MarkWest v. Rose

Colorado Court of Appeals·Decided April 24, 2025·No. 23CA0139 & 23CA0596·Unpublished

Opinion

23CA0139 & 23CA0596 MarkWest v Rose 04-24-2025 COLORADO COURT OF APPEALS

Court of Appeals Nos. 23CA0139 & 23CA0596 City and County of Denver District Court No. 18CV34272 Honorable Jill D. Dorancy, Judge Honorable Darryl F. Shockley, Judge

MarkWest Liberty Midstream & Resources, L.L.C., a Delaware limited liability company,

Plaintiff-Appellee and Cross-Appellant, v. John W. Rose, as litigation trustee for Meridien Litigation Trust, Defendant-Appellant and Cross-Appellee.

JUDGMENT AFFIRMED IN PART AND REVERSED IN PART, AND CASE REMANDED WITH DIRECTIONS

Division II

Opinion by JUDGE FOX

Gomez and Lum, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e)

Announced April 24, 2025

Snell & Wilmer L.L.P., James Kilroy, Ellie Lockwood, Denver, Colorado, for Plaintiff-Appellee and Cross-Appellant

Davis Graham & Stubbs LLP, Theresa Wardon Benz, Claire E. Mueller, Hannah McCrory, Denver, Colorado, for Defendant-Appellant and Cross-Appellee

¶1 Meridien Energy, L.L.C. (Meridien), through its litigation trustee, John W. Rose, appeals the district court’s judgment partially in favor of MarkWest Liberty Midstream & Resources, L.L.C. (MarkWest). MarkWest, in turn, cross-appeals the district court’s judgment partially in favor of Meridien. We affirm in part, reverse in part, and remand with directions.

I. Background

¶2 In 2018, MarkWest hired Meridien to construct an approximately eleven-mile portion of a longer natural gas liquids pipeline project in West Virginia. Meridien and MarkWest entered into a “Lump Sum Pipeline Construction Contract” (the Contract) on March 9, 2018, which specified Meridien would complete the pipeline project by November 15, 2018, in exchange for $34,814,000. The project was greatly delayed, however, and by October 16, 2018, Meridien had completed only approximately 150 feet of the pipeline. The cause of the delays was heavily contested at trial.

¶3 On October 8, 2018, Meridien wrote to MarkWest, requesting the work schedule be amended and demanding $16,099,986.00 in additional compensation for delays and costs that Meridien

attributed to MarkWest and to weather events (the Demand Letter). On October 16, MarkWest terminated the Contract for cause, alleging Meridien was responsible for environmental noncompliance and project delays. MarkWest hired new contractors, but the entire pipeline project was not finished until July 2019.

¶4 MarkWest sued Meridien in November 2018, and Meridien soon counterclaimed. As relevant to this appeal, MarkWest and Meridien both raised claims for breach of contract and breach of the implied duty of good faith and fair dealing. Meridien also raised a claim for unjust enrichment that the court decided after trial.

¶5 After a fifteen-day trial, the jury ruled partially in favor of MarkWest and partially in favor of Meridien. It found that Meridien (1) breached the Contract and (2) breached the implied duty of good faith and fair dealing. The jury awarded MarkWest $16,008,831.77 in damages for the former and no damages for the latter. It also found, however, that MarkWest had similarly breached its implied duty of good faith and fair dealing, and it awarded Meridien $1,510,362.00 in damages. The court then decided Meridien’s counterclaim for unjust enrichment and awarded Meridien

$2,562,994.15 plus interest. This appeal and cross-appeal followed.

¶6 Part II of this opinion addresses Meridien’s appeal, which pertains to each party’s claims for breach of the implied duty of good faith and fair dealing, an evidentiary ruling, and a jury instruction. We affirm the district court’s decisions on each issue.

¶7 Part III addresses MarkWest’s cross-appeal, which pertains to Meridien’s unjust enrichment counterclaim. In its cross-appeal, MarkWest argues that the district court (1) erroneously allowed the counterclaim to proceed and (2) applied the wrong interest rate to Meridien’s restitution award. We affirm the restitution award for unjust enrichment but reverse as to the applicable interest rate.

II. Meridien’s Appeal A. The Jury’s Verdicts

¶8 Meridien first contends that the jury’s verdicts are inconsistent and irreconcilable.

1. Additional Background

¶9 After the jury issued its verdicts, Meridien moved for judgment notwithstanding the verdict (JNOV) pursuant to C.R.C.P. 59, or, alternatively, a new trial. As relevant here, Meridien argued that

the jury instructions presented the breach of the implied duty of good faith and fair dealing claims as substantive claims and affirmative defenses — therefore the jury could not have awarded damages when it found both parties breached the implied duty. Meridien cited several jury instructions and the verdict form to support its contentions.

¶ 10 Instruction 14 informed the jury about material breaches of contract, stating that “[a] breach is not material if the other party receives substantially what it contracted for. In determining whether a breach is material, you may consider the nature of the promised performance, the purpose of the contract, and whether any defects in performance have defeated the purpose of the contract.” The instruction added that “[a] material breach by one party excuses performance by the other party to the contract.”

¶ 11 Instruction 16, concerning MarkWest’s breach of contract claim, provided that if the jury found that MarkWest proved the elements of breach of contract, the jury “must consider Meridien’s affirmative defenses,” and if “any one of those affirmative defenses has been proved by a preponderance of the evidence, then [its] verdict must be for Meridien.” Instruction 17 stated that

“MarkWest has raised breach of the implied duty of good faith and fair dealing as both a counterclaim and affirmative defense.”

¶ 12 The instructions for Meridien’s claims mirrored these instructions. Instruction 21 provided that Meridien “raised breach of the implied duty of good faith and fair dealing as both a counterclaim and affirmative defense.” Instruction 20 provided that if the jury found that Meridien proved its claim, the jury was required to “consider MarkWest’s affirmative defenses. . . . If [it] [found] that any one of those affirmative defenses ha[d] been proved by a preponderance of the evidence, then [its] verdict must be for MarkWest.”

¶ 13 Instruction 25, concerning damages, provided that if the jury found “in favor of MarkWest on its claim of breach of contract or breach of the implied duty of good faith and fair dealing, then [it] may award [MarkWest] damages.” And if the jury found “in favor of Meridien on its counterclaim of breach of contract or breach of the implied duty of good faith and fair dealing, then [it] may award [Meridien] damages.” Instruction 26 informed the jury that if it found “for either party on more than one claim for relief,” then it could “award it damages only once for the same damages.”

¶ 14 Using these instructions, the jury answered “yes” to three questions on the verdict form:

Do you find by a preponderance of the evidence that MarkWest is entitled to recover from Meridien on its claim for breach of contract, after taking into account any affirmative defenses proven by Meridien by a preponderance of the evidence? . . .

Do you find by a preponderance of the evidence that MarkWest is entitled to recover from Meridien on its claim for breach of the implied duty of good faith and fair dealing, after taking into account any affirmative defenses proven by Meridien by a preponderance of the evidence? . . .

Do you find by a preponderance of the evidence that Meridien is entitled to recover from MarkWest on its claim for breach of the implied duty of good faith and fair dealing, after taking into account any affirmative defenses proven by MarkWest by a preponderance of the evidence? . . .

¶ 15 The jury answered “no” to one question:

Free access — add to your briefcase to read the full text and ask questions with AI

MarkWest v. Rose, (Colo. Ct. App. 2025).

MarkWest v. Rose (MarkWest v. Rose) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of West Palm Beach v. Visionair, Inc.
199 F. App'x 768 (Eleventh Circuit, 2006)
Nelson v. Elway
908 P.2d 102 (Supreme Court of Colorado, 1995)
Associates of San Lazaro v. San Lazaro Park Properties
864 P.2d 111 (Supreme Court of Colorado, 1993)
Rodriguez v. Schutt
896 P.2d 881 (Colorado Court of Appeals, 1995)
Murdock v. Cohen
762 P.2d 691 (Colorado Court of Appeals, 1988)
H & H Distributors, Inc. v. BBC International, Inc.
812 P.2d 659 (Colorado Court of Appeals, 1990)
V. C. Edwards Contracting Co. v. Port of Tacoma
514 P.2d 1381 (Washington Supreme Court, 1973)
Jarosz v. Caesar Realty, Inc.
220 N.W.2d 191 (Michigan Court of Appeals, 1974)
O'QUINN v. Baca
250 P.3d 629 (Colorado Court of Appeals, 2010)
Bly v. Story
241 P.3d 529 (Supreme Court of Colorado, 2010)
Murray Equipment Co. v. Curtis, Inc.
725 P.2d 35 (Colorado Court of Appeals, 1986)
Dinosaur Park Investments, L.L.C. v. Tello
192 P.3d 513 (Colorado Court of Appeals, 2008)
Horton v. Suthers
43 P.3d 611 (Supreme Court of Colorado, 2002)
Aloi v. Union Pacific Railroad Corp.
129 P.3d 999 (Supreme Court of Colorado, 2006)
Specialized Grading Enterprises, Inc. v. Goodland Construction, Inc.
181 P.3d 352 (Colorado Court of Appeals, 2007)
City of Westminster v. Centric-Jones Constructors
100 P.3d 472 (Colorado Court of Appeals, 2004)
Pfantz v. Kmart Corp.
85 P.3d 564 (Colorado Court of Appeals, 2004)
In re Estate of Owens
2017 COA 53 (Colorado Court of Appeals, 2017)
v. Parrish
2019 COA 19 (Colorado Court of Appeals, 2019)