24CA0996 Ironshore v Pool 04-24-2025
COLORADO COURT OF APPEALS
Court of Appeals No. 24CA0996 Adams County District Court No. 22CV30798 Honorable Arturo G. Hernandez, Judge
Ironshore Specialty Insurance Company, an Arizona corporation, as subrogee of Brinkman Construction, Inc.,
Plaintiff-Appellant,
v.
Pool and Spa Company, a Colorado limited liability company,
Defendant-Appellee.
JUDGMENT AFFIRMED
Division VI Opinion by JUDGE KUHN Welling and Schutz, JJ., concur
NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced April 24, 2025
Nicolaides Fink Thorpe Michaelides Sullivan, LLP, Matthew J. Fink, Denver, Colorado; Michael A. Yanof, Dallas, Texas, for Plaintiff-Appellant
Tyson & Mendes LLP, Michael D. Drews, Greenwood Village, Colorado, for Defendant-Appellee ¶1 Plaintiff, Ironshore Specialty Insurance Company, appeals the
trial court’s judgment entered upon jury verdicts in favor of
defendant, Pool and Spa Company (Pool & Spa), on Ironshore’s
breach of contract and negligence claims. We affirm.
I. Background
¶2 We glean the following factual and procedural background
from the record and evidence the jury heard at trial.
¶3 This construction defect dispute concerns the development of
a hotel in Westminster, Colorado. In 2019, the hotel’s owner,
Marriott International, hired Brinkman Construction, Inc., to serve
as the general contractor for the project. A few months later, Pool &
Spa entered into a subcontract with Brinkman, in which it agreed
to design and build an outdoor swimming pool and spa in the
hotel’s courtyard for $160,500. Pool & Spa began working on the
project in April 2020 after obtaining all the necessary approvals
from Brinkman and its architect, Worth Group Architects and
Designers. In July of that year, Pool & Spa completed the
installation of the pool and spa, the structures passed a final
inspection, and Pool & Spa requested payment of $35,000, the
outstanding contract balance.
1 ¶4 Brinkman rejected the payment request. Instead, it informed
Pool & Spa that it was terminating the contract because the
structures contained numerous material defects that Pool & Spa
had failed to correct. Specifically, the termination letter alleged that
Pool & Spa, among other things, hadn’t properly installed the
coping and handrails and had failed to install “auto fill components”
and a “chemical feeder” for the pool.
¶5 Roughly two months later, in November, Brinkman sent
Pool & Spa notice of claim under section 13-20-803.5, C.R.S. 2024.
In addition to the previously identified defects, and as relevant on
appeal, Brinkman alleged that Pool & Spa and Pool & Spa’s
subcontractor had failed to design and install a leak collection
system that a civil engineering company, Kumar & Associates, had
recommended in a 2017 geotechnical soils report (the Kumar
report). Brinkman alleged that the defects in Pool & Spa’s
workmanship “ha[d] led to water leaks, potential safety issues, and
surrounding soils movement.” Considering the nature of the
alleged defects, Brinkman asserted that “the only workable solution
[was] to demolish, remove and replace the swimming pool in its
entirety.” After Pool & Spa denied liability for the claimed defects,
2 Brinkman paid approximately $647,000 to replace the pool, the
spa, and the surrounding concrete pool deck.
¶6 In June 2022, Brinkman and its insurer, Ironshore, sued Pool
& Spa. About seven months later, Ironshore paid Brinkman
roughly $540,000 under its policy in exchange for a release of any
claims relating to the pool project. Then, as Brinkman’s subrogee,
Ironshore filed an amended complaint and asserted against Pool &
Spa claims for general breach of contract, breach of the indemnity
clause in article 9.1.1 of the contract, negligence, and professional
negligence. In the meantime, Pool & Spa filed a third-party
complaint against several entities that had participated in the
project, including Worth Group and Aquatic Engineering
Consultants, LLC (AEC), the subcontractor that Pool & Spa had
hired to design the pool and spa. The trial court eventually
dismissed the third-party defendants from the suit, and Ironshore’s
claims against Pool & Spa proceeded to a six-day jury trial.1
1 Specifically, Pool & Spa stipulated to AEC’s dismissal from the
case before trial. It also settled with Worth Group, which Pool & Spa designated as a nonparty at fault shortly before trial.
3 ¶7 The jury returned special verdicts finding that (1) Pool & Spa
breached the pool contract with Brinkman, but Brinkman failed to
substantially perform its obligations under that contract; (2) Pool &
Spa didn’t breach the indemnification clause; (3) Brinkman and
Pool & Spa were both negligent; (4) Pool & Spa was 15% at fault for
Brinkman’s damages and Brinkman was 85% at fault; and
(5) Ironshore wasn’t entitled to any damages on its claims.
Consequently, the trial court entered judgment in favor of Pool &
Spa.
II. Analysis
¶8 On appeal, Ironshore contends that the trial court reversibly
erred by entering judgment on the jury’s special verdicts because
the evidence was insufficient to support the jury’s findings that
Brinkman (1) breached the contract with Pool & Spa and (2) was
85% negligent. Ironshore also contends that the jury erred by
finding that (3) Pool & Spa didn’t breach the indemnity clause in the
contract, and (4) Ironshore wasn’t entitled to recover any damages
because the evidence was insufficient to support those findings and
the findings were inconsistent with other aspects of the jury’s
4 verdicts. We set forth the applicable standard of review before
addressing each of Ironshore’s contentions.
A. Standard of Review
¶9 We review sufficiency of the evidence claims de novo.2
Northstar Project Mgmt., Inc. v. DLR Grp., Inc., 2013 CO 12, ¶ 14. In
doing so, “we must determine whether the evidence, viewed as a
whole and in the light most favorable to the prevailing party, is
sufficient to support the verdict.” Parr v. Triple L & J Corp., 107
P.3d 1104, 1106 (Colo. App. 2004). We also must “draw every
reasonable inference from the evidence in favor of [the prevailing]
2 Pool & Spa contends that “[s]ufficiency of the evidence to support
a jury’s finding is not a question of law reviewed [de novo].” In support of its position, Pool & Spa appears to argue that de novo review only applies when a sufficiency of the evidence claim relates to an underlying question of law. This argument misses the mark. See Coors v. Sec. Life of Denver Ins. Co., 112 P.3d 59, 66 (Colo. 2005). Our sufficiency review doesn’t turn on whether the underlying issue is one of law or fact because we don’t review de novo the jury’s ultimate conclusion. See Mince v. Butters, 616 P.2d 127, 129 (Colo. 1980) (noting that while the sufficiency of the evidence in awarding damages is a question of law, whether to award those damages lies in the discretion of the trier of fact). Instead, as the supreme court has observed, we merely “review all of the relevant evidence de novo in the light most favorable to the verdict” to decide whether it sufficiently supported the jury’s decision. Northstar Project Mgmt., Inc. v. DLR Grp., Inc., 2013 CO 12, ¶ 14.
5 party.” Averyt v. Wal-Mart Stores, Inc., 2013 COA 10, ¶ 18 (quoting
Harris Grp., Inc. v. Robinson, 209 P.3d 1188, 1201 (Colo. App.
2009)). It is the sole prerogative of the jury to resolve disputes of
fact and to determine the weight of the evidence, the inferences to
be drawn from it, and the credibility of the witnesses. Fisher v.
State Farm Mut. Auto. Ins. Co., 2015 COA 57, ¶ 40, aff’d, 2018 CO
39. Accordingly, we won’t disturb a jury’s verdict if there is
competent evidence in the record to support it, even if reasonable
people could reach a different conclusion based on the same facts.
Id.; see also People in Interest of S.G.L., 214 P.3d 580, 583 (Colo.
App. 2009).
¶ 10 Likewise, we won’t reverse a jury’s verdict for inconsistency
when the jury has been adequately instructed on the law and the
verdict is supported by sufficient competent evidence in the record.
Hock v. N.Y. Life Ins. Co., 876 P.2d 1242, 1259 (Colo. 1994). We
review the jury instructions, the jury verdict forms, and the
evidence presented at trial to answer this question. Id.; see also
Hall v. Frankel, 190 P.3d 852, 863 (Colo. App. 2008). “If there is a
view of the case that makes the jury’s verdict consistent, we have a
duty to reconcile the verdict in that way.” Hall, 190 P.3d at 863.
6 B. Ironshore’s Sufficiency Challenge to the General Breach of Contract Verdict
¶ 11 Ironshore contends that there was insufficient evidence
supporting the jury’s finding that Brinkman also breached the pool
contract, which means its ultimate conclusion that Ironshore
therefore couldn’t prevail on its general breach of contract claim is
also unsupported. We disagree.
1. Applicable Law
¶ 12 To prove a breach of contract, a plaintiff must show (1) the
existence of a contract; (2) performance by the plaintiff or some
justification for nonperformance; (3) failure to perform the contract
by the defendant; and (4) resulting damages to the plaintiff. Univ. of
Denver v. Doe, 2024 CO 27, ¶ 46.
¶ 13 “The ‘performance’ element in a breach of contract action
means ‘substantial’ performance.” McDonald v. Zions First Nat’l
Bank, N.A., 2015 COA 29, ¶ 50 (quoting W. Distrib. Co. v. Diodosio,
841 P.2d 1053, 1058 (Colo. 1992)). “A party has substantially
performed when the other party has substantially received the
expected benefit of the contract” and is therefore bound to pay the
contract price to the performing party. Stan Clauson Assocs., Inc. v.
7 Coleman Bros. Constr., LLC, 2013 COA 7, ¶ 9; Diodosio, 841 P.2d at
1058. “Failure to substantially perform constitutes a breach of
contract.” Stan Clauson Assocs., Inc., ¶ 9.
2. There Was Sufficient Evidence to Support the Jury’s Finding that Brinkman Failed to Substantially Perform the Contract
¶ 14 The parties’ dispute at trial centered around the
uncontroverted fact that Pool & Spa didn’t design and install the
leak collection system that the Kumar report had recommended.
The report stated that because of expansive soils at the project site,
“[t]he pool should include a leak collection system to reduce the
potential for leak-induced post-construction heave.” The contract
between Brinkman and Pool & Spa didn’t include the quoted
language or explicitly state that the pool must be equipped with the
recommended system. Instead, article 13 of the contract
incorporated several other documents by reference, including the
Kumar report. The contract included as an exhibit the cover page
of the Kumar report but not the remainder of the document. The
contract noted that the “[f]ull report [was] available in Sharefile” and
that “[a] link w[ould] be provided with the Subcontract Agreement.”
8 ¶ 15 Ironshore argued at trial that because the Kumar report
recommended a leak collection system, and that report was
referenced in the contract, Pool & Spa breached the contract by
failing to design and install the leak collection system underneath
the pool, or to at least confirm with Brinkman whether it was
expecting the pool to have such a system. That failure, Ironshore
contended, led to the build-up of leaking pool water in the
expansive subsoils, which, in turn, caused the pool and the
surrounding concrete deck to shift. As a result of these defects,
Brinkman had to spend roughly $647,000 on demolishing and
replacing the pool, spa, and concrete deck. And because the costs
associated with this corrective work exceeded the unpaid balance of
the contract price, Ironshore’s position was that Brinkman properly
withheld final payment in accordance with the contract’s plain
terms.
¶ 16 For its part, Pool & Spa didn’t dispute that its contract with
Brinkman referenced the Kumar report and that the pool it built
lacked the leak collection system. Pool & Spa argued that it
nonetheless completed all the work that Brinkman had hired it to
do because the disputed leak collection system wasn’t within the
9 scope of its work. In support of this argument, Pool & Spa
highlighted evidence suggesting that the design and installation of
the recommended leak collection system weren’t required under the
bid request that it had received from Brinkman, its proposal to
Brinkman, or the shop drawings that the parties had negotiated
and agreed upon. Pool & Spa also highlighted that Brinkman’s
engineer and Worth Group signed off on the design, which didn’t
explicitly contain a leak collection system. Finally, Pool & Spa
pointed out that Brinkman didn’t provide anything more than the
first page of the Kumar report until after the pool design had been
completed by AEC, approved by Brinkman, and submitted for
approval by Worth Group.
¶ 17 The jury ultimately found in favor of Pool & Spa on Ironshore’s
general breach of contract claim. In a special verdict addressing
this claim, the jury answered in the affirmative the following
question: “Did the defendant [Pool & Spa] and/or its
subcontractors, or anyone employed directly or indirectly by any of
them for whose acts any of them may be liable, fail to follow the
requirements in the contract between [Brinkman] and [Pool & Spa].”
But the jury also answered “No” to the next question: “Did . . .
10 Brinkman . . . substantially perform its part of the contract.” The
jury therefore determined that Ironshore didn’t prevail on its
contract claim against Pool & Spa.
¶ 18 We conclude that there was sufficient evidence supporting the
jury’s decision.3 While the contract generally referenced the Kumar
report, other evidence in the record suggested that Pool & Spa
wasn’t responsible for the design and installation of the leak
collection system, creating a factual dispute for the jury to resolve.
For example, it was undisputed that Brinkman’s request for bid and
Pool & Spa’s proposal — which reflected the eventual contract price
and was also incorporated by reference in the contract — didn’t list
3 In reaching this conclusion, we note that portions of Pool & Spa’s
answer brief addressing Ironshore’s sufficiency challenges only include a bare laundry list of witnesses and record cites for the testimony purportedly supporting the jury’s verdicts. Pool & Spa doesn’t discuss the contents of the witnesses’ statements in its brief, let alone indicate how they relate to its argument. While Pool & Spa nonetheless prevails on this and other sufficiency challenges raised in this appeal, we caution against this approach. See C.A.R. 28(a)(7)(B), (b) (providing that a party’s arguments must contain “a clear and concise discussion of the grounds” upon which the party is relying in advancing its position, including proper citations to the authorities and relevant parts of the record); Brighton Sch. Dist. 27J v. Transamerica Premier Ins. Co., 923 P.2d 328, 335 (Colo. App. 1996) (noting that, as the reviewing court, we don’t have the duty to search the record for evidence in support of a party’s arguments), aff’d, 940 P.2d 348 (Colo. 1997).
11 those services as a separate line item. T.J. Kate, a civil structural
engineer who was qualified “as an expert in the fields of civil and
forensic engineering and swimming pool contracting,” opined that
he would have expected Brinkman’s bid to include a leak collection
system as a separate item because it was “a very specialized kind of
thing.” Indeed, the owner of Pool & Spa testified that he hadn’t
installed such a system in the past because that was considered
soil mitigation work, an area outside of his and Pool & Spa’s
expertise. He noted that Pool & Spa “do[es] not do any soil
mitigation. Zero. We don’t do leak collection systems. We don’t
overexcavate. We build the swimming pool.”
¶ 19 Moreover, Kate and another expert witness, Aaron Bagley,4
testified that the final shop drawings that AEC prepared on Pool &
Spa’s behalf didn’t contain a design for the leak collection system.
The record shows that Brinkman and Worth Group approved those
drawings after several rounds of revisions and after engaging in
extensive communications with AEC. Kate opined that because the
4 Bagley was qualified as an expert on the standard of care in
contract compliance with plans and specifications and the reasonableness of a pool replacement.
12 drawings didn’t include the leak collection system, that feature
wasn’t part of the plans, specifications, and approved submittals
that Pool & Spa was required to follow under the contract:
Well, the pool and spa, per plans, this was a design-build contract. And the plans were prepared by [Pool & Spa] and its . . . engineer [AEC]. And so those are the plans that [Pool & Spa was] building to, and those are the plans that they bid off of. And those are the plans with their specs that were included as part of those plans. That’s what they submitted back to Brinkman and ultimately to the architect to Worth [Group] for approval, and so that becomes the approved submittals.
And so when you look at the plans, specifications and approved submittals, that’s what they are. And nowhere in there was there any kind of leak collection system.
¶ 20 Kate further opined that Pool & Spa’s work complied with the
approved shop drawings and that Pool & Spa completed all the
services for which it was hired by Brinkman. And Justin Tuck,
Brinkman’s former project manager and an expert on “construction
management and the standard of care required for [the] design and
construction of pools,” testified that the contract provision allowing
Brinkman to correct defective work and withhold from the contract
13 price the costs associated with that work assumed that the defects
were within Pool & Spa’s original scope of work.
¶ 21 Viewing this evidence in the light most favorable to Pool & Spa
as the prevailing party, a reasonable juror could have concluded
that the leak collection system was outside of Pool & Spa’s scope of
work, and in that case, Brinkman wasn’t entitled to withhold
payment of the remaining contract price. Accordingly, we conclude
that sufficient evidence supported the jury’s determination that
Brinkman didn’t substantially perform its obligations under the
contract. See Parr, 107 P.3d at 1106; see also Air Sols., Inc. v.
Spivey, 2023 COA 14, ¶ 9 n.2 (noting that we view in the light most
favorable to the verdict the jury’s “determination of the terms of the
contract”). And because Ironshore failed to establish the
“performance” element of its breach of contract claim, there was
sufficient evidence supporting the jury’s finding in favor of Pool &
Spa on that claim. See Univ. of Denver, ¶ 46; McDonald, ¶ 50; Stan
Clauson Assocs., Inc., ¶ 9.
14 C. Ironshore’s Sufficiency Challenge to the Negligence Verdict
¶ 22 Ironshore next contends that there was insufficient evidence
from which the jury could find that Brinkman was negligent in
connection with the pool project, and accordingly, to support the
jury’s apportionment of 85% of the fault to Brinkman. We again
disagree.
¶ 23 To prevail on a negligence claim, a “plaintiff must show a legal
duty of care on the defendant’s part, breach of that duty, injury to
the plaintiff, and that the defendant’s breach caused the plaintiff’s
injury.” Day v. Johnson, 255 P.3d 1064, 1068-69 (Colo. 2011).
However, “Colorado is a comparative negligence jurisdiction.” Ferrer
v. Okbamicael, 2017 CO 14M, ¶ 35, superseded by statute on other
grounds, Ch. 147, sec. 1, § 13-21-111.5(1.5)(c), 2021 Colo. Sess.
Laws 863. While comparative negligence is an affirmative defense,
its purpose “is to ameliorate the harshness of the complete bar [to
recovery] resulting from common law contributory negligence.”
Gordon v. Benson, 925 P.2d 775, 777 (Colo. 1996) (quoting
Montgomery Elevator Co. v. Gordon, 619 P.2d 66, 70 (Colo. 1980));
15 Dickinson v. Lincoln Bldg. Corp., 2015 COA 170M, ¶ 25.
Accordingly, section 13-21-111(1), C.R.S. 2024, provides that a
plaintiff who was negligent may nonetheless recover damages if the
plaintiff’s negligence was less than the negligence of the person
against whom recovery is sought. But if the plaintiff’s proportion of
negligence was equal to or greater than the negligence of the person
against whom recovery is sought, then the court must enter a
judgment for the defendant. § 13-21-111(3).
2. There Was Sufficient Evidence to Support the Jury’s Finding that Brinkman Was 85% Comparatively Negligent
¶ 24 Ironshore argues that Pool & Spa presented insufficient
evidence supporting its affirmative defense that Brinkman was
comparatively negligent with respect to the design and installation
of the pool and spa. See Diodosio, 841 P.2d at 1057 (“The burden of
proving an affirmative defense rests upon the defendant asserting
the defense.”). “And without sufficient evidence to even justify a
negligence finding,” Ironshore further contends, “the jury could not
properly apportion 85% (or any) responsibility to Brinkman.”
Specifically, Ironshore asserts that Pool & Spa failed to introduce
expert testimony about the duty of care that Brinkman was
16 required to exercise during the pool project, much less testimony
showing that Brinkman breached that duty.
¶ 25 It’s true that Pool & Spa didn’t present expert testimony
stating that Brinkman, in Ironshore’s words, “violated industry or
professional standards of care in its work regarding the swimming
pool or surrounding areas.” But Ironshore doesn’t provide any
compelling argument or authority indicating why such testimony
was required under the circumstances of this case.
¶ 26 For example, Ironshore’s reliance on Holland v. Green
Mountain Swim Club, Inc., 470 P.2d 61, 63 (Colo. App. 1970) (not
published pursuant to C.A.R. 35(f)), in support of its argument is
misplaced. In that case, a division of this court upheld the trial
court’s causation finding regarding a defective pool because that
finding was supported by expert testimony. The division didn’t
address the applicable duty of care, let alone hold that such duty
may only be proved through expert testimony as Ironshore
contends. To the contrary, the division merely held that the expert
testimony supported the trial court’s finding.
¶ 27 Likewise, Ironshore’s reliance on BSLNI, Inc. v. Russ T.
Diamonds, Inc., 2012 COA 214, is unavailing. In BSLNI, a division
17 of this court rejected the defendant’s argument that the plaintiff
was required “to prove the standard of care for concrete cutters by
expert testimony because the standard of care involve[d]
consideration of industry standards and other considerations that
[were] technical and outside the common knowledge and experience
of laypersons.” Id. at ¶ 21. The division reasoned that “any
industry standards or practices were irrelevant” because the
plaintiff was asserting a breach of contract claim and the contract
specified the defendant’s duty of care. Id. at ¶ 22. However, the
BSLNI court didn’t address the issue of whether a party must
present expert testimony to establish the duty of care involving
industry standards or practices. Thus, we don’t see how this case
supports Ironshore’s position.
¶ 28 Regardless, our review of the record reveals that there was
sufficient evidence, including expert testimony, from which a
reasonable juror could have concluded what the duty of care was
and that Brinkman breached it. Tuck testified that as a general
contractor, Brinkman’s role was “to oversee the design and
construction of the pool.” He also testified that Brinkman was
aware that a leak collection system was necessary “to reduce the
18 potential for leak-induced post-construction heave” given that the
Kumar report had indicated that the soil had “potential for swell
and movement, and that . . . introducing water [was] going to
increase that risk.” Tuck stated that Brinkman was “responsible for
the pool” along with Pool & Spa and admitted that Brinkman
should have compared the shop drawings with the requirements of
the Kumar report.
¶ 29 Yet, as noted above, the record shows that Brinkman didn’t
explicitly request the leak collection system discussed in the Kumar
report, and along with Worth Group, it approved the shop drawings
that didn’t include that system. True, the record also shows that
Brinkman’s project manager included the relevant portions of the
report in the following email he sent to Pool & Spa’s owner: “Here is
the GEO tech report for the pool. I am not sure if you have seen
this yet, but here it is for your reference.” However, by that time,
Brinkman had already signed off on the pool design that didn’t
provide for the leak collection system. And only three days after the
email, Worth Group also approved the shop drawings without the
recommended feature.
19 ¶ 30 Kate opined that under these circumstances, Brinkman failed
to satisfy its obligations in ensuring the pool had the leak collection
system:
Brinkman’s primary responsibility or thing they missed was they never commissioned anybody to do the work, right. They never bid it out. They never assigned that scope of work to a contractor. They never got pricing for it. They never hired anybody to do the work, and so it never got done.
And he opined that Brinkman specifically failed to exercise
reasonable care in reviewing and approving the shop drawings:
I mean, if [Brinkman] had expected that Pool & Spa was going to do that work, then when Pool & Spa submitted those shop drawings of the work they were going to do, and there was no leak collection system there, then that would have been when Brinkman [was] supposed to say, hey, you guys, you’re supposed to do this leak collection system. Go get that on these drawings before we approve them.
But that never happened. And even after Worth Group specifically pointed to it and said, Brinkman, you need to verify that everything’s cool with the geotechnical report, it still didn’t happen. And so [Brinkman] missed it. They just -- they missed getting that scope of work assigned to anybody or hiring anybody to do it.
20 ¶ 31 When viewed in the light most favorable to the verdict, the
foregoing record supported the jury’s finding that Brinkman was
negligent in handling the pool project. See Parr, 107 P.3d at 1106.
As a result, we necessarily reject Ironshore’s claim that the jury
erred by apportioning 85% percent of the fault to Brinkman. There
is ample evidence in this record from which the jury could have
assigned more responsibility to Brinkman than to Pool & Spa.
¶ 32 In conclusion, Ironshore’s sufficiency challenge to the jury’s
negligence verdict fails.
D. Ironshore’s Challenges to the Indemnity Clause Verdict Fail
¶ 33 Ironshore contends that the jury erred by determining that
Pool & Spa didn’t breach the indemnity clause in its contract with
Brinkman because that determination lacked sufficient evidentiary
support and was inconsistent with the jury’s verdicts on the general
breach of contract and negligence claims. We’re not persuaded.
¶ 34 The indemnity clause was set forth in article 9.1.1 of the
contract:
To the fullest extent permitted by law, [Pool & Spa] shall defend, indemnify and hold harmless [Brinkman], [Brinkman’s] other subcontractors, the Architect/Engineer, the
21 [hotel] Owner and their agents, consultants and employees (the Indemnitees) from all claims for bodily injury and property damage that may arise from the performance of the Subcontract Work to the extent of the negligence attributed to such acts or omissions by [Pool & Spa], [Pool & Spa’s] subcontractors or anyone employed directly or indirectly by any of them or by anyone for whose acts any of them may be liable.
¶ 35 In finding that Pool & Spa didn’t violate this provision, the jury
answered “No” to the following question in Special Verdict Form D:
“Did the defendant [Pool & Spa] fail to defend, indemnify, and hold
harmless . . . Brinkman . . . for the damage attributed to [Pool &
Spa], its subcontractors, or anyone employed directly or indirectly
by any of them for whose acts any of them may be liable.”
(Emphasis added.) Jury instruction #16 clarified what the italicized
language above referred to by stating that for Ironshore to prevail
on this claim, the jury must find, among other things, that Pool &
Spa “failed to defend, indemnify, and hold harmless Brinkman for
the damage attributed to Pool & Spa for its failure to install the leak
collection system.” (Emphasis added.) The verdict form and the
jury instruction together indicated that Pool & Spa’s duties under
the indemnity clause were triggered only to the extent Pool & Spa
22 was negligent by failing to install the leak collection system in the
pool.
¶ 36 We conclude that the jury could have determined that Pool &
Spa wasn’t required to indemnify Brinkman for the losses related to
the missing leak collection system for two reasons. First, the jury
could have found that while Pool & Spa breached the contract in
some other way, it wasn’t responsible for the design and installation
of the leak collection system. After all, Pool & Spa argued that point
to the jury, and as noted above, it presented sufficient evidence
from which the jury could have concluded that those services
weren’t within its scope of work.
¶ 37 Second, recall that the jury attributed 85% of the fault to
Brinkman and only 15% of the fault to Pool & Spa. That
determination — which we uphold in this appeal — precluded
Ironshore from recovering any damages on its negligence claims
under the comparative negligence statute and the instruction that
was given to the jury. In pertinent part, the instruction provided
that if the jury found that
[Brinkman] and the defendant, [Pool & Spa], and [Worth Group] as [a] designated nonparty, were negligent and/or professionally negligent
23 and that the negligence of [Brinkman] was equal to or greater than the combined negligence of the defendant and the designated nonparty, then [Brinkman] will not be allowed to recover.
See § 13-21-111(1) (precluding recovery when a party’s negligence
was equal to or greater than the negligence of the person from
whom damages are sought).
¶ 38 Therefore, the jury’s comparative fault determination also
could have supported its finding that Pool & Spa wasn’t required to
indemnify, defend, and hold Brinkman harmless. Specifically,
because the jury found that Pool & Spa didn’t have to pay any
damages in connection with its negligent conduct, the jury
reasonably could have found that Pool & Spa didn’t breach the
indemnity clause by not paying Ironshore what it was entitled to
recover, which was nothing.
¶ 39 Finally, for the same two reasons, we conclude that the jury’s
verdict on this claim wasn’t inconsistent with its findings that Pool
& Spa breached the contract and was 15% negligent. Under these
circumstances, then, we have no basis to disturb the jury’s verdict
on Ironshore’s breach of the indemnity clause claim.
24 E. The Jury’s Award of No Damages Was Consistent with Its Other Findings
¶ 40 Ironshore contends that the jury erred by not awarding any
damages because after the jury found that Pool & Spa breached the
contract and was negligent in the performance of the pool project, it
was required to award Ironshore damages “within the range of the
evidence.” Ironshore asserts that based on the evidence presented
at trial, that range was from about $15,100, the amount Pool & Spa
argued that Brinkman would have spent had it properly mitigated
its damages, to about $647,000, the amount reflecting the total
replacement costs. Ironshore argues that the jury reasonably could
have awarded damages within this range and that its zero award
wasn’t supported by the evidence.
¶ 41 While Ironshore frames this issue as both a challenge to the
sufficiency of the evidence and a challenge to the consistency of the
jury’s verdicts, the resolution of the issue only implicates the
question of whether the jury’s award of no damages was
inconsistent with its findings that Pool & Spa breached the contract
and was negligent. Answering that question requires us to review
the jury instructions, the special verdict forms, and the evidence
25 that was presented to the jury in connection with Ironshore’s
general breach of contract and negligence claims. See Hock, 876
P.2d at 1259. After doing so, we conclude that the jury’s verdicts
on those claims weren’t inconsistent.
¶ 42 The jury completed two special verdict forms with respect to
Ironshore’s general breach of contract claim. On Special Verdict
Form C, as we note above, the jury found that Pool & Spa breached
its contract with Brinkman. But the jury also found with sufficient
evidentiary support that Brinkman failed to substantially perform
on its obligations under the contract. After the jury made that
finding, Special Verdict Form C required it to find in favor of Pool &
Spa and to fill out a separate Special Verdict Form E. In turn, the
latter verdict form simply stated that Ironshore wasn’t entitled to a
damages award.5 Thus, the jury’s award of no damages on the
general breach of contract claim was consistent with its finding that
Ironshore didn’t prevail on that claim because Brinkman failed to
substantially perform under the contract.
5 Ironshore didn’t object to the special verdict forms in the trial
court and doesn’t argue on appeal that they were improper.
26 ¶ 43 As for the negligence claims, the jury filled out Special Verdict
Form B. It answered “Yes” to the questions about whether Pool &
Spa was negligent and professionally negligent, and whether
Ironshore suffered damages as a result of Pool & Spa’s negligent
conduct. However, the jury also decided that Brinkman was
negligent and that its negligence was “a cause . . . of [its own]
damages and losses.” And the jury found Brinkman 85% at fault
for those damages. So the jury found that the total amount of
Ironshore’s general damages was zero.
¶ 44 This last finding is consistent with the jury’s apportionment of
comparative fault between the parties. Again, the jury instruction
addressing comparative negligence provided that Ironshore wouldn’t
be entitled to recover any damages if the jury were to determine
that Ironshore’s proportion of negligence was equal to or greater
than the negligence of Pool & Spa.6 Because the jury determined
that Brinkman was more negligent than Pool & Spa, there is no
error in the jury also finding that Ironshore’s general damages were
zero dollars. This was consistent with the jury instruction and the
6 Ironshore also didn’t object to this jury instruction at trial.
27 statute providing for no recovery of damages under those
circumstances. See § 13-21-111(1); see also City of Westminster v.
Centric-Jones Constructors, 100 P.3d 472, 486 (Colo. App. 2003) (“A
jury verdict will not be disturbed for inconsistency if a review of the
record indicates any basis for the verdict.”). Thus, we also don’t
discern any inconsistencies in the jury’s special verdict on the
negligence claims.
¶ 45 In sum, we conclude that the jury didn’t err by awarding
Ironshore no damages in connection with its general breach of
contract and negligence claims.
III. Appellate Costs
¶ 46 Lastly, we grant Pool & Spa’s request for appellate costs. See
C.A.R. 39(a)(2) (“[I]f a judgment is affirmed, costs are taxed against
the appellant.”). Pool & Spa may pursue those costs in the trial
court by following the procedure set forth in C.A.R. 39(c)(2).
IV. Disposition
¶ 47 The judgment is affirmed.
JUDGE WELLING and JUDGE SCHUTZ concur.