Stein v. William C. Cox, Inc. (In Re Stein)

57 B.R. 1016, 1986 U.S. Dist. LEXIS 28985
CourtDistrict Court, E.D. Pennsylvania
DecidedFebruary 24, 1986
DocketCiv. A. No. 85-6161, Bankruptcy No. 83-03955G, Adv. No. 84-0216G
StatusPublished
Cited by1 cases

This text of 57 B.R. 1016 (Stein v. William C. Cox, Inc. (In Re Stein)) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stein v. William C. Cox, Inc. (In Re Stein), 57 B.R. 1016, 1986 U.S. Dist. LEXIS 28985 (E.D. Pa. 1986).

Opinion

MEMORANDUM

KATZ, District Judge.

Appellant William C. Cox, Inc. (“Cox”) appeals from an order of the Bankruptcy Court, 53 B.R. 81 (1985). This court has jurisdiction of the appeal pursuant to 28 U.S.C. section 1334(a). Under Rule 8013 of the Bankruptcy Code, the appropriate standard of review is that the findings of fact of the Bankruptcy Court will not be set aside unless clearly erroneous. Bankruptcy Rule 8013. However, I must make an independent determination of the bankruptcy court’s legal conclusions. Universal Minerals, Inc. v. C.A. Hughes & Co., 669 F.2d 98, 103 (3d Cir.1981); In re Mead Land Development Co., 527 F.2d 280, 282-83 (3d Cir.1975); In re Furst, et al., 57 B.R. 1013, 1014. (E.D.Pa.1986); In re Philadelphia Athletic Club, Inc., 20 B.R. 328, 331 (E.D.Pa.1982).

For the reasons below, the order of the Bankruptcy Court will be affirmed.

In October, 1983, appellee, Paul C. Stein, Jr., t/a Fairfax Construction Company (“Fairfax”) filed an voluntary petition for reorganization under Chapter 11 of the Bankruptcy Code. Stein is the sole proprietor of Fairfax, which engages primarily in landscaping, excavating and paving. Fair-fax filed the complaint giving rise to this litigation on February 16, 1984. Fairfax sought to recover for services it performed for Cox on a playground project in Philadelphia. Cox was the general contractor on the project and subcontracted demolition, landscaping and paving work to Fairfax. Fairfax also sought the return of certain equipment which Fairfax used during its work on the playground and left on the site. Fairfax alleged that Cox had later removed the equipment from the site and refused to return it to Fairfax. Fairfax also asked for compensatory and punitive damages for Cox’s seizure of its machinery.

Cox, in a counterclaim, sought to recover expenses allegedly incurred in finishing the work Fairfax was supposed to complete under its contract. Cox also requested damages for Fairfax’s delay in completing its portion of the playground project, a delay which allegedly set back completion of the project as a whole.

*1018 The Honorable Emil F. Goldhaber, Chief Bankruptcy Judge, held several hearings in this matter, and on September 16, 1985 issued an opinion and order. Judge Gold-haber awarded Fairfax the amount of $11,-082.00 for services performed on the playground project, but denied all other relief. Cox then filed this appeal.

The Bankruptcy Court found that Cox had contracted with the City of Philadelphia for construction of the playground. Cox had then subcontracted work for demolition, excavation, paving and landscaping to Fairfax at a contract price of $32,200.00. The Bankruptcy Court found much of Fair-fax’s work on the playground to be below contract standards but attributed some of the substandard performance to directions from Cox. In particular, the Bankruptcy Court found, that Cox had instructed Fair-fax to pave when temperatures were far below optimal levels. Both Fairfax and Cox were forced to expend additional costs to correct deficiencies in work Fairfax had performed.

In addition, the Bankruptcy Court found that Fairfax had performed additional work (incurring additional costs) on the project beyond that set forth in its agreement with Cox. Fairfax had performed this work at Cox’s request. Fairfax also sustained additional expenses because it had to re-do work on one of the playing fields due to discrepancies between the actual dimensions of the playground and those set forth in the plan Cox gave to Fairfax.

The Bankruptcy Court noted that Fairfax ultimately left the work site without completing all of the work required under its agreement with Cox. However, Fairfax left behind a paving machine and a tractor with a rake attachment. Cox informed Fairfax that the City of Philadelphia wanted the equipment removed from the site. Fairfax refused to remove the equipment, claiming that moving it under the current weather and ground conditions presented a substantial risk of damage to the surface of the playground. With the machinery still on the site some months after this exchange of communications, Cox removed Fairfax’s equipment. The machinery was left at an uncovered area beside an auto garage. When Fairfax first requested the return of its equipment, Cox refused to turn the machines over.

The Bankruptcy Court denied relief to Fairfax in connection with its claim for damages arising out of Cox’s removal and storage of its equipment. First, the court found that the machines “were of nominal value.” Opinion at 83. The court also noted that Cox had urged Fairfax to move the machinery, but Fairfax had declined to do so. “Any deterioration of the equipment due to weathering and vandalism,” the Court found, “could have happened while the property was resting on the playground lot, and apparently much of that damage did occur there.” Id. at 83. Since Fairfax was now free to reclaim its equipment, the Court held that Fairfax was entitled to no damages.

The Bankruptcy Court found that Fair-fax had completed 81% of the work required under the contract. Despite its finding that much of the debtor’s work was sub-standard, the Bankruptcy Court ruled that Fairfax had performed substantially all of the work required and was entitled to payment for the work it had completed. Since 81% of the contract price came to $26,082.00, and Fairfax had already received payment of $15,000.00, Cox owed Fairfax $11,082.00.

In its counterclaim, Cox sought damages for overhead costs allegedly caused by Fairfax’s failure to complete its portion of the playground project on time. The Bankruptcy Court found that Cox’s contract with the City of Philadelphia was not fulfilled until months after the expected completion date, a fact which neither side disputed. However, the court ruled that Cox had failed to prove what portion of this delay, if any, was attributable to Fairfax. Indeed, the court found that Cox itself and other of its subcontractors — as well as Fairfax — had all contributed to the delay. According to the Bankruptcy Judge, Fair-fax was no more culpable for the delay than Cox and the other subcontractors, so Cox was not entitled to damages.

*1019 Fairfax also sought damages in connection with the work that it performed beyond the scope of its agreement with Cox. On the other hand, Cox sought damages for work it performed to correct deficiencies in Fairfax’s work. The Bankruptcy Court was unable to affix a dollar value for the work performed by either litigant because of the “numerous, amorphous constituent elements” of each claim for damages. Opinion at 82. The court found that “the two countercharges are approximately equal and thus nullify each other.” Id.

Cox lists twelve bases for its appeal. 1 In its brief, Cox states that these twelve specific issue can be categorized into four factual matters and two areas of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Net Construction, Inc. v. C & C Rehab & Construction, Inc.
256 F. Supp. 2d 350 (E.D. Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
57 B.R. 1016, 1986 U.S. Dist. LEXIS 28985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stein-v-william-c-cox-inc-in-re-stein-paed-1986.