McGarry & Sons, Inc. v. Constr. Resources One, L.L.C.

2018 Ohio 528, 107 N.E.3d 91
CourtOhio Court of Appeals
DecidedFebruary 9, 2018
DocketS-17-005
StatusPublished
Cited by20 cases

This text of 2018 Ohio 528 (McGarry & Sons, Inc. v. Constr. Resources One, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGarry & Sons, Inc. v. Constr. Resources One, L.L.C., 2018 Ohio 528, 107 N.E.3d 91 (Ohio Ct. App. 2018).

Opinion

OSOWIK, J.

Introduction

{¶ 1} This case concerns a contractual dispute between a painting subcontractor, Mike McGarry & Sons, Inc., a general contractor, Construction Resources One, Inc., and the owner of the facility where the work was performed, Cuyahoga Heights Commerce One, LLC.

{¶ 2} In 2013, Construction Resources One, Inc. ("CR-One") engaged Mike McGarry & Sons, Inc. ("MMS") to clean, prime and paint part of an unoccupied manufacturing facility. The property owner, Cuyahoga Heights Commerce One, LLC. ("Cuyahoga Heights"), was negotiating with a tenant, and CR-One's job was to prepare part of the building for occupancy.

{¶ 3} The painting aspect of the project was beset by cost-overruns and delays. MMS alleges that Cr-One breached an agreement to pay it for those extra costs. When CR-One did not pay, MMS filed a mechanic's lien against the property owner, asserting more than twice the value of the original contract.

{¶ 4} On October 24, 2014, MMS filed a four count complaint in the Sandusky County Court of Common Pleas against CR-One and Cuyahoga Heights (referred jointly as "appellees") for breach of contract, violation of Ohio's Prompt Payment Act, unjust enrichment, and foreclosure of a mechanic's lien. Cuyahoga Heights counterclaimed, asserting fraud and tortious interference with business relations based upon the filing of the lien.

{¶ 5} Acting on the parties' cross motions for summary judgment, the trial court dismissed all of MMS' claims, except the breach of contract claim. After a bench trial, the trial court found that MMS failed to show that appellees breached an agreement to compensate it for any amount over the original contract. The court found in favor of Cuyahoga Heights as to both of its counterclaims. The court also sanctioned MMS for maintaining the mechanic's lien and for unnecessary motion practice. MMS appealed.

{¶ 6} The facts giving rise to the claims asserted in this case, unless noted, are not disputed and are set forth below.

Facts and Procedural History

{¶ 7} Cuyahoga Heights owns commercial properties throughout northern Ohio, including property located at 4600 Oak Harbor Road, in Fremont, Ohio. In 2013, it hired CR-One to act as general contractor and to prepare the vacant facility for occupancy. At the time, Cuyahoga Heights was negotiating with "Unican" to lease the facility. Among other items, Unican manufactures paint cans. It was to occupy part of the property and operate a single manufacturing line, with the hope that it would add lines, and with them, the need for more space in the future. Accordingly, Cuyahoga Heights hired CR-One to refurbish the facility in four phases. Phases two, three and four would be added when and if the need arose.

{¶ 8} CR-One's President, Matt Ambrose ("Ambrose"), invited MMS to submit a quote to clean, prime, and paint the walls and ceiling of phase I, which consisted of 105,717 square feet.

{¶ 9} Cuyahoga Heights and CR-One share common owners. Real estate developers Christopher Semarjian and Stuart Lichter are the majority owners of Cuyahoga Heights and the co-owners of CR-One. Semarjian testified that CR-One is Cuyahoga Heights' exclusive general contractor, although CR-One occasionally performs contracting service for other clients.

{¶ 10} MMS is in the commercial painting business. Sean McGarry ("Sean") is MMS' estimator and project manager. Sean has been in the painting industry for 26 years and has estimated thousands of projects. In preparation for quoting this job, Sean was given complete access to the property. After visiting the property, Sean provided CR-One with a quote of $118,340, which amounted to $1.12 per square foot. Sean estimated that the project would require six weeks, three to prime and clean and three weeks to paint. The evidence shows that CR-One had no input on the methods or products used by MMS.

{¶ 11} On February 13, 2013, prior to executing a written contract, MMS set up at the property. As it did so, MMS asked CR-One for access to water so that it could power wash the surfaces, to turn off the electricity, and to increase the temperature to at least 50 degrees so that paint could adhere.

{¶ 12} CR-One delivered heaters to the property and hung tarps to enclose phase I so as to prevent heat from escaping. The temperature improved when the heaters were delivered. MMS did not raise any concerns about temperature after the delivery of the heaters. At MMS' request, CR-One also delivered water trucks to allow MMS to power wash. To maintain safety while power washing, Ambrose proposed that CR-One would shut off the electricity in segments (so MMS would have access to lighting and power), and he asked MMS to cover the electrical bus ducts to avoid electrocution. MMS did not object to this proposal or state that it would result in extra cost.

{¶ 13} Despite asking for access for water, MMS decided to "blow down" the surfaces of the property, rather than to power wash. This change was not done at CR-One's request. On February 28, 2013, after MMS had decided to change its cleaning method, Ambrose asked Sean for a breakdown of the costs for the project, including the "blow down." On March 6, 2013, Sean responded that the cost would remain $118,340.

{¶ 14} MMS' paint supplier on the project was Glidden. On February 20, 2013, Glidden agent, Brian Conroy, recommended that MMS should prime " all surface areas (100%)" with a primer called "Devguard 436." At trial, Sean testified that he viewed the recommendation to prime the entire project as "overkill."

{¶ 15} MMS began working on the property on or about February 21, 2013, still without a contract.

{¶ 16} On March 7, 2013, MMS, through its president, Brendan McGarry, signed a "SUBCONTRACT AGREEMENT BETWEEN GENERAL CONTRACTOR AND SUBCONTRACTOR." Before sending it to Ambrose for CR-One's signature, Brendan unilaterally made some handwritten changes to a few provisions, but he left undisturbed the originally quoted price, notwithstanding that, by then, (1) MMS had decided to change its cleaning methods and (2) it was aware of its paint supplier's recommendation that MMS prime the whole structure, not just to "spot prime." The quoted price included "spot priming," which means only priming certain areas, not the entire structure. Sean reviewed the contract and advised Brendan that it was acceptable.

{¶ 17} Paragraph 2 of the contract provides, "[f]or performing the scope of work, The Subcontractor will be paid in monthly payments, based on completion percentages, the following not-to-exceed amount: $118,340.00." The term "scope of work" is used throughout the contract, but is not defined. CR-One's president, Ambrose, told Sean that he wanted phase I properly cleaned, primed, and painted to an industry standard. Sean testified that MMS's promise to CR-One was more than just that MMS "would clean and paint," but instead that phase I would be cleaned, primed, and painted "appropriately" so that "[t]he paint would stay on the wall" and the "paint would stay on the ceiling," or else MMS would fix the problems at MMS's cost.

{¶ 18} On or about March 15, 2013, CR-One asked MMS to vacate the property and to stop working, due to Cuyahoga Heights' uncertainty over lease negotiations with Unican.

{¶ 19} On March 25, 2013, during the shutdown, Sean sent Ambrose an email (the "March 2013 Email").

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Apple-Chamberlain v. Apple
2025 Ohio 5388 (Ohio Court of Appeals, 2025)
Fremont Cutting Dies, Inc. v. Trigo Quality Solutions US, Inc.
2025 Ohio 5167 (Ohio Court of Appeals, 2025)
Haskins v. F. Leo Groff, Inc.
2025 Ohio 1850 (Ohio Court of Appeals, 2025)
Effinger v. Vermilion Power Boats, Inc.
2025 Ohio 1851 (Ohio Court of Appeals, 2025)
Dexter v. Fairfield
2024 Ohio 6080 (Ohio Court of Appeals, 2024)
Iron Horse Bar & Grill, L.L.C. v. GGJ Triune, PLL
2024 Ohio 284 (Ohio Court of Appeals, 2024)
Cyrus v. Ohio Rehab. Servs. Comm.
2023 Ohio 1506 (Ohio Court of Appeals, 2023)
State ex rel. Betton v. Burgess & Niple, Inc.
2023 Ohio 740 (Ohio Court of Appeals, 2023)
Bernholtz v. Bernholtz
2022 Ohio 4764 (Ohio Court of Appeals, 2022)
Pierre Invests., Inc. v. CLE Capital Group, Inc.
2022 Ohio 4311 (Ohio Court of Appeals, 2022)
Bonner v. Delp
2021 Ohio 3772 (Ohio Court of Appeals, 2021)
Bliss v. Johns Manville Corp.
2021 Ohio 1673 (Ohio Court of Appeals, 2021)
William Powell Co. v. OneBeacon Ins. Co.
2020 Ohio 3270 (Ohio Court of Appeals, 2020)
Accurate Elec. Constr., Inc. v. Ohio State Univ.
2019 Ohio 4992 (Ohio Court of Appeals, 2019)
DeFoe v. Schoen Builders, L.L.C.
2019 Ohio 2255 (Ohio Court of Appeals, 2019)
Tassone v. Tassone
2019 Ohio 683 (Ohio Court of Appeals, 2019)
Pollard v. Elber
2018 Ohio 4538 (Ohio Court of Appeals, 2018)
McCormack v. Jefferson Area Local School Dist.
2018 Ohio 3744 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 528, 107 N.E.3d 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgarry-sons-inc-v-constr-resources-one-llc-ohioctapp-2018.