Leduc Construction, LLC CU Variance

CourtVermont Superior Court
DecidedDecember 29, 2016
Docket102-7-14 Vtec
StatusPublished

This text of Leduc Construction, LLC CU Variance (Leduc Construction, LLC CU Variance) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leduc Construction, LLC CU Variance, (Vt. Ct. App. 2016).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION

LEDUC CONSTRUCTION, LLC Docket No. 102-7-14 Vtec CONDITIONAL USE APPEAL

LEDUC CONSTRUCTION, LLC Docket No. 119-10-15 Vtec VARIANCE APP. APPEAL

Decision on the Merits Leduc Construction, LLC (“Applicant” or “Appellant”), by and through its principal, Andre Leduc, seeks permit authority to excavate its property along Vermont Route 78 in the Town of Highgate so it may extract and sell what is anticipated to be high-quality sand for use on construction projects. When its application for conditional use and a setback waiver was denied by the Town of Highgate Development Review Board (“DRB”), Applicant appealed to this Court. That appeal was assigned Docket No. 102-7-14 Vtec. While that appeal was pending, Applicant also applied for a variance from the setback minimums from the side and rear boundaries. When its variance application was also denied by the DRB, Applicant appealed that determination to this Court as well. That appeal was assigned Docket No. 119-10-15 Vtec. At the time of trial, Applicant was represented by Attorney Lisa B. Shelkrot. The Town of Highgate (“Town”) has appeared and actively participated in each of the pending appeals, with the assistance of its attorney, Edward G. Adrian. No other party has entered an appearance in either of the appeals. The parties endeavored to resolve their disputes through informal discussions. When those efforts failed, the Court initially set the first appeal for trial on August 20, 2015. However, the parties jointly requested that the Court delay that trial, as they anticipated that the variance application that was then pending before the DRB would result in a second appeal to this Court. The Court therefore cancelled the August 20, 2015 trial and awaited a determination on the

1 variance application and possible appeal. When that DRB determination was appealed to this Court, the Court coordinated both matters to be jointly tried. That coordinated trial occurred on April 27, 2016. On the morning of the trial, the Court conducted a site visit with the parties and their counsel. Once the trial was completed, the parties were afforded an opportunity to file proposed Findings of Fact and Conclusions of Law. Those post-trial filings were completed on May 31, 2016 and these coordinated appeals thereafter came under advisement for the Court’s consideration. Other hearings and writing responsibilities prevented the Court from completing its research and drafting on this Merits Decision until just recently. The Court apologizes to the parties and their counsel for its delay. Based upon the credible evidence admitted at trial, which the site visit helped put into context, the Court renders the following Findings of Fact, Conclusions of Law, and the accompanying Judgment Order.

Findings of Fact 1. Applicant owns a 5± acre parcel at 835 Vermont Route 78 in Highgate, Vermont (“the Property”). 2. The Property is narrow and deep, being about 224 feet wide in the front (adjoining Route 78) and rear, and about 1,250 feet along each side boundary. The property is mostly undeveloped, save for a trailer and septic system on the front portion of the lot, and is mostly open and lacking of trees, save for tall white pine trees that border the Property along the entire length of the two side and rear boundaries. 3. The Property is located in the Town of Highgate Industrial/Commercial Zoning District (“I/C District”). 4. The surrounding neighborhood includes several commercial developments, including a former landfill, the Franklin County Field Days site, a trucking office and depot (Charlebois Trucking) and a construction company office (owned and operated by Mr. Leduc). 5. There are no residential properties in the immediate vicinity of the Property. During the proceedings on both applications before the DRB, no interested party (other than the Town) appeared or voiced concerns about the Leduc sand extraction operation.

2 6. Mr. Leduc discovered that the property contains deposits of what is believed to be high- quality sand. Sand of this high quality is most suitable for use when constructing commercial and residential on-site sewage disposal systems that require a mound or other deposit of imported soils to host the leaching component of the sewage disposal system. 7. This type of high-quality sand has been extracted from several other area sand pits, but the existing pits are approaching the end of their usable life. The supply of high-quality sand is becoming more scarce in this region. 8. Prior to applying for any municipal zoning permits, Applicant began extracting sand from the Property. Mr. Leduc professed to have been unaware that a permit was required for his sand extraction activities. 9. Once Mr. Leduc was made aware that permits were required for his planned extraction activities, he stopped the pre-permit excavation and Applicant applied for conditional use approval. 10. Because of the narrowness of the Property, Applicant concluded that it needed to conduct its sand excavation work within the 150-foot side- and rear-yard boundary setbacks. Applicant therefore included a request for a waiver from the setback limitations in his conditional use application. If Applicant were required to respect the 150-foot side yard setbacks, it would not be able to conduct any excavation activities, given that the Property is no more than 274 feet wide. 11. Applicant proposes to excavate and extract sand up to fifty feet from the side and rear boundary lines of its Property. A set of site plans, consisting of six pages, was admitted at trial as Exhibit 5. 12. The proposed excavation and extraction will be conducted in three phases over an estimated period of two and a half years. The excavation activities would occur on the back 3± acres of the Property, with the 2± acres closest to Route 78 remaining undisturbed, save for some improvements to the internal roadway that will be used by excavation trucks and equipment. See Exhibit 5, at page C-1. 13. Excavation of the 3± acres will occur in three phases, with each phase to encompass about 1± acre of the Property. Phase 1 will occur on the acre approximately in the middle of the

3 Property, with the subsequent Phase 2 and Phase 3 to occur on each of the 2± acres at the rear of the Property. Id. 14. Within each Phase, the open extraction area will be approximately 125 feet by 200 feet. Exhibit 5 at pages C-2, C-3, and C-4. The excavation will create a depression in the land that will be no more than thirteen feet below the existing ground level. The excavated area will stop at fifty feet from the side and rear boundaries. 15. As the high-quality sand is extracted from each Phase of the site, Applicant proposes to truck the extracted sand to another site for storage and sale. No sand will be stored, displayed, or sold on the Property. 16. As the high-quality sand is extracted from each Phase, Applicant proposes to bring lesser- quality sand onto the site from another location. This imported sand will be used to backfill the excavated area, with the goal being to return the Property to the same level and grade as presently exists. Applicant also proposes to bring topsoil onto the Property and will thereafter grade, seed and mulch the topsoil for growth. The topsoil that once was on the property was removed years ago. 17. Sand extraction would occur during the non-winter months, for a total of 180 days each year. The excavation activities would take place during the weekdays, from 7:30 AM to 4:00 PM. There would not be any commercial operation on the Property during the weekends. 18. Phases 1 and 2, once all excavation is complete, will result in about 9,600 cubic yards of high-quality sand being extracted and trucked off site. Phase 3 will result in about 6,500 cubic yards of high-quality sand being extracted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LaRocque v. LaMarche
292 A.2d 259 (Supreme Court of Vermont, 1972)
In Re Laberge Moto-Cross Track
2011 VT 1 (Supreme Court of Vermont, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Leduc Construction, LLC CU Variance, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leduc-construction-llc-cu-variance-vtsuperct-2016.