MarkWest v. Rose

CourtColorado Court of Appeals
DecidedApril 24, 2025
Docket23CA0139 & 23CA0596
StatusUnpublished

This text of MarkWest v. Rose (MarkWest v. Rose) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MarkWest v. Rose, (Colo. Ct. App. 2025).

Opinion

23CA0139 & 23CA0596 MarkWest v Rose 04-24-2025

COLORADO COURT OF APPEALS

Court of Appeals Nos. 23CA0139 & 23CA0596 City and County of Denver District Court No. 18CV34272 Honorable Jill D. Dorancy, Judge Honorable Darryl F. Shockley, Judge

MarkWest Liberty Midstream & Resources, L.L.C., a Delaware limited liability company,

Plaintiff-Appellee and Cross-Appellant,

v.

John W. Rose, as litigation trustee for Meridien Litigation Trust,

Defendant-Appellant and Cross-Appellee.

JUDGMENT AFFIRMED IN PART AND REVERSED IN PART, AND CASE REMANDED WITH DIRECTIONS

Division II Opinion by JUDGE FOX Gomez and Lum, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced April 24, 2025

Snell & Wilmer L.L.P., James Kilroy, Ellie Lockwood, Denver, Colorado, for Plaintiff-Appellee and Cross-Appellant

Davis Graham & Stubbs LLP, Theresa Wardon Benz, Claire E. Mueller, Hannah McCrory, Denver, Colorado, for Defendant-Appellant and Cross-Appellee ¶1 Meridien Energy, L.L.C. (Meridien), through its litigation

trustee, John W. Rose, appeals the district court’s judgment

partially in favor of MarkWest Liberty Midstream & Resources,

L.L.C. (MarkWest). MarkWest, in turn, cross-appeals the district

court’s judgment partially in favor of Meridien. We affirm in part,

reverse in part, and remand with directions.

I. Background

¶2 In 2018, MarkWest hired Meridien to construct an

approximately eleven-mile portion of a longer natural gas liquids

pipeline project in West Virginia. Meridien and MarkWest entered

into a “Lump Sum Pipeline Construction Contract” (the Contract) on

March 9, 2018, which specified Meridien would complete the

pipeline project by November 15, 2018, in exchange for

$34,814,000. The project was greatly delayed, however, and by

October 16, 2018, Meridien had completed only approximately 150

feet of the pipeline. The cause of the delays was heavily contested

at trial.

¶3 On October 8, 2018, Meridien wrote to MarkWest, requesting

the work schedule be amended and demanding $16,099,986.00 in

additional compensation for delays and costs that Meridien

1 attributed to MarkWest and to weather events (the Demand Letter).

On October 16, MarkWest terminated the Contract for cause,

alleging Meridien was responsible for environmental noncompliance

and project delays. MarkWest hired new contractors, but the entire

pipeline project was not finished until July 2019.

¶4 MarkWest sued Meridien in November 2018, and Meridien

soon counterclaimed. As relevant to this appeal, MarkWest and

Meridien both raised claims for breach of contract and breach of the

implied duty of good faith and fair dealing. Meridien also raised a

claim for unjust enrichment that the court decided after trial.

¶5 After a fifteen-day trial, the jury ruled partially in favor of

MarkWest and partially in favor of Meridien. It found that Meridien

(1) breached the Contract and (2) breached the implied duty of good

faith and fair dealing. The jury awarded MarkWest $16,008,831.77

in damages for the former and no damages for the latter. It also

found, however, that MarkWest had similarly breached its implied

duty of good faith and fair dealing, and it awarded Meridien

$1,510,362.00 in damages. The court then decided Meridien’s

counterclaim for unjust enrichment and awarded Meridien

2 $2,562,994.15 plus interest. This appeal and cross-appeal

followed.

¶6 Part II of this opinion addresses Meridien’s appeal, which

pertains to each party’s claims for breach of the implied duty of

good faith and fair dealing, an evidentiary ruling, and a jury

instruction. We affirm the district court’s decisions on each issue.

¶7 Part III addresses MarkWest’s cross-appeal, which pertains to

Meridien’s unjust enrichment counterclaim. In its cross-appeal,

MarkWest argues that the district court (1) erroneously allowed the

counterclaim to proceed and (2) applied the wrong interest rate to

Meridien’s restitution award. We affirm the restitution award for

unjust enrichment but reverse as to the applicable interest rate.

II. Meridien’s Appeal

A. The Jury’s Verdicts

¶8 Meridien first contends that the jury’s verdicts are inconsistent

and irreconcilable.

1. Additional Background

¶9 After the jury issued its verdicts, Meridien moved for judgment

notwithstanding the verdict (JNOV) pursuant to C.R.C.P. 59, or,

alternatively, a new trial. As relevant here, Meridien argued that

3 the jury instructions presented the breach of the implied duty of

good faith and fair dealing claims as substantive claims and

affirmative defenses — therefore the jury could not have awarded

damages when it found both parties breached the implied duty.

Meridien cited several jury instructions and the verdict form to

support its contentions.

¶ 10 Instruction 14 informed the jury about material breaches of

contract, stating that “[a] breach is not material if the other party

receives substantially what it contracted for. In determining

whether a breach is material, you may consider the nature of the

promised performance, the purpose of the contract, and whether

any defects in performance have defeated the purpose of the

contract.” The instruction added that “[a] material breach by one

party excuses performance by the other party to the contract.”

¶ 11 Instruction 16, concerning MarkWest’s breach of contract

claim, provided that if the jury found that MarkWest proved the

elements of breach of contract, the jury “must consider Meridien’s

affirmative defenses,” and if “any one of those affirmative defenses

has been proved by a preponderance of the evidence, then [its]

verdict must be for Meridien.” Instruction 17 stated that

4 “MarkWest has raised breach of the implied duty of good faith and

fair dealing as both a counterclaim and affirmative defense.”

¶ 12 The instructions for Meridien’s claims mirrored these

instructions. Instruction 21 provided that Meridien “raised breach

of the implied duty of good faith and fair dealing as both a

counterclaim and affirmative defense.” Instruction 20 provided that

if the jury found that Meridien proved its claim, the jury was

required to “consider MarkWest’s affirmative defenses. . . . If [it]

[found] that any one of those affirmative defenses ha[d] been proved

by a preponderance of the evidence, then [its] verdict must be for

MarkWest.”

¶ 13 Instruction 25, concerning damages, provided that if the jury

found “in favor of MarkWest on its claim of breach of contract or

breach of the implied duty of good faith and fair dealing, then [it]

may award [MarkWest] damages.” And if the jury found “in favor of

Meridien on its counterclaim of breach of contract or breach of the

implied duty of good faith and fair dealing, then [it] may award

[Meridien] damages.” Instruction 26 informed the jury that if it

found “for either party on more than one claim for relief,” then it

could “award it damages only once for the same damages.”

5 ¶ 14 Using these instructions, the jury answered “yes” to three

questions on the verdict form:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of West Palm Beach v. Visionair, Inc.
199 F. App'x 768 (Eleventh Circuit, 2006)
Nelson v. Elway
908 P.2d 102 (Supreme Court of Colorado, 1995)
Associates of San Lazaro v. San Lazaro Park Properties
864 P.2d 111 (Supreme Court of Colorado, 1993)
Rodriguez v. Schutt
896 P.2d 881 (Colorado Court of Appeals, 1995)
Murdock v. Cohen
762 P.2d 691 (Colorado Court of Appeals, 1988)
H & H Distributors, Inc. v. BBC International, Inc.
812 P.2d 659 (Colorado Court of Appeals, 1990)
V. C. Edwards Contracting Co. v. Port of Tacoma
514 P.2d 1381 (Washington Supreme Court, 1973)
Jarosz v. Caesar Realty, Inc.
220 N.W.2d 191 (Michigan Court of Appeals, 1974)
O'QUINN v. Baca
250 P.3d 629 (Colorado Court of Appeals, 2010)
Bly v. Story
241 P.3d 529 (Supreme Court of Colorado, 2010)
Murray Equipment Co. v. Curtis, Inc.
725 P.2d 35 (Colorado Court of Appeals, 1986)
Dinosaur Park Investments, L.L.C. v. Tello
192 P.3d 513 (Colorado Court of Appeals, 2008)
Horton v. Suthers
43 P.3d 611 (Supreme Court of Colorado, 2002)
Aloi v. Union Pacific Railroad Corp.
129 P.3d 999 (Supreme Court of Colorado, 2006)
Specialized Grading Enterprises, Inc. v. Goodland Construction, Inc.
181 P.3d 352 (Colorado Court of Appeals, 2007)
City of Westminster v. Centric-Jones Constructors
100 P.3d 472 (Colorado Court of Appeals, 2004)
Pfantz v. Kmart Corp.
85 P.3d 564 (Colorado Court of Appeals, 2004)
In re Estate of Owens
2017 COA 53 (Colorado Court of Appeals, 2017)
v. Parrish
2019 COA 19 (Colorado Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
MarkWest v. Rose, Counsel Stack Legal Research, https://law.counselstack.com/opinion/markwest-v-rose-coloctapp-2025.