Northstar Project Management, Inc. v. DLR Group, Inc.

2013 CO 12, 295 P.3d 956, 2013 Colo. LEXIS 115, 2013 WL 501375
CourtSupreme Court of Colorado
DecidedFebruary 11, 2013
DocketSupreme Court Case No. 11SC494
StatusPublished
Cited by328 cases

This text of 2013 CO 12 (Northstar Project Management, Inc. v. DLR Group, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northstar Project Management, Inc. v. DLR Group, Inc., 2013 CO 12, 295 P.3d 956, 2013 Colo. LEXIS 115, 2013 WL 501375 (Colo. 2013).

Opinion

JUSTICE RICE

delivered the Opinion of the Court.

1 1 In this contract action, we hold that the court of appeals erred when it held that the record designated by Respondent DLR Group, Inc. ("DLR") satisfied C.A.R. 10(b). DLR should have designated the entire trial transcript in this case along with all of the admitted exhibits to provide the appellate court with the necessary information to determine whether the evidence sufficiently supported the jury's verdict in favor of Petitioner Northstar Project Management, Inc. ("Northstar"). We therefore reverse the judgment of the court of appeals and remand for dismissal of DLR's appeal with prejudice pursuant to C.A.R. 88(e).

I. Facts and Procedural History

12 Northstar entered into a contract with DLR pursuant to which Northstar agreed to pay DLR $226,882 in exchange for DLR's completion of some of the tasks required under Northstar's agreement to operate and manage construction of a new building for the National Renewable Energy Laboratory. DLR began performing under the contract and submitted invoices to Northstar. North-star paid DLR in part, but became dissatisfied with DLR's performance before fully satisfying DLR's invoices. Northstar's president and sole employee, Leandra Thompson, withheld $110,502.84 from DLR as the parties attempted to work through their differences. These negotiations proved unsuccessful and Northstar terminated the contract.

T3 Northstar sued DLR for breach of contract and related declaratory relief. DLR counterclaimed for breach of contract and declaratory relief against Northstar. The case proceeded to a four-day jury trial.

14 Four witnesses, including Thompson, testified at trial regarding issues related to the parties' alleged breaches of the contract. The trial court also admitted a number of exhibits as evidence of the parties' contract claims. DLR moved the trial court for a directed verdiet at the close of Northstar's case-in-chief on the grounds that Northstar failed to show any damages. The trial court denied the motion. At the close of evidence, the trial court instructed the jury to determine whether either Northstar or DLR breached the contract based on "the sworn testimony of all of the witnesses, all exhibits which have been received in evidence, all facts which have been admitted or agreed to, and all presumptions stated in" the jury instructions.

1 5 The jury determined that DLR breached the contract and accordingly rendered a verdict in favor of Northstar on its breach of contract claim. The jury found that North-star suffered $151,186 in actual damages as a result of DLR's breach and-after subtracting the $110,502.84 that Thompson withheld from DLR prior to the commencement of the action from the total damages-awarded Northstar $40,688.16. To memorialize their decision, the jurors signed a verdict form [958]*958that read: "We, the jury, find for the Plaintiff, Northstar Project Management Inc., and award damages of $40,688.16 against the Defendant, DLR Group, Inc.".

16 DLR filed a post-trial motion for judgment notwithstanding the verdict ("JNOV"), or in the alternative, a new trial, arguing, among other things, that the jury erred as a matter of law because Northstar "failed to meet its prima fucte case" and because the verdiet was "not supported by any proper or legitimate measure of contract damages." DLR also took issue with the trial court's admission of several trial exhibits and argued that the admission of these exhibits led the jury to award "excessive" damages to North-star. The trial court denied the motion and entered judgment in favor of Northstar. It then awarded Northstar costs and pre-judgment interest in addition to its damages.

T7 DLR appealed the trial court's judgment to the court of appeals. About two weeks after filing its notice of appeal, DLR designated the appellate record. The designation included a transcript of Thompson's trial testimony, all of the exhibits admitted at trial, a transcript of the pre-trial conference regarding DLR's evidentiary motion in li-mine, and a transcript of the conference between the trial court and the parties regarding DLR's motion for directed verdict. The designation did not include a transcript of any of the other three witness's trial testimony. In its responsive brief to the court of appeals, Northstar argued that DLR failed to comply with C.A.R. 10(b) by neglecting to designate a complete trial transeript.

T8 The court of appeals held that DLR's designated record was adequate to review the sufficiency of the evidence to support the jury's verdiet under C.AR. 10(b). Northstar Project Mgmt., Inc. v. DLR Group, Inc., No. 10CA1057, slip op. at 10-12, 2011 WL 1631979 (Colo.App. Apr. 28, 2011) (not selected for official publication). It reasoned that it was "beyond reasonable dispute that Northstar's proof of damages was through Ms. Thompson's testimony and supporting Exhibits 105 and 186[,] ... [therefore, DLR provided us with the record necessary to review the jury's award." Id. at 11. Moreover, the court of appeals opined that C.A.R. 10) required Northstar, rather than DLR, to designate additional portions of the record that it deemed necessary to refute DLR's challenge to the sufficiency of the evidence supporting the jury verdict. Id. at 11-12. Having determined that DLR complied with C.AR. 10(b), the court of appeals analyzed the designated record and concluded that the evidence did not support the jury's verdict. Id. at 12. It accordingly vacated the jury's decision and remanded the case to the trial court for entry of an "award of $30,388.34 in favor of DLR." Id. at 22.

T9 In a dissenting opinion, Judge Jones opined that DLR failed to comply with C.AR. 10) and with Colorado case law because "a party challenging a finding on appeal must provide us with a complete ree-ord on the issue" Id. at 25 (Jones, J., dissenting). Judge Jones disagreed with the court of appeals majority's conclusion that it was beyond reasonable dispute that Thompson' s testimony and supporting exhibits 105 and 186 provided the only evidence necessary to review the sufficiency question, and also disagreed with the majority's decision to fault Northstar for failing to supplement the record with transcripts of additional trial testimony. Id. at 25-26 (Jones, J., dissenting).

110 We granted Northstar's petition for certiorari review of the court of appeals' opinion and now reverse the judgment of the court of appeals.1

II. Analysis

{11 DLR failed to comply with C.AR. 10(b) when it designated a partial trial tran-seript because it did not provide the court of appeals with "all evidence relevant" to the contention that the evidence did not suffi[959]*959ciently support the jury verdict. According ly, the court of appeals did not have an adequate record upon which to determine the sufficiency of the evidence issue. We therefore reverse the judgment of the court of appeals and remand for dismissal of DLR's appeal with prejudice pursuant to C.A.R. 38(e).

A. Standard of Review

§¥12 We review questions of law involving statutory interpretation de novo. Smith v. Exec. Custom Homes, Inc., 230 P.3d 1186, 1189 (Colo.2010). We interpret rules of procedure consistent with principles of statutory construction and, thus, review procedural rules de novo as well. People v. Zhuk, 239 P.3d 437, 438-39 (Colo.2010) (interpreting appellate rules on de novo review).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peo in Int of BDR
Colorado Court of Appeals, 2026
Vreeland v. Griffin
Colorado Court of Appeals, 2026
Green v. US Anesthesia
Colorado Court of Appeals, 2026
Bai v. Shoyu Denver
Colorado Court of Appeals, 2025
Stonig v. Midyette
Colorado Court of Appeals, 2025
V&H v. Beardsley
Colorado Court of Appeals, 2025
Peo v. Leary
Colorado Court of Appeals, 2025
Ironshore v. Pool
Colorado Court of Appeals, 2025
Guillot v. Salter
Colorado Court of Appeals, 2025
Mile Hi Vets v. Moreno
Colorado Court of Appeals, 2024
In Re: People v. James Dye
2024 CO 2 (Supreme Court of Colorado, 2024)
Tisch v. Tisch
2019 COA 41 (Colorado Court of Appeals, 2019)
Love v. Klosky
2016 COA 131 (Colorado Court of Appeals, 2016)
Johnson v. VCG Restaurants Denver
2015 COA 179 (Colorado Court of Appeals, 2015)
Johnson v. VCG Restaurants Denver, Inc
2015 COA 179 (Colorado Court of Appeals, 2015)
People v. Duran
2015 COA 141 (Colorado Court of Appeals, 2015)
People v. Shifrin
2014 COA 14 (Colorado Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2013 CO 12, 295 P.3d 956, 2013 Colo. LEXIS 115, 2013 WL 501375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northstar-project-management-inc-v-dlr-group-inc-colo-2013.