Net Construction, Inc. v. C & C Rehab & Construction, Inc.

256 F. Supp. 2d 350, 2003 U.S. Dist. LEXIS 6141, 2003 WL 1870563
CourtDistrict Court, E.D. Pennsylvania
DecidedApril 9, 2003
Docket2:99-cv-03371
StatusPublished
Cited by12 cases

This text of 256 F. Supp. 2d 350 (Net Construction, Inc. v. C & C Rehab & Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Net Construction, Inc. v. C & C Rehab & Construction, Inc., 256 F. Supp. 2d 350, 2003 U.S. Dist. LEXIS 6141, 2003 WL 1870563 (E.D. Pa. 2003).

Opinion

MEMORANDUM AND ORDER

ANITA B. BRODY, District Judge.

I. Background

On July 1, 1999, Net, a Pennsylvania Corporation, commenced this action against C & C, a New Jersey Corporation. C & C served as the general contractor for the Chester Housing Authority during the construction of the William Penn Homes Project (“the project”). On or about February 3, 1997, Net and C & C entered into a written agreement; under the agreement, Net would perform concrete site work services and installations for the project on behalf of C & C. From February *352 3, 1997 through March 25, 1999, when C & C was removed from the project by a federally appointed receiver, Net performed installation of concrete site work services and installations pursuant to the parties’ agreement and the instructions of C&C.

Under the Contract for Construction (“the contract”) between Net and C&C, Net was required to submit to C & C billing requisitions or estimates at regular intervals for work performed by Net for C & C at the project site. Contract ¶ 10. The contract also required C & C to pay Net under each estimate within 60 days of the receipt of the requisitions without respect to the status of the Owner’s payment to C & C. Id. All work performed by Net through December 31, 1998 has been accepted by the Owner or its representative.

This case has a complicated and lengthy procedural history. On September 8, 1999, a default was entered against C&C for failure to appear, plead, or otherwise defend Net’s Complaint. On September 13, 1999, C&C submitted an Answer and affirmative defenses to Net’s Complaint. On September 16,1999, attorney Joseph S. Caruso (“Caruso”) was admitted pro hac vice on the motion of attorney Saul Stein-berg. C&C, acting through its counsel Caruso, submitted a brief on November 23, 1999 in support of its motion to vacate the entry of default and to dismiss Net’s claims against it pursuant to Federal Rules of Civil Procedure 12(b)(4), (5), and (6). On March, 17, 2000, however, the court vacated its Order granting C & C’s motion for Caruso to appear in this matter pro hac vice because it had come to the court’s attention that Caruso had been convicted of conspiracy to commit bribery. C&C was granted leave to have substitute counsel enter an appearance by April 3, 2000.

On May 12, 2000, Net entered into a Settlement Agreement with Montbatten Surety Co. (“Montbatten”), which was C & C’s bonding company, to settle Net’s claims against Montbatten brought by Net in the Court of Common Pleas of Philadelphia County to recover on the payment withheld by C & C. Among other things, the Settlement Agreement provided that Montbatten would pay Net $207,000 of the amount due Net and owed by C & C for its contract balance, extra and additional work, and prejudgment interest. Settlement Agreement ¶ 2. Accordingly, Net released C&C from liability on Net’s claims for the contract balance, extra and additional work, and Net’s prejudgment interest thereon. Id. Significantly, however, “Net specifically reservefd] the right to assert all other claims against C & C in the Federal Court Case or otherwise, including without limitation its claims for statutory penalty and legal fees, lost productivity, overhead and escalation.” Id. at ¶ 5. Pursuant to the settlement, Net received payment from Montbatten on May 19, 2000.

Nine months later, by letter dated February 15, 2001 C & C’s new counsel Stein-berg, the same attorney who moved for Caruso’s pro hac vice admission, informed the court that C&C had authorized him to withdraw both its motion to vacate default entry and its motion to dismiss. On February 16, 2001, therefore, the court denied as moot C & C’s motions to vacate default entry and to dismiss Net’s complaint.

Almost a year and a half later, on July 2, 2002, the court ordered Net to show cause why the case should not be dismissed unless Net filed a ‘motion for default judgment on or before July 26, 2002. Net filed a motion for default judgment on July 26, 2002, and on August 14, 2002 the court ordered Net to file a detailed affidavit in *353 support of its motion for default judgment, itemizing the damages it seeks against C & C.

On August 26, 2002 C & C’s third counsel in this action, Charles K. Graber (“Gra-ber”), entered his appearance on behalf of C & C, and Steinberg withdrew his representation of C & C. On August 29, 2002, C & C, acting through its counsel Graber, moved to vacate the court’s February 16, 2001 Order denying as moot C & C’s motions to vacate default entry and to dismiss Net’s claims. Also, C & C again moved to dismiss Net’s claims under Federal Rule of Civil Procedure 12 on the basis of a forum selection clause in the contract. 1 Contract ¶ 15.

On October 8, 2002, I denied C & C’s motion to vacate the Order of February 16, 2001 as well as C & C’s motion to dismiss Net’s complaint. Net Const., Inc. v. C & C Rehab & Const., Inc., No. 99-CV-3371, 2002 WL 31268385, at *1, (E.D.Pa. October 8, 2002). On October 23-24, 2002, I held a default judgment hearing (the “hearing”) pursuant to Fed.R.Civ.P. 55(b)(2) to determine the amount of damages suffered by Net as a result of C & C’s breach of the contract.

Net did not rely on an independent expert at the damages hearing. Instead, Net’s only witness was its President Mr. Christopher J. Colletti (“Colletti”). The project proceeded in two “phases” (“Phase I” and “Phase II”), each of which involved work on ten to twelve homes that were basically identical. (N.T. 10/23/02 (Collet-ti) at 6). As the concrete site work contractor, Net performed two kinds of work on the project. Id. The first involved work directly related to the construction of the buildings, and involved pouring concrete “footers” and “base slabs.” Id. at 8. Net also performed miscellaneous site-work, including the construction of curbs and sidewalks.

Colletti testified that work on phase I was supposed to be completed in July of 1997, but it did not end until April of 1998. (N.T. 10/23/02 (Colletti) at 45). Colletti testified that Net lost $103,188 on Phase I of the project. Id. at 24. The whole project, including the completion of phase II was supposed to end in April of 1998, but the project was not complete until April of 1999. Colletti testified that Net lost $139,000 on Phase II. Id. at 56.

Colletti attributed the delay in finishing the project primarily to C & C’s poor management especially during of Phase I of the project. For example, Colletti testified that C & C had installed a fence around the project that made it difficult to gain easy access to the construction site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baker DC, LLC v. Baggette Constr., Inc.
378 F. Supp. 3d 399 (D. Maryland, 2019)
Stanley Miller Constr. Co. v. State
2010 Ohio 1488 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. Ohio School Facilities Comm.
2010 Ohio 1528 (Ohio Court of Claims, 2010)
Mastercraft Woodworking Co. v. Jim Lagana Plumbing & Heating Inc.
9 Pa. D. & C.5th 251 (Berks County Court of Common Pleas, 2009)
Cohen v. Kallok (In Re JRA 222, Inc.)
365 B.R. 508 (E.D. Pennsylvania, 2007)
City of Westminster v. Centric-Jones Constructors
100 P.3d 472 (Colorado Court of Appeals, 2004)
R.W. Sidley, Inc. v. United States Fidelity & Guaranty Co.
319 F. Supp. 2d 554 (W.D. Pennsylvania, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
256 F. Supp. 2d 350, 2003 U.S. Dist. LEXIS 6141, 2003 WL 1870563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/net-construction-inc-v-c-c-rehab-construction-inc-paed-2003.