Flagstaff Enterprises Construction, Inc. v. Snow

908 P.2d 1183, 19 Brief Times Rptr. 1599, 1995 Colo. App. LEXIS 312, 1995 WL 656892
CourtColorado Court of Appeals
DecidedNovember 9, 1995
Docket94CA1205
StatusPublished
Cited by26 cases

This text of 908 P.2d 1183 (Flagstaff Enterprises Construction, Inc. v. Snow) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flagstaff Enterprises Construction, Inc. v. Snow, 908 P.2d 1183, 19 Brief Times Rptr. 1599, 1995 Colo. App. LEXIS 312, 1995 WL 656892 (Colo. Ct. App. 1995).

Opinion

Opinion by

Judge NEY.

In this construction contract dispute, defendants, Theodore P. and Constance M. Snow (owners), appeal the judgment entered after a trial to the court in favor of plaintiff, Flagstaff Enterprises Construction, Inc. (builder). We affirm.

The parties entered into an oral agreement for builder to sell the owners land and build a home for them on the land. It is undisputed that the original price of the land and the home was $210,000, which later increased to $215,020. It is also undisputed that owners paid a portion of the total purchase price and that the parties orally agreed that the owners would pay the balance over a thirty-year period. However, the parties dispute the amount of the final purchase price and the amount of the unpaid balance.

Builder brought this action when owners ceased making payments on the balance. Owners asserted, as an affirmative defense, a setoff related to an allegedly defective roof.

At trial, builder introduced testimony that owners requested construction changes total-ling an additional $18,900, thus increasing the total purchase price from $215,020 to approximately $234,000. Builder introduced evidence that the parties orally agreed that there was an unpaid balance due builder of $30,000, which would be paid over thirty years at 10% interest, with monthly payments of $275. Builder’s evidence included a thirty-year amortization schedule hand-written by owner Theodore Snow showing a beginning balance of $30,000, as well as copies of owners’ monthly cheeks to builder, or its assignee, showing uniform payments for five years in accordance with this amortization schedule.

Builder presented evidence that it had received $187,890 of the price from the owners’ bank and a $15,000 payment directly from the owners, for a total of $202,890. Builder also testified that the parties agreed the unpaid balance was $30,000 after the owners had made the $15,000 payment. Builder testified that the total amount owed by owners, with unpaid interest, was $34,000.

Owners testified that the final price did not increase above $216,000. They disputed there were changes that increased the price of the home, stating that some of the changes described by builder had been included in the original plans for the home. They also testified that they had paid for some of the contract items themselves.

The owners acknowledged they had agreed with builder that there was an unpaid balance of $30,000. However, they testified they made this agreement in the belief that they had only paid $185,000 at that time. They testified that after the parties reached the amortization agreement relating to the $30,000 balance, they made a lump sum prepayment of $15,000 towards this balance. They also testified that seven years after this agreement, they concluded they had paid for the home’s building permit at the start of construction, which reduced their unpaid balance by $16,000. They testified that this reduction, together with the payment of $15,-000, left no unpaid balance.

After a bench trial, the trial court found that the purchase price had increased to $234,000 because of construction changes requested by the owners and that the owners had only paid builder $202,890. The trial court found that the parties had taken these figures into account when they agreed the unpaid balance was $30,000. Thus, the trial court ruled that the owners breached their agreement to make monthly payments on the $30,000 balance and owed builder $34,722.40.

I.

The owners contend the trial court’s finding that owners had paid builder only $202,890.07 was contrary to the undisputed evidence. We disagree.

There is a presumption that a judgment entered by the trial court is correct. Colorado National Bank —Boulder v. Zerobnick & Sander, P.C., 768 P.2d 1276 (Colo.App.1989).

*1185 The trial court’s determination of the sufficiency, probative effect, and weight of the evidence, as well as the credibility of the witnesses must be accepted on appeal unless the findings are so clearly erroneous as not to find support in the record. M.D.C./Wood, Inc. v. Mortimer, 866 P.2d 1380 (Colo.1994).

And, when evidence is conflicting, a reviewing court may not substitute its conclusions for those of the trial court merely because there may be credible evidence supporting a different result. See Page v. Clark, 197 Colo. 306, 592 P.2d 792 (1979).

Here, the record reveals that the issues concerning the amounts paid by the owners and owed to the builder were the subjects of conflicting testimony. Nevertheless, after the controversy arose, both parties agreed that a $30,000 balance was owed to the builder. See Caldwell v. Armstrong, 642 P.2d 47 (Colo.1982). The trial court’s findings and conclusions are adequately supported by the record. Thus, they are binding on appeal. See M.D.C./Wood, Inc. v. Mortimer, supra.

We do not consider owners’ argument that the parties’ agreement was based on a mutual mistake of fact because it was raised for the first time in them reply brief. See People v. Czemerynski 786 P.2d 1100 (Colo.1990); Knappenberger v. Shea, 874 P.2d 498 (Colo.App.1994) (issues not presented in an opening brief generally are not considered by the court).

II.

The owners next contend that the trial court erred in ruling that the statute of limitations barred them affirmative defense based on a setoff for defective construction. We do not address this contention because it was not properly presented to the trial court. See In re Estate of Stevenson v. Hollywood Bar & Cafe, Inc., 832 P.2d 718 (Colo.1992) (issues, defenses, and objections not presented at trial and considered or ruled upon by a trial court are deemed waived and cannot be raised for the first time on appeal).

Because the owners first contended that the applicable statute of limitations was § 13-80-109, C.R.S. (1987 Repl.Vol. 6A) in their reply brief in support of their C.R.C.P. 59 motion, the builder was unable to address owners’ contention before the trial court, and the trial court made no findings or conclusions as to owners’ contention. See Dahl v. Young, 862 P.2d 969 (Colo.App.1993) (issue raised after all evidence and argument concluded not considered on appeal). Hence, the reasoning of People v. Czemerynski supra, and Knappenberger v. Shea, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitt v. Colorado Retina Associates
Colorado Court of Appeals, 2026
Marriage of Kinning
Colorado Court of Appeals, 2025
Egbune v. Always Enterprises
Colorado Court of Appeals, 2025
Karl v. Dept of Safety
Colorado Court of Appeals, 2024
GSI v. Hudson
Colorado Court of Appeals, 2021
Family v. Pomeroy
2021 COA 73 (Colorado Court of Appeals, 2021)
v. Boulder Community Health
2018 COA 126 (Colorado Court of Appeals, 2018)
Perfect Place, LLC v. Semler
2016 COA 152 (Colorado Court of Appeals, 2016)
Core-Mark Midcontinent Inc. v. Sonitrol Corporation
2016 COA 22 (Colorado Court of Appeals, 2016)
Core-Mark Midcontinent Inc. v. Sonitrol Corp.
2016 COA 22 (Colorado Court of Appeals, 2016)
Calvin v. Stirling Ranch Prop. Owners Ass'n, Inc.
411 P.3d 145 (Colorado Court of Appeals, 2015)
Patterson v. BP America Production Co.
2015 COA 28 (Colorado Court of Appeals, 2015)
Liberty Bankers Life Ins. Co. v. First Citizens Bank & Trust Co.
411 P.3d 111 (Colorado Court of Appeals, 2014)
Maralex Resources, Inc. v. Chamberlain
2014 COA 5 (Colorado Court of Appeals, 2014)
Meyer v. Haskett
251 P.3d 1287 (Colorado Court of Appeals, 2010)
Negron v. Gillespie
111 P.3d 556 (Colorado Court of Appeals, 2005)
City of Westminster v. Centric-Jones Constructors
100 P.3d 472 (Colorado Court of Appeals, 2004)
Town of Frederick v. North American Resources Co.
60 P.3d 758 (Colorado Court of Appeals, 2002)
Spencer v. Board of County Commissioners
39 P.3d 1272 (Colorado Court of Appeals, 2001)
Lawrence Ex Rel. Fritz v. Taylor
8 P.3d 607 (Colorado Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
908 P.2d 1183, 19 Brief Times Rptr. 1599, 1995 Colo. App. LEXIS 312, 1995 WL 656892, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flagstaff-enterprises-construction-inc-v-snow-coloctapp-1995.