Ironshore v. Pool

CourtColorado Court of Appeals
DecidedApril 24, 2025
Docket24CA0996
StatusUnpublished

This text of Ironshore v. Pool (Ironshore v. Pool) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ironshore v. Pool, (Colo. Ct. App. 2025).

Opinion

24CA0996 Ironshore v Pool 04-24-2025

COLORADO COURT OF APPEALS

Court of Appeals No. 24CA0996 Adams County District Court No. 22CV30798 Honorable Arturo G. Hernandez, Judge

Ironshore Specialty Insurance Company, an Arizona corporation, as subrogee of Brinkman Construction, Inc.,

Plaintiff-Appellant,

v.

Pool and Spa Company, a Colorado limited liability company,

Defendant-Appellee.

JUDGMENT AFFIRMED

Division VI Opinion by JUDGE KUHN Welling and Schutz, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced April 24, 2025

Nicolaides Fink Thorpe Michaelides Sullivan, LLP, Matthew J. Fink, Denver, Colorado; Michael A. Yanof, Dallas, Texas, for Plaintiff-Appellant

Tyson & Mendes LLP, Michael D. Drews, Greenwood Village, Colorado, for Defendant-Appellee ¶1 Plaintiff, Ironshore Specialty Insurance Company, appeals the

trial court’s judgment entered upon jury verdicts in favor of

defendant, Pool and Spa Company (Pool & Spa), on Ironshore’s

breach of contract and negligence claims. We affirm.

I. Background

¶2 We glean the following factual and procedural background

from the record and evidence the jury heard at trial.

¶3 This construction defect dispute concerns the development of

a hotel in Westminster, Colorado. In 2019, the hotel’s owner,

Marriott International, hired Brinkman Construction, Inc., to serve

as the general contractor for the project. A few months later, Pool &

Spa entered into a subcontract with Brinkman, in which it agreed

to design and build an outdoor swimming pool and spa in the

hotel’s courtyard for $160,500. Pool & Spa began working on the

project in April 2020 after obtaining all the necessary approvals

from Brinkman and its architect, Worth Group Architects and

Designers. In July of that year, Pool & Spa completed the

installation of the pool and spa, the structures passed a final

inspection, and Pool & Spa requested payment of $35,000, the

outstanding contract balance.

1 ¶4 Brinkman rejected the payment request. Instead, it informed

Pool & Spa that it was terminating the contract because the

structures contained numerous material defects that Pool & Spa

had failed to correct. Specifically, the termination letter alleged that

Pool & Spa, among other things, hadn’t properly installed the

coping and handrails and had failed to install “auto fill components”

and a “chemical feeder” for the pool.

¶5 Roughly two months later, in November, Brinkman sent

Pool & Spa notice of claim under section 13-20-803.5, C.R.S. 2024.

In addition to the previously identified defects, and as relevant on

appeal, Brinkman alleged that Pool & Spa and Pool & Spa’s

subcontractor had failed to design and install a leak collection

system that a civil engineering company, Kumar & Associates, had

recommended in a 2017 geotechnical soils report (the Kumar

report). Brinkman alleged that the defects in Pool & Spa’s

workmanship “ha[d] led to water leaks, potential safety issues, and

surrounding soils movement.” Considering the nature of the

alleged defects, Brinkman asserted that “the only workable solution

[was] to demolish, remove and replace the swimming pool in its

entirety.” After Pool & Spa denied liability for the claimed defects,

2 Brinkman paid approximately $647,000 to replace the pool, the

spa, and the surrounding concrete pool deck.

¶6 In June 2022, Brinkman and its insurer, Ironshore, sued Pool

& Spa. About seven months later, Ironshore paid Brinkman

roughly $540,000 under its policy in exchange for a release of any

claims relating to the pool project. Then, as Brinkman’s subrogee,

Ironshore filed an amended complaint and asserted against Pool &

Spa claims for general breach of contract, breach of the indemnity

clause in article 9.1.1 of the contract, negligence, and professional

negligence. In the meantime, Pool & Spa filed a third-party

complaint against several entities that had participated in the

project, including Worth Group and Aquatic Engineering

Consultants, LLC (AEC), the subcontractor that Pool & Spa had

hired to design the pool and spa. The trial court eventually

dismissed the third-party defendants from the suit, and Ironshore’s

claims against Pool & Spa proceeded to a six-day jury trial.1

1 Specifically, Pool & Spa stipulated to AEC’s dismissal from the

case before trial. It also settled with Worth Group, which Pool & Spa designated as a nonparty at fault shortly before trial.

3 ¶7 The jury returned special verdicts finding that (1) Pool & Spa

breached the pool contract with Brinkman, but Brinkman failed to

substantially perform its obligations under that contract; (2) Pool &

Spa didn’t breach the indemnification clause; (3) Brinkman and

Pool & Spa were both negligent; (4) Pool & Spa was 15% at fault for

Brinkman’s damages and Brinkman was 85% at fault; and

(5) Ironshore wasn’t entitled to any damages on its claims.

Consequently, the trial court entered judgment in favor of Pool &

Spa.

II. Analysis

¶8 On appeal, Ironshore contends that the trial court reversibly

erred by entering judgment on the jury’s special verdicts because

the evidence was insufficient to support the jury’s findings that

Brinkman (1) breached the contract with Pool & Spa and (2) was

85% negligent. Ironshore also contends that the jury erred by

finding that (3) Pool & Spa didn’t breach the indemnity clause in the

contract, and (4) Ironshore wasn’t entitled to recover any damages

because the evidence was insufficient to support those findings and

the findings were inconsistent with other aspects of the jury’s

4 verdicts. We set forth the applicable standard of review before

addressing each of Ironshore’s contentions.

A. Standard of Review

¶9 We review sufficiency of the evidence claims de novo.2

Northstar Project Mgmt., Inc. v. DLR Grp., Inc., 2013 CO 12, ¶ 14. In

doing so, “we must determine whether the evidence, viewed as a

whole and in the light most favorable to the prevailing party, is

sufficient to support the verdict.” Parr v. Triple L & J Corp., 107

P.3d 1104, 1106 (Colo. App. 2004). We also must “draw every

reasonable inference from the evidence in favor of [the prevailing]

2 Pool & Spa contends that “[s]ufficiency of the evidence to support

a jury’s finding is not a question of law reviewed [de novo].” In support of its position, Pool & Spa appears to argue that de novo review only applies when a sufficiency of the evidence claim relates to an underlying question of law. This argument misses the mark. See Coors v. Sec. Life of Denver Ins. Co., 112 P.3d 59, 66 (Colo. 2005). Our sufficiency review doesn’t turn on whether the underlying issue is one of law or fact because we don’t review de novo the jury’s ultimate conclusion. See Mince v. Butters, 616 P.2d 127, 129 (Colo. 1980) (noting that while the sufficiency of the evidence in awarding damages is a question of law, whether to award those damages lies in the discretion of the trier of fact).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gordon v. Benson
925 P.2d 775 (Supreme Court of Colorado, 1996)
Transamerica Premier Insurance Co. v. Brighton School District 27J
940 P.2d 348 (Supreme Court of Colorado, 1997)
Western Distributing Co. v. Diodosio
841 P.2d 1053 (Supreme Court of Colorado, 1992)
Hock v. New York Life Insurance Co.
876 P.2d 1242 (Supreme Court of Colorado, 1994)
Mince v. Butters
616 P.2d 127 (Supreme Court of Colorado, 1980)
Brighton School District 27J v. Transamerica Premier Insurance Co.
923 P.2d 328 (Colorado Court of Appeals, 1996)
Parr v. TRIPLE L & J CORP.
107 P.3d 1104 (Colorado Court of Appeals, 2004)
Coors v. Security Life of Denver Insurance Co.
112 P.3d 59 (Supreme Court of Colorado, 2005)
Holland v. Green Mountain Swim Club, Inc.
470 P.2d 61 (Colorado Court of Appeals, 1970)
Harris Group, Inc. v. Robinson
209 P.3d 1188 (Colorado Court of Appeals, 2009)
City of Westminster v. Centric-Jones Constructors
100 P.3d 472 (Colorado Court of Appeals, 2004)
Hall v. Frankel
190 P.3d 852 (Colorado Court of Appeals, 2008)
Ferrer v. Okbamicael
2017 CO 14 (Supreme Court of Colorado, 2017)
State Farm Mutual Automobile Insurance Co. v. Fisher
2018 CO 39 (Supreme Court of Colorado, 2018)
People ex rel. S.G.L.
214 P.3d 580 (Colorado Court of Appeals, 2009)
Montgomery Elevator Co. v. Gordon
619 P.2d 66 (Supreme Court of Colorado, 1980)
Day v. Johnson
255 P.3d 1064 (Supreme Court of Colorado, 2011)
BSLNI, Inc. v. Russ T. Diamonds, Inc.
2012 COA 214 (Colorado Court of Appeals, 2012)
Northstar Project Management, Inc. v. DLR Group, Inc.
2013 CO 12 (Supreme Court of Colorado, 2013)
Stan Clauson Associates, Inc v. Coleman Bros. Construction, LLC
2013 COA 7 (Colorado Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Ironshore v. Pool, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ironshore-v-pool-coloctapp-2025.