Maghie Savage, Inc. v. P.J. Dick Inc., 08ap-487 (5-5-2009)

2009 Ohio 2164
CourtOhio Court of Appeals
DecidedMay 5, 2009
DocketNo. 08AP-487.
StatusPublished
Cited by27 cases

This text of 2009 Ohio 2164 (Maghie Savage, Inc. v. P.J. Dick Inc., 08ap-487 (5-5-2009)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maghie Savage, Inc. v. P.J. Dick Inc., 08ap-487 (5-5-2009), 2009 Ohio 2164 (Ohio Ct. App. 2009).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, Maghie Savage, Inc. ("MS"), appeals from the Franklin County Court of Common Pleas' judgment on a directed verdict in favor of defendant-appellee, P.J. Dick Inc. ("PJD"), and entry of summary judgment in favor of defendant-appellee, Blakley Corporation ("Blakley"). For the following reasons, we affirm. *Page 2

{¶ 2} This action arises out of the construction of the Austin Knowlton School of Architecture (the "project") at The Ohio State University ("OSU"). Construction began in June 2002 and was originally scheduled for completion in April 2004. The completion date for the project was informally extended to June 2004, but the project was not completed until August 2004.

{¶ 3} The project involved a number of separate prime contracts. PJD was the prime contractor for the general trades work, the lead contractor, and responsible for scheduling all of the contractors' work. PJD entered into subcontracts with MS and Blakley. PJD's subcontract with Blakley (the "Blakley subcontract") encompassed the installation of windows, skylights, curtainwall, and other glass exteriors, and its subcontract with MS (the "subcontract") encompassed the framing, hanging and finishing of drywall, and the installation of ceiling tiles.

{¶ 4} Article 9 of the subcontract specified the procedures by which MS could assert a claim for additional compensation. Paragraph 9.1.1 provides as follows:

If Subcontractor's Work is delayed, accelerated, compressed, re-sequenced or if Subcontractor is adversely impacted in any way in the prosecution of the Work due to the schedule, or the acts of Owner and/or its agents, other independent contractors of Owner, Contractor, or Contractor's other subcontractors, and Subcontractor suffers delay, acceleration, compression, loss of efficiency, extended overhead, or any other type of damages, losses or impacts therefrom, or if Subcontractor has any other type of claim for additional compensation to be asserted against Contractor or any of such other entities, Subcontractor agrees to provide written notice within two (2) business days of the event or occurrence giving rise to the impact to Subcontractor's Work, or such claims shall be barred. Time shall be of the essence.

*Page 3

Plaintiff's Exhibit 1. Paragraph 9.1.2 states that "failure to provide timely written notice to Contractor of any * * * adverse impact to Subcontractor's work" will preclude recovery of damages incurred "as a result of any adverse impact to Subcontractor's Work." Paragraph 9.3.1 requires the subcontractor's written notice to include "a brief statement of the impact to Subcontractor's Work, the entity Subcontractor believes to be responsible for the impact to Subcontractor's Work, and any damages known to Subcontractor arising from such additional work or impact."

{¶ 5} Blakley's installation of windows and skylights was originally scheduled to commence in September 2003, but was rescheduled to November 2003. By January 2004, however, Blakley had not begun installation because the windows had not shipped from the supplier. Upon learning, in late 2003, of Blakley's delay, PJD temporarily enclosed the building with visqueen, a plastic material, and provided temporary heaters from December 2003 through March 2004.

{¶ 6} MS received a January 2004 start date for its interior work on the project, but, because of environmental conditions, including moisture, standing water, and temperatures below 50 degrees, caused by weather and the absence of windows and skylights, MS was hesitant to commence its drywall work. MS maintains that the conditions in the building were inadequate for drywall installation and that the plastic enclosure and temporary heaters employed by PJD were insufficient to remedy the inadequate conditions. MS notified PJD of its concerns in a series of letters dated between January 5, 2004 and March 23, 2004. A common thread in MS's letters was that it could not warrant the installation performed in inadequate environmental conditions. On January 6, 2004, PJD responded to MS's first letter, stating that "[t]he *Page 4 completion date of this project dictates that you start installing drywall." Plaintiff's Exhibit 13. As ordered by PJD, MS began work under the subcontract in January 2004 and had completed 85 percent of its drywall work by the end of March 2004. MS's expert witness, Kurt Keidel, testified that MS's work, which included most of the drywall hanging, during the cold and wet weather was performed efficiently.

{¶ 7} In a letter dated January 14, 2004, Scott Conlon ("Conlon"), the OSU Project Manager, responded to notice from PJD that it was unable to meet the approved construction schedule with respect to Blakley's work. Conlon informed PJD that, "should the other Prime Contractors not be able to complete their work as a result of your inability to meet the schedule, [PJD] will be held responsible for all costs associated with the delays." Plaintiff's Exhibit 53.

{¶ 8} From January 5, 2004 through October 13, 2004, as a result of Blakley's delay, PJD issued eight change orders to Blakley, deducting various amounts from the Blakley subcontract for weather protection, drywall repair, water damage repairs, acceleration costs, and extended field office overhead. PJD also issued change orders to pay MS for extra work to replace and repair water-damaged portions of its work.

{¶ 9} In a letter dated October 21, 2004, months after MS completed its work on the project, MS notified PJD that, "[a]s a result of the job conditions [including low temperatures, high moisture, standing water, and ice] our labor escalated for both hanging and finishing drywall." Plaintiff's Exhibit 48. MS requested a change order authorizing additional costs of $248,459. Explaining the basis of MS's claim, Keidel testified that MS suffered labor inefficiencies and lost productivity from April to *Page 5 June 2004 as a result of acceleration of the project schedule, suboptimal crew size, and overcrowding. James Savage, an owner of MS, testified that MS waited until October 2004 to file a claim for additional costs because those costs could not previously be calculated. Savage explained that, in January 2004, when MS notified PJD about the inadequate environmental conditions, MS did not know the value of the impact those conditions would have on its work. Savage stated that MS did not know whether "the other trades [were] going to be able to get out of our way, there was no possible way to put a price on the future because of the job conditions." (Vol. V Tr. 709.) PJD did not issue a written response to MS's October 2004 claim letter.

{¶ 10} On March 4, 2005, MS sent a follow-up letter to PJD, reiterating its "claim for lost productivity due to acceleration required to meet schedules delayed by environmental conditions." Plaintiff's Exhibit 54. That letter stated as follows:

As you are aware, the lack of a completed shell (i.e. windows, roofing) caused the interior environment (lack of adequate temporary heat and presence of [too] much water) to delay the start of the hanging and finishing by 5 weeks. These conditions also contributed to poor production during the interior framing sequences. The additional hours referenced in my earlier letter were worked in a 3-month period and represent a doubling of our planned crew size for both the hanging and finishing work on this project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tornstrom Indus. Dev. Corp. v. 123 Lyndhurst, L.L.C.
2025 Ohio 2302 (Ohio Court of Appeals, 2025)
Sparks v. Fitzhugh
N.D. Ohio, 2025
Am. Business Invests., L.L.C. v. Shaeena & Allos, L.L.C.
2023 Ohio 739 (Ohio Court of Appeals, 2023)
Lakhi v. Meritra Health Care, L.L.C.
2022 Ohio 3062 (Ohio Court of Appeals, 2022)
Hlad v. Step Lively Foot & Ankle Ctrs., Inc.
2022 Ohio 3060 (Ohio Court of Appeals, 2022)
In re Name Change of E.S.
2022 Ohio 2107 (Ohio Court of Appeals, 2022)
Prime Invests., L.L.C. v. Altimate Care, L.L.C.
2022 Ohio 1181 (Ohio Court of Appeals, 2022)
Zara Constr., Inc. v. Belcastro
2022 Ohio 788 (Ohio Court of Appeals, 2022)
Becker v. Cardinal Health, Inc.
2021 Ohio 3804 (Ohio Court of Appeals, 2021)
Sullinger v. Reed
2021 Ohio 2872 (Ohio Court of Appeals, 2021)
Bakhshi v. Baarlaer
2021 Ohio 13 (Ohio Court of Appeals, 2021)
Santagate v. Pennsylvania Higher Edn. Assistance Agency
2020 Ohio 3153 (Ohio Court of Appeals, 2020)
Simek v. Orthopedic & Neurological Consultants, Inc.
2019 Ohio 3901 (Ohio Court of Appeals, 2019)
O'Brien v. Dept. of Transp.
2019 Ohio 724 (Ohio Court of Appeals, 2019)
Pollard v. Elber
2018 Ohio 4538 (Ohio Court of Appeals, 2018)
McGarry & Sons, Inc. v. Constr. Resources One, L.L.C.
2018 Ohio 528 (Ohio Court of Appeals, 2018)
Long v. Mount Carmel Health Sys.
2017 Ohio 5522 (Ohio Court of Appeals, 2017)
LHPT Columbus, L.L.C. v. Capitol City Cardiology, Inc.
2014 Ohio 5247 (Ohio Court of Appeals, 2014)
Pertoria, Inc. v. Bowling Green State Univ.
2014 Ohio 3793 (Ohio Court of Appeals, 2014)
Fleming v. Kent State Univ.
2014 Ohio 3471 (Ohio Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2009 Ohio 2164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maghie-savage-inc-v-pj-dick-inc-08ap-487-5-5-2009-ohioctapp-2009.