Cleveland Constr. v. Ohio Pub. Emps. Retirement Sys., 07ap-574 (4-3-2008)

2008 Ohio 1630
CourtOhio Court of Appeals
DecidedApril 3, 2008
DocketNo. 07AP-574.
StatusPublished
Cited by10 cases

This text of 2008 Ohio 1630 (Cleveland Constr. v. Ohio Pub. Emps. Retirement Sys., 07ap-574 (4-3-2008)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cleveland Constr. v. Ohio Pub. Emps. Retirement Sys., 07ap-574 (4-3-2008), 2008 Ohio 1630 (Ohio Ct. App. 2008).

Opinion

OPINION
{¶ 1} In this construction case, the appellant, Ohio Public Employees Retirement System ("PERS"), is the project owner who entered into a $6.3 million interior trades contract with appellee, Cleveland Construction, Inc. ("CCI"), to build portions of a $90 million office tower on East Town Street in downtown Columbus, Ohio. At trial, a jury found that PERS materially breached its contract with CCI by failing to properly schedule and coordinate the project's various tasks. *Page 2

{¶ 2} PERS does not challenge the jury's finding that PERS (and its construction manager, the Gilbane Building Company) failed to properly schedule and coordinate the project. The jury heard evidence concerning the lack of up-to-date project schedules, coordination issues, activity delay, out of sequence work, and the failure of the project manager to address issues impacting the schedule. Despite these problems, the project was substantially complete by the time set forth in a revised schedule.

{¶ 3} The jury found that PERS materially breached the contract, and PERS does not challenge that fact. Implicit in the jury's finding of a material breach was that the failure to properly schedule the project led to labor inefficiencies that hindered the progress of the work and ultimately caused CCI to incur higher costs.

{¶ 4} The jury awarded CCI $640,298 in damages for the loss of efficiency caused by PERS' breach. Prior to the case going to the jury, PERS unsuccessfully moved the court for a directed verdict, insisting that under the contract's terms, CCI had waived its right to collect damages. In ruling on the motion, the trial court determined that the contract did not unambiguously bar CCI's claim, and that the waiver provision at issue was unenforceable because of R.C. 4113.62(C)(1), which prohibits project owners from contracting out of liability for their own delay.

{¶ 5} On appeal, PERS raises the following assignments of error:

[I.] The Contract language in General Conditions § 6.1.1.5 and § 6.3.1 is enforceable when it provides that the sole remedy for interference, disruption or hindrance is an extension of time and there will be no additional compensation for acceleration or other loss of efficiency damages.

[II.] The Trial Court erred in failing to direct a verdict when the evidence was undisputed that the contractor failed to seek a *Page 3 time extension in writing as required by General Condition § 6.4.1, and therefore waived any claim for damages.

[III.] The Jury nullified a proper instruction on the Total Cost Method of computing damages (which required no portion of the loss be caused by the Contractor) when the Jury's verdict implicitly acknowledged the Contractor's shortcomings, which were well supported by the record.

{¶ 6} In its first assignment of error, PERS contends that the trial court misconstrued both the language of the contract and R.C.4113.62(C)(1), which invalidates no-damages-for-delay provisions. In connection with this assignment of error, PERS has urged us to review the entire case de novo, on the basis that the only issue for consideration is the interpretation of the contract, and the interpretation of R.C. 4113.62(C)(1).

{¶ 7} Issues of contract construction and interpretation are questions of law subject to de novo review on appeal. Sherman R. Smoot Co. v. OhioDept. of Adm. Serv., 136 Ohio App.3d 166, 172. To the extent necessary to understand the nature and effect of the statute's relationship to the contract at issue, we will review those items without deference to the trial court's determination. We will not, however, review the entire case de novo, as the case presents questions of law, questions of fact, and mixed questions of fact and law. It is the function of the jury to weigh the evidence and find the facts. The jury's findings will not be overturned on appeal if there is competent, credible evidence to support them. Seasons Coal Co. v. Cleveland (1984), 10 Ohio St.3d 77, 80;C.E. Morris Co. v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, 280.

{¶ 8} Section 6.1.1.5 of the contract provides, in pertinent part, as follows:

[CCI] agrees that the possibility that [it] may be subject to interference, disruption, hindrance or delay in the progress of *Page 4 the Work from any and all causes is within the contemplation of the parties and that the sole remedy for such interference, disruption, hindrance or delay shall be an extension of time

{¶ 9} In addition, Section 6.3.1 of the contract provides as follows:

To the fullest extent permitted by law, any extension of time granted pursuant to paragraph GC 6.2 shall be the sole remedy which may be provided by [PERS], and [CCI] shall not be entitled to additional compensation or mitigation of Liquidated Damages for any delay, interference, hindrance or disruption, including, without limitation, costs of acceleration, consequential damages, loss of efficiency, loss of productivity, lost opportunity costs, impact damages, lost profits or other similar remuneration. [CCI] agrees that the possibility that [CCI] may accelerate its performance to meet the Construction Schedule is within the contemplation of the parties and that any such acceleration is solely within the discretion of [CCI]. This provision is intended to be, and shall be construed as consistent with, and not in conflict with, Section 4113.62, ORC, to the fullest extent permitted.

{¶ 10} This "boilerplate" contractual language, known as a "no-damages-for-delay" clause, has been standard in state construction contracts and, until fairly recently, has been valid and enforceable. In 1998, however, the General Assembly declared no-damages-for-delay clauses void and unenforceable as against public policy "when the cause of the delay is a proximate result of the owner's act or failure to act." R.C. 4113.62(C)(1) (effective September 30, 1998), which invalidated these types of clauses in construction contracts, provides, in pertinent part, as follows:

Any provision of a construction contract * * * that waives or precludes liability for delay * * * when the cause of the delay is a proximate result of the owner's act or failure to act, or that waives any other remedy for a construction contract when the cause of the delay is a proximate result of the owner's act or failure to act, is void and unenforceable as against public policy.

*Page 5

Thus, if CCI's claim for damages is not due to delay caused by PERS, the statute has no application, and the contract provisions quoted above would bar CCI's claim for damages.

{¶ 11} PERS of course, contends that the statute does not apply to the claim in this case. PERS contends that CCI's claim is barred because, in reality, CCI has asserted a claim for acceleration costs, not delay damages.

{¶ 12} PERS argues that in enacting R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Moses
2025 Ohio 5515 (Ohio Court of Appeals, 2025)
State v. Reyes-Figueroa
2020 Ohio 4460 (Ohio Court of Appeals, 2020)
IPS Elec, Servs., L.L.C. v. Univ. of Toledo
2016 Ohio 361 (Ohio Court of Appeals, 2016)
Aggressive Mechanical, Inc. v. Ohio School Facilities Comm.
2012 Ohio 6332 (Ohio Court of Claims, 2012)
J-Way Leasing, Ltd. v. American Bridge Company
500 F. App'x 365 (Sixth Circuit, 2012)
Stanley Miller Constr. Co. v. State
2010 Ohio 1488 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. Ohio School Facilities Comm.
2010 Ohio 1528 (Ohio Court of Claims, 2010)
Maghie Savage, Inc. v. P.J. Dick Inc., 08ap-487 (5-5-2009)
2009 Ohio 2164 (Ohio Court of Appeals, 2009)
Davis v. Georgopoulos, 08 Ma 85 (12-2-2008)
2008 Ohio 6368 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2008 Ohio 1630, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleveland-constr-v-ohio-pub-emps-retirement-sys-07ap-574-4-3-2008-ohioctapp-2008.