Stanley Miller Constr. Co. v. State

2010 Ohio 1488
CourtOhio Court of Claims
DecidedMarch 1, 2010
Docket2006-05632-PR
StatusPublished

This text of 2010 Ohio 1488 (Stanley Miller Constr. Co. v. State) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanley Miller Constr. Co. v. State, 2010 Ohio 1488 (Ohio Super. Ct. 2010).

Opinion

[Cite as Stanley Miller Constr. Co. v. State, 2010-Ohio-1488.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

STANLEY MILLER CONSTRUCTION CO.

Plaintiff

v.

STATE OF OHIO

Defendant

and

CANTON CITY SCHOOL DISTRICT BOARD OF EDUCATION, et al.

Defendants/Third-Party Plaintiffs

OHIO SCHOOL FACILITIES COMMISSION

Defendant/Third-Party Defendant Case No. 2006-05632-PR

Judge Joseph T. Clark

DECISION

{¶ 1} Plaintiff, Stanley Miller Construction Company (Stanley Miller), brought this action against defendants, Ohio School Facilities Commission (OSFC) and Canton City School District Board of Education (Canton), alleging breach of contract, negligence, and unjust enrichment. The case was tried to the court on the issues of liability and damages. {¶ 2} The procedural history of this case begins on June 30, 2006, when Stanley Miller filed a complaint against Canton in the Stark County Court of Common Pleas. Canton filed an answer to Stanley Miller’s complaint and a third-party complaint against OSFC on August 16, 2006. The filing of the third-party complaint against OSFC in the common pleas court, combined with the later mandatory filing of a petition for removal in this court on September 1, 2006, effected the removal of the case to this court pursuant to R.C. 2743.03(E).1 {¶ 3} Stanley Miller entered into a contract with OSFC and Canton in January 2003 for the construction of what was to be the Lehman Middle School (Lehman project). During the construction phase, ownership of the proposed middle school was to be shared by OSFC (77 percent) and Canton (23 percent). Although Canton was not a signatory to the contract between OSFC and Stanley Miller, there is no dispute that Canton was an intended beneficiary of such contract.2 {¶ 4} Stanley Miller was a prime contractor on the project having been awarded a contract for numerous divisions of the work, including the division for masonry, which was the largest single component of the project. Jeffrey Tuckerman, OSFC’s project administrator, selected Ruhlin Construction (Ruhlin) as construction manager for the Lehman project. According to Tuckerman, Ruhlin was an extension of OSFC with respect to the management of the Lehman project. {¶ 5} Stanley Miller alleges that their work on the Lehman project was plagued by a myriad of costly inefficiencies that were caused by factors outside of its control. For example, Stanley Miller alleges that the combined effect of a hopelessly flawed construction schedule and the persistent meddling of Ruhlin resulted in delays and extra work. {¶ 6} On July 2, 2004, the scheduled project completion date, Stanley Miller submitted a one-page document to OSFC wherein Stanley Miller demanded that OSFC make an equitable adjustment to the contract price of more than $1.1 million in order to compensate Stanley Miller for unanticipated additional costs it had incurred on the project. The document was authored by Stanley Miller Vice President and Co-owner,

1 On June 29, 2006, Stanley Miller filed an original action in this court against OSFC arising from the same transaction. See Stanley Miller Constr. Co. v. OSFC, Ct. of Cl. No. 2006-04351. Although the two cases were combined for trial, the court will issue a separate decision for each case. 2 OSFC and Canton will be referred to collectively as “OSFC” throughout this decision. Steve Miller, and became known at trial as the “one-page, $1.1 million claim.” (Plaintiff’s Exhibit 64.) The document reads as follows:

Est. Actual Difference Masonry costs including labor, material and equipment 2,274,738.00 2,751,130.77 (476,392.77) Cold Weather Protect 0.00 35,973.27 (35,973.27) Backfill Retaining Walls 17,400.00 51,707.84 (34,307.84) Concrete Costs 404,200.00 507,029.96 (102,829.96) Clean Up Costs 23,000.00 56,583.29 (33,583.29) Temp. Roads, Repair Sub- grade 8,500.00 25,973.04 (17,473.04) Sewer Work 53,700.00 71,364.53 (17,664.53) Roof Trusses 221,600.00 291,974.39 (70,374.39) Total Losses (788,598.79) Total OH & (350,000.00) Profit (1,138,598.79 )

Current 5,923,846.19 Contract Costs as of this date (7/1/04) (6,660,747.80 ) (736,901.61) Estimated costs to complete, (Concrete bills yet to (51,697.18) arrive and labor to install curb and sidewalk along Broad St.) (788,598.79) {¶ 7} Although there were some subsequent communications between the parties regarding the claim and a brief meeting which occurred in July 2004, it is clear that no payment was made. Plaintiff now seeks to recover these additional costs under theories of breach of contract, negligence, and unjust enrichment. The third-party complaint states a claim for contractual indemnity. I. THE LEHMAN PROJECT {¶ 8} As stated above, following a competitive bidding process, Stanley Miller was awarded a contract for multiple divisions of the work on the Lehman project, including the following : {¶ 9} “1. Bid Package 2B - Site Work is generally all labor, equipment, material and supervision as required to complete: site development, removal of existing concrete and asphalt, earthwork, asphalt paving, concrete walks and curbs, sewer collection systems, bicycle parking racks, landscape work, and site concrete. {¶ 10} “2. Bid Package 3B - Interior Concrete Slabs is generally all labor, equipment, material and supervision as required to complete: slab on grade and slab of deck. {¶ 11} “3. Bid Package 4A - Masonry is generally all labor, equipment, material and supervision as required to complete: exterior and interior masonry, including site work masonry, insulation, caulking and related work as shown on the Contract Documents. {¶ 12} “4. Bid Package 5B - Miscellaneous Metals is generally all work required to provide materials and complete installation of materials such as ladders, stairs, handrails, etc which includes offloading, shakeout, raising, bolting, cutting, welding, alignment, shop priming, galvanizing and touch-up. The Prime Contractor responsible for this work shall be termed the Miscellaneous Steel Installation Contractor (MSIC). {¶ 13} “5. Bid Package 9A - General Trades Package is generally all labor, equipment, material and supervision as required to complete: Rough and finish carpentry, insulation, EIFS, shingled and metal roof, all interior and exterior doors, frames, and hardware, rolling security gates, glass and glazing, studs and drywall, all flooring, finish carpentry, caulking, gypsum board walls, acoustical ceilings, paint, division 10 specialties, stage equipment, projection screens, athletic equipment, and gym bleachers.” (Plaintiff’s Exhibit 2.) {¶ 14} As is evident from the quantity of work that Stanley Miller was responsible to complete on the Lehman project, the construction of the Lehman Middle School was essentially a Stanley Miller project. The Lehman project was scheduled to be completed on or before July 2, 2004, but work continued until early 2005. There is no argument that the project was substantially completed by the start of the school year and that the building was open for classes in August 2004.

II. STATUTE OF LIMITATIONS {¶ 15} OSFC contends that Stanley Miller’s cause of action for breach of contract accrued at the time the breach occurred. OSFC argues that the latest date when a breach could have occurred was when Stanley Miller incurred the additional costs it seeks to recover. Steve Miller testified that a majority of additional costs reflected in the one-page, $1.1 million claim were incurred by Stanley Miller in 2003. As noted above, Stanley Miller filed this action in the court of common pleas on June 30, 2006, more than two years after such costs were incurred. {¶ 16} For the following reasons, OSFC’s argument is without merit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips Construction Co., Inc. v. The United States
394 F.2d 834 (Court of Claims, 1968)
Net Construction, Inc. v. C & C Rehab & Construction, Inc.
256 F. Supp. 2d 350 (E.D. Pennsylvania, 2003)
Galayda v. Lake Hospital Systems, Inc.
1994 Ohio 64 (Ohio Supreme Court, 1994)
Bemmes v. Public Employees Retirement System
658 N.E.2d 31 (Ohio Court of Appeals, 1995)
Fouty v. Ohio Department of Youth Services
855 N.E.2d 909 (Ohio Court of Appeals, 2006)
Marok v. the Ohio State University, 07ap-921 (6-26-2008)
2008 Ohio 3170 (Ohio Court of Appeals, 2008)
Conti Corp. v. Ohio Department of Administrative Services
629 N.E.2d 1073 (Ohio Court of Appeals, 1993)
Textron Financial Corp. v. Nationwide Mutual Insurance
684 N.E.2d 1261 (Ohio Court of Appeals, 1996)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Inglis v. American Motors Corp.
209 N.E.2d 583 (Ohio Supreme Court, 1965)
Mills v. Whitehouse Trucking Co.
320 N.E.2d 668 (Ohio Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
2010 Ohio 1488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanley-miller-constr-co-v-state-ohioctcl-2010.