J & K Tile Company

2019 VT 78
CourtSupreme Court of Vermont
DecidedOctober 25, 2019
Docket2018-110
StatusPublished
Cited by6 cases

This text of 2019 VT 78 (J & K Tile Company) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J & K Tile Company, 2019 VT 78 (Vt. 2019).

Opinion

NOTICE: This opinion is subject to motions for reargument under V.R.A.P. 40 as well as formal revision before publication in the Vermont Reports. Readers are requested to notify the Reporter of Decisions by email at: JUD.Reporter@vermont.gov or by mail at: Vermont Supreme Court, 109 State Street, Montpelier, Vermont 05609-0801, of any errors in order that corrections may be made before this opinion goes to press.

2019 VT 78

No. 2018-110

J & K Tile Company Supreme Court

On Appeal from v. Superior Court, Chittenden Unit, Civil Division

Wright & Morrissey, Inc. January Term, 2019

Robert A. Mello, J.

Mark G. Hall of Paul Frank + Collins P.C., Burlington, for Plaintiff-Appellee/Cross-Appellant.

Michael B. Clapp, Middlebury, for Defendant-Appellant.

PRESENT: Reiber, C.J., Skoglund, Robinson, Eaton and Carroll, JJ.

¶ 1. REIBER, C.J. This is a contractual dispute between J & K Tile Co., a

subcontractor, and Wright & Morrissey, a general contractor. After a bench trial, the court issued

a judgment and order on February 23, 2018, which held, among other things, that Wright &

Morrissey owed J & K Tile Co. $42,000 plus interest under a Memorandum of Understanding

(MOU) between the parties, and that Wright & Morrissey unlawfully withheld J & K Tile Co.’s

retainage1 check in violation of the Vermont Prompt Pay Act. Following this decision, on May

31, 2018, the court further held that each party was the prevailing party in a portion of the litigation

and should be awarded attorney’s fees regarding that portion. Wright & Morrissey appeals, and

J & K Tile Co. cross-appeals. We affirm in part and reverse and remand in part.

1 “Retainage” is “a percentage of a contract price retained from a contractor as assurance that subcontractors will be paid and that the job will be completed.” Retainage, Merriam-Webster Online Dictionary, Merriam-Webster.com [https://perma.cc/M2SQ-WH4B]. ¶ 2. The general factual background is as follows. The parties entered a contract for

Texas-based J & K Tile Co. to install flooring for Wright & Morrissey’s construction project in

Vermont. J & K Tile Co. began work, expecting to complete its job within two months. Soon

afterward, anticipating there might be general delays in construction, the parties agreed to an MOU

providing that Wright & Morrissey would make additional payments to J & K Tile Co. if delays

arose that were beyond J & K Tile Co.’s control. The anticipated delay occurred, and J & K Tile

Co. requested three payments under the MOU. Wright & Morrissey denied two of these requests.

After construction was completed, Wright & Morrissey sent the subcontractor a retainage check

as its final payment.

¶ 3. Three disputes are raised in this appeal: (1) J & K Tile Co.’s claim that it is owed

$42,000 under the MOU; (2) a dispute about the retainage check; and (3) a dispute about attorney’s

fees under the Prompt Pay Act. We discuss each in turn and recount additional facts as needed.

I. Claim for $42,000

¶ 4. The first dispute addresses whether Wright & Morrissey breached its contract by

failing to pay J & K Tile Co. $42,000 under the MOU.

A. Facts

¶ 5. The parties entered into a construction contract in December 2014; following

discussions about anticipated delays, the parties agreed to an MOU in April 2015, outside the

amendment process set forth in the contract. The MOU provided that the general contractor would

pay two additional costs. One was the “cost for travel and downtime” if Wright & Morrissey

suspended the project. After Wright & Morrissey suspended the subcontractor’s work and J & K

Tile Co. returned to Texas, the subcontractor requested additional payment, pursuant to the MOU,

for leaving and returning to the job site. The general contractor approved this payment.

¶ 6. The other was a daily additional cost, provided by the MOU as follows: “If J & K

Tile is delayed beyond May 21, 2015 through no fault of its own, Wright & Morrissey agrees to

pay not to exceed documented daily costs of $2,000.00 per day.” The subcontractor worked 2 twenty-one days past May 21, 2015, due to delays it did not cause. It documented that each day

resulted in more than $2000 in labor and fixed costs. On September 23, 2015, the subcontractor

requested a $42,000 payment based on the MOU for the twenty-one days that it worked past May

21. Wright & Morrissey denied the payment. J & K Tile Co. sued, alleging in its complaint that

Wright & Morrissey had breached its contract by failing to approve the September 23 request. The

complaint did not specifically identify the MOU, although it did identify the September 23 request,

which in turn identified the MOU.

¶ 7. In the litigation that ensued, both parties, as well as the trial court, acknowledged

that J & K Tile Co.’s claim regarding the $42,000 was based on the MOU. However, the parties

contested whether the MOU was part of the contract. Wright & Morrissey argued in its summary-

judgment briefing that the MOU was not an amendment, and therefore not part of the contract;

thus, when the subcontractor alleged in its complaint that Wright & Morrissey had breached the

“contract,” it had not alleged a breach of the MOU. J & K Tile Co. countered that the MOU was

an amendment and also that it did not matter; in whatever way they characterized the document,

Wright & Morrissey’s actions constituted a breach of contract. Later, at trial, Wright & Morrisey’s

witness testified that the MOU was a “standalone understanding,” rather than an “agreement” or

an amendment to the contract.

¶ 8. In J & K Tile Co.’s post-trial proposed findings of fact and conclusions of law, it

adopted the view, raised by Wright & Morrissey’s witness, that the MOU was a standalone

document. It concluded that the MOU was an independently enforceable contract. Wright &

Morrissey disagreed, stating in its proposed findings of fact and conclusions of law that the MOU

was not a standalone contract and that the question was irrelevant because J & K Tile Co. never

alleged breach of the MOU in its complaint. Wright & Morrissey then filed a motion for

clarification requesting that the court rule the original complaint did not allege a breach of the

MOU. J & K Tile Co. responded with motions to clarify and to amend the complaint, arguing that

the original complaint sufficiently notified Wright & Morrissey of its claim, but, in the alternative, 3 asking the court to amend the complaint to conform to the evidence pursuant to Vermont Rule of

Civil Procedure 15(b).

¶ 9. In the trial court’s February 23 judgment and order, it held that the MOU was an

enforceable contract and granted J & K Tile Co.’s motion to amend. It further determined that

Wright & Morrissey breached the MOU by failing to pay J & K Tile Co. $2000 per day for twenty-

one days, and it accordingly awarded the subcontractor $42,000 plus interest.

¶ 10. On appeal, Wright & Morrissey challenges this judgment with three legal

arguments: (1) the MOU is an “interpretive gloss” on the original contract, not an independent

contract, and therefore the timing and waiver provisions of the original contract bar the claim; (2)

the court erred in allowing J & K Tile Co. to amend the complaint to expressly cite the MOU as

the basis for J & K Tile Co.’s claims; and (3) the $2000-per-day cost outlined in the MOU does

not include labor costs. We do not address the third argument because it was not raised below.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rogers v. Rogers
Vermont Superior Court, 2025
Andrzejkiewicz v. Old High School
Vermont Superior Court, 2025
Berol Dewdney and Cordelia Dewdney v. Ralph E. Duncan, IV
2025 VT 26 (Supreme Court of Vermont, 2025)
kramer v. bd of educ
Vermont Superior Court, 2024
Energy Policy Advocates v. Attorney General's Office
2023 VT 43 (Supreme Court of Vermont, 2023)
Johnson v. Smith Bros. Ins., LLC
Vermont Superior Court, 2020

Cite This Page — Counsel Stack

Bluebook (online)
2019 VT 78, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-k-tile-company-vt-2019.