33, 28 U.C.C. Rep. Serv. (West) 1382, 1980 Vt. LEXIS 1011
CourtSupreme Court of Vermont
DecidedJanuary 16, 1980
Docket110-79
StatusPublished
Cited by41 cases

This text of 410 A.2d 1359 (South Burlington School District v. Calcagni-Frazier-Zajchowski Architects, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Burlington School District v. Calcagni-Frazier-Zajchowski Architects, Inc., 410 A.2d 1359, 138 Vt. 33, 28 U.C.C. Rep. Serv. (West) 1382, 1980 Vt. LEXIS 1011 (Vt. 1980).

Opinion

Hill, J.

Plaintiff, South Burlington School District (South Burlington), appeals from the entry of a judgment order on verdicts directed in favor of each defendant at the close of plaintiff’s case. South Burlington claims that the trial court erred in taking the case from the jury and in support of its contention points to evidence in the record which it believes sufficiently raised issues of fact to be decided by the jury.

The relevant facts are as follows. On December 9, 1968, South Burlington contracted with Calcagni-Frazier-Zajchowski (CFZ), a partnership, 1 for the planning, design and construction of an addition to the Orchard Elementary School. CFZ drafted plans, and specifications were put out to bid. Although the original specifications called for a particular lightweight insulating roof fill, CFZ also included in the specifications an alternative calling for the use of a less expensive roofing system, Zonolite Dyzone, manufactured by defendant W. R. Grace & Company (Grace). The substitute roofing was added to the specifications in case South Burlington needed to trim costs to meet its budget after receiving the bids.

The specifications went out to bid and Kenclif Construction, Inc. (Kenclif) submitted the low bid. In order to reduce costs Kenclif and South Burlington agreed that the substitute Zonolite Dyzone system would be used. That system called for successive layers of materials, the base of which was a *39 precast structural deck. A one-inch thickness of Dyfoam vent board was then to be applied to the deck and the Zonolite lightweight concrete was to be placed to a specified thickness and profile on top of the Dyfoam vent board. The Zonolite insulating concrete was then to be covered by a built-up roofing. Kenclif subcontracted with Martin Fireproofing Corp. (Martin) for the installation of the Zonolite Dyzone insulating fill, and with A. C. Hathome Co., Inc. (Hathorne) for construction of the built-up roof. The insulation was laid by Martin on October 6, 7, and 8, 1969, and construction of the built-up roof, although originally scheduled to begin on October 15, 1969, was not commenced until the last few days of October. During the period between the scheduled commencement of construction of the built-up roof and the actual beginning of construction the roofing insulation was exposed to substantial precipitation.

In mid-May 1970, CFZ certified to South Burlington that the school addition was substantially complete. In February 1971, after the addition had been occupied, the roof split and leaking occurred. After repair efforts by the various defendants failed to remedy the problem, South Burlington hired an outside firm to correct the defects in the roof.

On July 3, 1974, South Burlington commenced this action against defendants CFZ, Kenclif, Hathome and Grace, alleging negligence, breach of contract, and breach of express and implied warranties in connection with the design and construction of the school roof. Numerous cross-claims were filed by the various defendants, and Martin was impleaded by CFZ and Kenclif as a third-party defendant. In addition, Hathorne counterclaimed against South Burlington for the value of repair work performed on the roof. 2

The trial court directed the verdicts at issue here ostensibly because South Burlington had failed to establish a prima facie case for relief. Plaintiff claims that the trial court erred in granting these motions since there is sufficient *40 •evidence in the record which fairly and reasonably tends to •support its claims, and that if there are any insufficiencies in the record it is because of the lower court’s errors in excluding evidence, particularly the testimony of plaintiff’s expert witness. We consider plaintiff’s claims in order.

I. Directed Verdicts

In considering a motion for a directed verdict, a trial court is “required to view the evidence in the light most favorable to the plaintiff, exclude the effect of modifying evidence, and resolve all conflicts against the defendants.” Waite v. Brown, 132 Vt. 20, 23, 312 A.2d 915, 915 (1973). If, after examining the evidence in this manner, it appears to the court that there is any substantial evidence which fairly and reasonably tends to support the plaintiff’s claim, the case should go to the jury for resolution. Burleson v. Caledonia Sand & Gravel Co., 127 Vt. 594, 594, 255 A.2d 680, 681 (1969); Hedman v. Siegriest, 127 Vt. 291, 293, 248 A.2d 685, 686 (1968). Moreover, in determining whether there is sufficient evidence to carry the matter to the jury, the court must focus on the tendency of the evidence, not its weight. Lewis v. Vermont Gas Corp., 121 Vt. 168, 179, 151 A.2d 297, 304 (1959). It is not for the court to decide which of two or more conclusions that are supportable by the evidence is more correct. Forcier v. Grand Union Stores, Inc., 128 Vt. 389, 398, 264 A.2d 796, 800 (1970). In short, the plaintiff is entitled to the strongest inferences reasonably deducible from the most favorable evidence, and insofar as the evidence “tends, in any fashion, to support” plaintiff’s claim it is entitled to a jury determination of the issues. LaRocque v. LaMarche, 130 Vt. 311, 314, 292 A.2d 259, 261 (1972).

Of course, there must be a view of the evidence which supports the essential elements of the plaintiff’s case. Id. Evidence which gives rise to a determination based on “mere conjecture, surmise or suspicion, is an insufficient foundation for a verdict.” Lewis, supra, 121 Vt. at 179, 151 A.2d at 304.

With these standards in mind, we proceed to examine whether the plaintiff established below the necessary ele *41 ments of its prima facie case against the various defendants.

A. Defendant CFZ

Plaintiff claims that CFZ was negligent in the performance of its obligation to exercise reasonable skill and care in the design and selection of materials for the construction of the roof and that CFZ was negligent in its failure to supervise the construction project. CFZ moved for a directed verdict on these claims, raising four grounds, two of which are relevant here: first, that there was no evidence of negligence attributable to CFZ, and second, that there was no evidence of negligence attributable to CFZ which was the proximate cause of South Burlington’s injury. 3

With respect to the negligent design claim, in order to establish a prima facie case for relief South Burlington had to show that CFZ breached its duty to use reasonable care and that as a proximate result of this breach the plaintiff suffered injury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kingsbury v. Goodrich
Vermont Superior Court, 2025
Allen v. Feeney Property
Vermont Superior Court, 2024
State v. Venessa Sarkisian-Kennedy
2020 VT 6 (Supreme Court of Vermont, 2020)
In re Gregory J. Bombardier
2018 VT 11 (Supreme Court of Vermont, 2018)
Leduc Construction, LLC CU Variance
Vermont Superior Court, 2016
Larry Fenter v. Rebecca Brown
Supreme Court of Vermont, 2016
B & M Realty Act 250
Vermont Superior Court, 2015
Lamell Lumber Corp. v. Newstress International, Inc.
182 Vt. 282 (Supreme Court of Vermont, 2007)
Lamell Lumber Corp. v. NEWSTRESS INTERN.
2007 VT 83 (Supreme Court of Vermont, 2007)
Banknorth, N.A. v. Littlefield
Vermont Superior Court, 2005
Sheldrake v. Skyline Corp.
Vermont Superior Court, 2005
Howard v. Usiak
775 A.2d 909 (Supreme Court of Vermont, 2001)
Barnes v. Anderson
202 F.3d 150 (Second Circuit, 1999)
Estate of Fleming v. Nicholson
724 A.2d 1026 (Supreme Court of Vermont, 1998)
Long v. L'ESPERANCE
701 A.2d 1048 (Supreme Court of Vermont, 1997)
Wolf v. State, 94-1607 (1996)
Superior Court of Rhode Island, 1996
Central Washington Refrigeration, Inc. v. Barbee
913 P.2d 836 (Court of Appeals of Washington, 1996)
Breslauer v. Fayston School District
659 A.2d 1129 (Supreme Court of Vermont, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
410 A.2d 1359, 138 Vt. 33, 28 U.C.C. Rep. Serv. (West) 1382, 1980 Vt. LEXIS 1011, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-burlington-school-district-v-calcagni-frazier-zajchowski-architects-vt-1980.