Bircwhood Land Dev. Corp. v. Ormond Bushey & Sons, Inc.

CourtVermont Superior Court
DecidedDecember 21, 2011
DocketS0946
StatusPublished

This text of Bircwhood Land Dev. Corp. v. Ormond Bushey & Sons, Inc. (Bircwhood Land Dev. Corp. v. Ormond Bushey & Sons, Inc.) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bircwhood Land Dev. Corp. v. Ormond Bushey & Sons, Inc., (Vt. Ct. App. 2011).

Opinion

Birchwood Land Dev. Corp. v. Ormond Bushey & Sons, Inc., No. S0946-08 CnC (Tomasi, J., Dec. 21, 2011)

[The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the accompanying data included in the Vermont trial court opinion database is not guaranteed.] STATE OF VERMONT

SUPERIOR COURT CIVIL DIVISION Chittenden Unit No. S0946-08 CnC

│ Birchwood Land Development Corp., │ Plaintiff, │ │ v. │ │ Ormond Bushey & Sons, Inc., │ Defendant. │ │

Order on Defendant’s Motion to Reconsider

Following issuance of the Court’s Findings of Fact, Conclusions of Law

and Order on October 7, 2011 (the “Ruling”), Defendant Ormond Bushey & Sons,

Inc. (“Bushey”) filed a Motion to Reconsider (the “Motion”). Specifically, Bushey

contends that the Court erred in its analysis of whether Bushey is entitled to

penalties and attorneys’ fees under the Prompt Pay Act in this case. As the Motion

was served within ten days of the Judgment, it was timely filed. Vt. R. Civ. P. 59(e).

For the following reasons, the Motion is granted in part and denied in part.

As the Vermont Rules of Civil Procedure have no formal standards for post-

judgment motions to reconsider, courts often analyze them under the provisions of

Rule 59. The Court retains broad discretion to review orders under that Rule. See

Drumheller v. Drumheller, 2009 VT 23, ¶36, 185 Vt. 417, 432 (2009). Nonetheless, a

motion to reconsider should not be a vehicle to re-litigate matters previously adjudicated by the court. As a result, the United States District of Vermont has

rightly noted that: “‘The standard for granting [a motion to reconsider] is strict, and

reconsideration will generally be denied unless the moving party can point to

controlling decisions or data that the court overlooked -- matters, in other words,

that might reasonably be expected to alter the conclusion reached by the court.’”

Latouche v. N. Country Union High Sch. Dist., 131 F. Supp. 2d 568, 569 (D. Vt.

2001) (quoting Shrader v. CSX Transp., Inc., 70 F.3d 255, 257 (2d Cir. 1995)).

Ultimately, a motion to reconsider should only be granted to the extent “justice

requires.” Putney School, Inc. v. Schaaf, 157 Vt. 396, 407 (1991).

The Court will address each of Bushey’s contentions in turn.

I. Premature Consideration of Sanctions and Attorneys’ Fees Under the Prompt Pay Act

Bushey argues that the Court improperly considered the issues of penalties

and attorneys’ fees under the Prompt Pay Act (“PPA”) without the benefit of briefing

from the parties. It asserts that the Court should have solicited such input before

deciding those questions.

Contrary to Bushey’s contention, Bushey did address these points in its pre-

and post-trial submissions. See, e.g., Defendant’s Proposed Findings of Fact and

Law, at 20-22; Defendant’s Proposed Findings of Fact and Conclusions of Law, at

34-36 (arguing that Birchwood had no good faith basis to withhold funds). In those

submissions, Bushey sought attorneys’ fees and penalties under the PPA.

2 Nonetheless, Bushey is correct that these PPA issues could not be addressed in

full detail until the parties had learned of the Court’s ruling on the merits. The

Court believes it appropriate to provide full opportunity for the parties to submit

arguments on these points. Accordingly, the Court grants Bushey’s motion to

reconsider its ruling on the PPA issues. As set forth below, the Court will reassess

the PPA issues in light of the parties’ most recent submissions and arguments.1

II. Penalties and Attorneys’ Fees Under the PPA

Bushey asserts that the Court erred in not awarding it PPA penalties. 9 V.S.A.

§ 4007. As described in the Ruling, such penalties may be appropriate in cases

where an owner withholds payment from a contractor. They are not warranted

where an owner has a good faith dispute with a contractor, and the amount

withheld bears a reasonable relation to the damages sought by the owner. Id.

Here, Bushey takes issue with the Court’s conclusion that the amounts

withheld by Birchwood Land Company, Inc. (“Birchwood”) bore a reasonable

relationship to the amounts in dispute concerning Birchwood’s claims against

Bushey. Bushey argues that Birchwood withheld far more funds than it recovered

in this action. Citing the disparity, it asserts that there was no reasonable

relationship between the disputed amounts and the sums withheld. Bushey takes

nothing from this argument.

1Given its decision to reconsider the issue, the Court need not address whether a request for attorneys’ fees under the PPA need follow the procedure set out in Vt. R. Civ. P. 54(d). 3 As the Court stated in the Ruling, Birchwood sought damages far in excess of

the amounts awarded by the Court. The Court found that Birchwood failed to prove

those additional damages at trial with reasonable certainty. That failure does not

require a finding that, for purposes of the PPA, the amount in dispute between the

parties is limited to the actual damages awarded by the Court. Had Birchwood

provided different or additional proof at trial, it is quite likely that additional

damages would have been awarded. Indeed, Birchwood sought damages at trial in

the amount of $56,825. It also had a claim for punitive damages.

The Vermont Supreme Court provided useful guidance on this point in Fletcher

Hill, Inc. v. Crosbie, 2005 VT 1, 178 Vt. 77 (2005). There, the owner withheld

$15,000 from a contractor to cover inadequate work and a possible payment due to a

subcontractor of $5,595. 2005 VT 1, at ¶8, 178 Vt. at 80-81. At trial, the owner

recovered only $4,000. In affirming the rejection of PPA penalties, the Court held

that an owner should not be penalized for “miscalculating the amount she was

entitled to withhold” where the owner had a good faith claim against the contractor.

Id. Just so here.

While Birchwood did not ultimately obtain all of the damages it sought, as

Crosbie instructs, the proper focus is on the value of Birchwood’s good faith claims.

Id.; 9 V.S.A. § 4007(d). Birchwood’s claims for damages were asserted in good faith

and were based, in part, on the limited evidence Bushey could produce as to the

amount of sand taken from the project. Those claimed damages bore a reasonable

relation to the amount Birchwood withheld. The fact that Bushey was unable – 4 even as late as trial – to provide a full accounting of the exact amount of sand taken

from the job site only reinforces the Court’s conclusion in this regard.

Accordingly, the Court re-affirms and adopts in full the discussion of PPA

penalties set out in the Ruling.

III. Substantially Prevailing Party Under the PPA

Bushy devotes the lion’s share of its Motion to the claim that it should be

awarded prevailing-party status. The Court has reconsidered its earlier analysis of

this issue in the Ruling in light of the most recent submissions of the parties. For

the following reasons, the Court re-affirms the discussion of this issue that is set

forth in the Ruling.

The Court has discretion in deciding whether one party or no party is the

substantially prevailing party in a PPA case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce C. Shrader v. Csx Transportation, Inc.
70 F.3d 255 (Second Circuit, 1995)
Drumheller v. Drumheller
2009 VT 23 (Supreme Court of Vermont, 2009)
Putney School, Inc. v. Schaaf
599 A.2d 322 (Supreme Court of Vermont, 1991)
Latouche v. North Country Union High School District
131 F. Supp. 2d 568 (D. Vermont, 2001)
Fletcher Hill, Inc. v. Crosbie
2005 VT 1 (Supreme Court of Vermont, 2005)
Electric Man, Inc. v. Charos
2006 VT 16 (Supreme Court of Vermont, 2006)
In re Harwood
2006 VT 15 (Supreme Court of Vermont, 2006)
King v. Hofmann
2008 VT 18 (Supreme Court of Vermont, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Bircwhood Land Dev. Corp. v. Ormond Bushey & Sons, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bircwhood-land-dev-corp-v-ormond-bushey-sons-inc-vtsuperct-2011.