Cuspide Properties, Ltd. v. Earl Mechanical Servs.

2015 Ohio 5019
CourtOhio Court of Appeals
DecidedDecember 4, 2015
DocketL-14-1253
StatusPublished
Cited by16 cases

This text of 2015 Ohio 5019 (Cuspide Properties, Ltd. v. Earl Mechanical Servs.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cuspide Properties, Ltd. v. Earl Mechanical Servs., 2015 Ohio 5019 (Ohio Ct. App. 2015).

Opinion

[Cite as Cuspide Properties, Ltd. v. Earl Mechanical Servs., 2015-Ohio-5019.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT LUCAS COUNTY

Cuspide Properties, Ltd. Court of Appeals No. L-14-1253

Appellee/Cross-Appellant Trial Court No. CI0200805503

v.

Earl Mechanical Services, Inc.

Appellant/Cross-Appellee

Huntington Bancshares Financial Corp., et al. DECISION AND JUDGMENT

Appellees Decided: December 4, 2015

*****

Fritz A. Byers, for appellee/cross-appellant Cuspide Properties, Ltd. and appellee Community ISP, Inc.

Erik G. Chappell and Julie A. Douglas, for appellant/cross-appellee.

***** YARBROUGH, P.J.

I. Introduction

{¶ 1} This is an appeal from the Lucas County Court of Common Pleas.

Appellant, Earl Mechanical Services, Inc., appeals the trial court’s grant of summary

judgment to appellee/cross-appellant, Cuspide Properties, Ltd. (“Cuspide”), on Cuspide’s

action to quiet title and liability in its slander of title action. Appellant appeals the trial

court’s decision to grant summary judgment to Cuspide and appellee, Community ISP,

Inc. (“CISP”), on all of appellant’s counterclaims. Cuspide cross-appeals the trial court’s

grant of summary judgment to appellant on the element of damages for its slander of title

action.

A. Facts

{¶ 2} This dispute began after appellant contracted with CISP to install air

conditioning and condenser units on the property it leases from Cuspide. Appellant is

owned by Jeffrey Earl and is a company providing construction services for commercial

properties. Cuspide is owned by Jeffrey Klingshirn, who also serves as CEO of CISP.

Dustin Wade serves as president of CISP. Appellee Huntington Bancshares Financial

Corporation holds a mortgage on Cuspide’s property where CISP is located.

{¶ 3} In early 2006, CISP decided to build and equip a data center on Cuspide’s

property. Before the construction process, CISP purchased six air conditioning units and

six condensers from an unrelated third party. CISP then began receiving quotes for the

2. mechanical work needed to connect the air conditioning units and condensers and run

pipes between the units and into the building. CISP spoke to several contractors and

received estimates. One such estimate was more than $100,000. After speaking with

Wade, appellant gave an estimate of $47,600. The parties eventually entered into a

contract for $51,100. When asked about the large price difference between the bids, Earl

stated it was due to the other contractor’s reliance on workers who belonged to labor

unions.

{¶ 4} The job was slated to be completed by early November 2006, so CISP could

have an open house to promote their new data center. After the contract was signed, but

before the work was completed, Earl informed Wade additional costs above the contract

price were being accrued. The two then spoke to Klingshirn over the telephone about the

extra costs. Some of these costs were associated with two changes to the project that

were made by CISP. One change was installing the condenser units on the roof of the

building rather than on concrete pads located in the back of the building. Wade testified

in his deposition, he was told by appellant this change in location would not change the

cost in the project.

{¶ 5} The more significant change was the decision to change the system from a

four pump system to a dual pump system produced by a company called Liebert. When

CISP originally sought a quote from appellant, the estimate was based on each air

conditioner and condenser having its own pump. However, after speaking with another

potential contractor who suggested the dual pump system, CISP decided a dual pump

3. system by Liebert should be installed. Wade then informed appellant of the requested

changes and a new contract was drawn up.

{¶ 6} The contract between the parties makes a notation in price for four pumps,

which is what was originally agreed to between the parties. A few lines later, a line item

for $3,500 is listed for “Add for Liebert 7 1/2 HP pump package.” Wade testified he

believed that line item was referring to the dual pump system CISP wanted installed,

including the labor and other costs associated with installing the system. This is

supported by the change in estimates given to CISP by appellant. Appellant originally

gave CISP an estimate for $47,600, but the contract between the parties was for $51,100.

{¶ 7} Earl testified in his deposition that the line item was merely the price

difference between the pumps and did not account for the extra work needed to actually

install the different pump system. Several engineering drawings had to be made and the

units had to be manifolded together for the system to operate correctly. He testified he

was unaware until much later in the project what the extra costs of installing the new

system would be.

{¶ 8} The contract included a forum selection clause which required suit to be

brought in Fulton County. The agreement required any changes in the scope of work to

be in written change orders.

{¶ 9} Toward the end of the project, Earl informed CISP and Wade extra costs

were being incurred above the contract price. Wade and Klingshirn told Earl to continue

his work, as the project needed to be completed on time and the company did not have

4. enough time to hire a new contractor. Klingshirn told Earl he should continue work and

the parties would negotiate the costs later. At the time of the conversation, appellant was

unaware of the exact amount of the additional costs and told Wade he would have to

make some calculations before he knew the exact amount.

{¶ 10} During the construction project, Wade was generally overseeing the

project. Klingshirn delegated the responsibility to Wade to ensure that the project was

completed and on time. Wade continually spoke with Klingshirn about the project. Both

men had the right to sign checks to pay invoices, and Wade generally got approval from

Klingshirn before paying any invoices. Earl directly dealt with Wade during the course

of the project except for the one incident where he spoke with Klingshirn over the phone

about the extra costs of the project.

{¶ 11} Appellant completed the project in a time and manner that met the approval

of CISP. Following the completion of the project, CISP paid appellant the balance of the

contract which amounted to $25,500 based on an invoice from appellant. The bottom of

this invoice stated extra work was still pending. CISP paid $15,520.97 in additional costs

above the contracted price. Appellant then demanded an additional $47,491.97 which it

claims is for the installation of the Liebert dual pump systems. In total, appellant asked

CISP to pay $114,112.94 for a job which was originally contracted for $51,100. CISP

refused to pay these extra costs. Consequently, appellant filed a mechanic’s lien against

CISP’s lessee interest and Cuspide’s lessor interest on January 24, 2007.

5. B. Procedural History

{¶ 12} On February 21, 2008, CISP and Cuspide filed a complaint in Lucas

County against appellant seeking to have the lien removed and other relief. Due to the

forum selection clause in the contract, the case was transferred to Fulton County. CISP

and Cuspide failed to pay the necessary filing fees and the case was dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lashaway v. Lashaway
Ohio Court of Appeals, 2026
COD Properties Ohio, L.L.C. v. Black Tie Title, L.L.C.
2025 Ohio 2519 (Ohio Court of Appeals, 2025)
Wright v. Mallet
2025 Ohio 1729 (Ohio Court of Appeals, 2025)
Speedy Maintenance Serv., L.L.C. v. Windsor Tower, L.L.C.
2024 Ohio 5841 (Ohio Court of Appeals, 2024)
InvesTek Mgt. Servs., Inc. v. Tate
2024 Ohio 5850 (Ohio Court of Appeals, 2024)
N. Royalton Court Condo Owners' Assn. v. Stadul
2024 Ohio 1280 (Ohio Court of Appeals, 2024)
WWSD, L.L.C. v. Woods
2022 Ohio 952 (Ohio Court of Appeals, 2022)
Shannack v. Yark Automotive Group, Inc.
2021 Ohio 2372 (Ohio Court of Appeals, 2021)
Valentine v. Cedar Fair, L.P.
2021 Ohio 2144 (Ohio Court of Appeals, 2021)
Lakeview Elec., Inc. v. Van Auken
2020 Ohio 4941 (Ohio Court of Appeals, 2020)
Krohn v. Ostafi
2020 Ohio 1536 (Ohio Court of Appeals, 2020)
Silberhorn v. Flemco, L.L.C.
2020 Ohio 913 (Ohio Court of Appeals, 2020)
McGarry & Sons, Inc. v. Constr. Resources One, L.L.C.
2018 Ohio 528 (Ohio Court of Appeals, 2018)
Cuspide Properties, Ltd. v. Earl Mechanical Servs., Inc.
2017 Ohio 5680 (Ohio Court of Appeals, 2017)
Paul v. Hannon
2017 Ohio 1261 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2015 Ohio 5019, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cuspide-properties-ltd-v-earl-mechanical-servs-ohioctapp-2015.