City of Westminster v. Centric-Jones Constructors

100 P.3d 472, 2003 WL 22098771
CourtColorado Court of Appeals
DecidedNovember 8, 2004
Docket01CA0502, 02CA0602
StatusPublished
Cited by35 cases

This text of 100 P.3d 472 (City of Westminster v. Centric-Jones Constructors) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Westminster v. Centric-Jones Constructors, 100 P.3d 472, 2003 WL 22098771 (Colo. Ct. App. 2004).

Opinion

Opinion by Judge WEBB.

In this construction dispute, plaintiff, the City of Westminster (City), appeals the judgments entered against it and in favor of defendants, Centric-Jones Constructors and its affiliates (collectively Jones); Travelers Casualty & Surety Company; Aetna Casualty & Surety Company; and Bates Engineering, Inc. Jones cross-appeals the judgments entered against it and in favor of third-party defendants, Fischbach Masonry, Inc. and Reliance Insurance Company, only to the extent of further proceedings between the City and Jones. We affirm.

The City, as owner, and Jones, as prime contractor, entered into a contract to expand the City’s water treatment plant. Travelers and Aetna (collectively Travelers) were sureties to Jones. Fischbach was a subcontractor to Jones and Reliance was its surety. Bates and other engineering firms performed all design work for the City.

The project involved design and construction of three structures, two of which are at the center of this appeal: a five-million-gallon, below ground concrete tank to hold treated water (elearwell); and a high service pumping station to move the treated water into the City’s distribution system (HSPS).

In 1995, Jones began construction using designs and specifications prepared by the engineering firms. Work continued beyond the scheduled completion date. Disagreements among the City, Jones, and the engineering firms arose over water leakage from the elearwell into the underlying fill, wetting and destabilization of bedrock below the fill, and resulting movement of the elearwell. Other disagreements arose over structural problems in the walls and foundation of the nearby HSPS.

In late 1997, with most of the work done, the City terminated the contract and asserted a claim against Travelers under the performance bond. Travelers denied the claim on the basis of improper contract termination.

The City then hired new engineers. They recommended that the City demolish and rebuild the elearwell using a significantly different foundation design, demolish and rebuild the masonry walls of the HSPS to new specifications, and change the HSPS foundation. The City did so, although expenses substantially exceeded the original construction costs and the new specifications added features to both the elearwell and the HSPS.

The City sued Jones, Bates, and the other initial engineering firms for breach of contract and negligence, claiming as damages *477 the entire cost of removing, redesigning, and rebuilding the elearwell; redesigning and rebuilding the HSPS walls; and modifying the HSPS foundation. The City also sued Travelers for breach of the performance bond and bad faith investigation of the City’s claim.

Jones counterclaimed for lost profits from unfinished work based on wrongful termination of the contract and for nonpayment for work performed to the termination date. Jones also filed a third-party complaint against Fischbach and Reliance seeking indemnification for damages arising from work done by Fischbach on the HSPS walls.

The court entered summary judgments dismissing the claims against Bates, and in favor of Jones on the City’s negligence claim. The other engineering firms then settled with the City.

At trial, after the City rested its case-in-chief, the court directed verdicts for all defendants and third-party defendants. The court concluded that the City had failed to present a reasonable basis on which the jury could apportion damages based on either the benefit of the City’s bargain with Jones or Jones’ breaches.

At the conclusion of its deliberations on Jones’ counterclaims, the jury did not complete the verdict form on the wrongful termination counterclaim. Instead, it completed the verdict form on the other counterclaim and awarded Jones payment for work performed.

The trial court awarded substantial costs to all defendants and third-party defendants. A separate appeal and a cross-appeal of the cost awards were consolidated with this appeal.

I. Directed Verdict for Jones

The City first argues that the trial court erred in directing a verdict based on its failure to prove damages. We disagree.

We review a directed verdict de novo. Campbell v. Burt Toyota-Diahatsu, Inc., 983 P.2d 95 (Colo.App.1998).

A motion for directed verdict should not be granted unless the evidence compels the conclusion that reasonable jurors could not disagree and that no evidence or inference has been received at trial upon which a verdict against the moving party could be sustained. If a trial judge concludes that a reasonable jury could return a verdict in the plaintiffs favor, a defendant’s directed verdict motion cannot be granted. The trial judge must view the evidence in a light most favorable to the nonmoving party. Fair v. Red Lion Inn, 943 P.2d 431 (Colo. 1997).

A party attempting to recover for breach of contract must prove: (1) the existence of a contract; (2) performance by the plaintiff or some justification for nonperformance; (3) failure to perform the contract by the defendant; and (4) resulting damages. Western Distrib. Co. v. Diodosio, 841 P.2d 1053 (Colo.1992).

Here, the parties dispute only the sufficiency of the City’s damages evidence, and we examine separately the claims for actual damages and for liquidated delay damages.

A. Actual Damages

The trial court concluded that the City failed to provide any basis on which the jury could apportion damages, either between the benefit of the City’s bargain with Jones and additional benefit to the City from rebuilding the structures to new specifications, or between particular breaches by Jones and design errors of others for which Jones was not responsible. We agree.

To survive a directed verdict motion challenging proof of actual damages, the plaintiff in a breach of contract action must have presented evidence of both the existence and the cause of damages. See Roberts v. Adams, 47 P.3d 690 (Colo.App.2001). The plaintiff must also provide the factfinder with a reasonable basis for calculating actual damages in accordance with the relevant measure. Husband v. Colo. Mountain Cellars, Inc., 867 P.2d 57 (Colo.App.1993). However, proof of damages with mathematical certainty is not required. Tull v. Gundersons, Inc., 709 P.2d 940 (Colo.1985).

The general measure of damages for breach of a construction contract is that *478 amount required to place the owner “in the same position he would have occupied had the breach not occurred.” Pomeranz v. McDonald’s Corp., 843 P.2d 1378, 1381 (Colo.1993); see also McDonald’s Corp. v. Brentwood Center, Ltd., 942 P.2d 1308, 1310 (Colo. App.1997). This rule protects defendants against speculative awards that would otherwise provide plaintiffs with an economic windfall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

3939 Williams v. Weaver
Colorado Court of Appeals, 2026
Starski v. Holderness
Colorado Court of Appeals, 2025
Ironshore v. Pool
Colorado Court of Appeals, 2025
MarkWest v. Rose
Colorado Court of Appeals, 2025
Continental v. Ball Corp
Colorado Court of Appeals, 2025
Lockhart v. Van Beek
D. Colorado, 2025
Brone v. Cromer
Colorado Court of Appeals, 2025
Brown v. Smith
Colorado Court of Appeals, 2024
John Doe v. University of Denver
Colorado Court of Appeals, 2022
Lorenzen v. Pinnacol Assurance
2019 COA 54 (Colorado Court of Appeals, 2019)
Gallegos v. LeHouillier
2017 COA 35 (Colorado Court of Appeals, 2017)
Mid-Century Insurance v. InsulVail, LLC
592 F. App'x 677 (Tenth Circuit, 2014)
Gibbons v. Ludlow
2013 CO 49 (Supreme Court of Colorado, 2013)
Engeman Enterprises, LLC v. Tolin Mechanical Systems Co.
2013 COA 34 (Colorado Court of Appeals, 2013)
Banning v. Prester
2012 COA 215 (Colorado Court of Appeals, 2012)
Ludlow v. Gibbons
310 P.3d 130 (Colorado Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
100 P.3d 472, 2003 WL 22098771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-westminster-v-centric-jones-constructors-coloctapp-2004.