Columbus Garage Floor Coating, Inc. v. Iowa Concrete, LLC

CourtDistrict Court, S.D. Ohio
DecidedFebruary 25, 2022
Docket2:21-cv-03851
StatusUnknown

This text of Columbus Garage Floor Coating, Inc. v. Iowa Concrete, LLC (Columbus Garage Floor Coating, Inc. v. Iowa Concrete, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbus Garage Floor Coating, Inc. v. Iowa Concrete, LLC, (S.D. Ohio 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF OHIO EASTERN DIVISION

Columbus Garage Floor Coating LLC, Case No: 2:21-cv-3851 Plaintiff, Judge Graham v. Magistrate Judge Jolson Iowa Concrete, LLC, et al., Defendants. Opinion and Order Plaintiff Columbus Garage Floor Coating LLC (“CGFC”) seeks to recover payment for work it performed as a subcontractor on two construction projects. CGFC asserts breach of contract claims against the general contractor, defendant Iowa Concrete, LLC, and it asserts claims for unjust enrichment and third-party beneficiary against the project owner, defendant Heartland Express, Inc. This matter is before the Court on the motion of Heartland Express to dismiss the claims against it. Heartland argues that the unjust enrichment claim fails because CGFC has a means available to recover from Iowa Concrete, with whom CGFC was in privity of contract. Heartland contends that the third-party beneficiary claim fails because subcontractors generally are not third- party beneficiaries to prime contracts in the construction law context. The Court grants in part and denies in part the motion to dismiss, as set forth below. I. Background CGFC is an Ohio limited liability company. Iowa Concrete is an Iowa limited liability company. In October 2019, CGFC and Iowa Concrete entered into a contract (the “Ohio contract”) for CGFC to perform epoxy floor-coating work at facility located in Columbus. The facility is owned by Heartland Express, an Iowa corporation in the over-the-road trucking industry. According to the complaint, CGFC performed the work and received partial payment from Iowa Concrete. The parties then agreed, at Iowa Concrete’s request, to roll the rest of the payment due on the Ohio contract into a new contract (the “Tennessee contract”) for a similar project in Mt. Juliet, Tennessee. Heartland also owned the facility in Tennessee. CGFC and Iowa Concrete entered into the Tennessee contract on January 21, 2020. Iowa Concrete issued work orders to CGFC, which would submit invoices once it completed a work order. CGFC alleges that under the contract, Iowa Concrete had an obligation to make at least partial payment upon receipt of each invoice. CGFC contends that beginning with the first invoice it submitted on February 3, 2020, Iowa Concrete failed to make payment. CGFC nonetheless continued to perform additional work orders and completed performance of the Tennessee contract on August 11, 2020. CGFC submitted a total of seven invoices. In July 2020 Iowa Concrete raised concerns about the quality of workmanship relating to one of the work orders. According to the complaint, CGFC cured the alleged defects and executed a “punch list” reflecting its resolution each defect. On August 11 – the day CGFC completed performance – Iowa Concrete allegedly raised “spurious, de minimis” concerns about the quality of CGFC’s work. Sec. Am. Compl. at ¶ 24. CGFC offered to satisfy Iowa Concrete’s concerns by starting a new punch list. But Iowa Concrete responded that it was terminating the Tennessee contract and would not be issuing payment to CGFC because of alleged defects in workmanship. CGFC alleges that Iowa Concrete has not responded to its demands for payment under the Ohio and Tennessee contracts. This action was originally filed in state court in Ohio. The operative pleading is the Second Amended Complaint filed in state court. In addition to naming Iowa Concrete and Heartland Express as defendants, the complaint named Sherwin-Williams Company, an Ohio limited liability company. The complaint alleged that Sherwin-Williams had a materialman’s lien relating to equipment and supplies which CGFC obtained on credit from Sherwin-Williams for the Tennessee contract. The complaint sought a declaratory judgment “of the extent of [CGFC’s] obligation, if any, to Defendant Sherwin-Williams.” Sec. Am. Compl. at ¶ 71. Sherwin-Williams was voluntarily dismissed from the lawsuit in June 2021. On June 29, 2021, Iowa Concrete and Heartland removed the action to this Court on the grounds of diversity jurisdiction. See 28 U.S.C. § 1446(b)(3) (permitting removal within 30 days of an amended pleading, order or other paper from which it first can be ascertained that the case has become removeable). The complaint asserts claims against Iowa Concrete for breach of contract, fraud and conversion. The complaint asserts claims against Heartland for unjust enrichment and third-party beneficiary. In support of the unjust enrichment claim, CGFC alleges that it conferred a benefit on Heartland by performing improvements at its facilities in Ohio and Tennessee. In support of the third-party beneficiary claim, CGFC alleges that the prime contracts between Heartland and Iowa Concrete identified CGFC as a subcontractor and payee and thus made CGFC an intended beneficiary of the prime contract.1 This matter is now before the Court on Heartland’s motion to dismiss. II. Standard of Review Federal Rule of Civil Procedure 8(a) requires that a pleading contain a “short and plain statement of the claim showing that the pleader is entitled to relief.” Fed. R. Civ. P. 8(a)(2). When considering a motion under Rule 12(b)(6) to dismiss a pleading for failure to state a claim, a court must determine whether the complaint “contain[s] sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)). A court should construe the complaint in the light most favorable to the plaintiff and accept all well-pleaded material allegations in the complaint as true. Iqbal, 556 U.S. at 679; Erickson v. Pardus, 551 U.S. 89, 93-94 (2007); Twombly, 550 U.S. at 555-56. Despite this liberal pleading standard, the “tenet that a court must accept as true all of the allegations contained in a complaint is inapplicable to legal conclusions. Threadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not suffice.” Iqbal, 556 U.S. at 678; see also Twombly, 550 U.S. at 555, 557 (“labels and conclusions” or a “formulaic recitation of the elements of a cause of action will not do,” nor will “naked assertion[s]” devoid of “further factual enhancements”); Papasan v. Allain, 478 U.S. 265, 286 (1986) (a court is “not bound to accept as true a legal conclusion couched as a factual allegation”). The plaintiff must provide the grounds of his entitlement to relief “rather than a blanket assertion of entitlement to relief.” Twombly, 550 U.S. at 556 n.3. Thus, “a court considering a motion to dismiss can choose to begin by identifying pleadings that, because they are no more than conclusions, are not entitled to the assumption of truth.” Iqbal, 556 U.S. at 679. When the complaint does contain well-pleaded factual allegations, “a court should assume their veracity and then determine whether they plausibly give rise to an entitlement to relief.” Iqbal,

1 The complaint also asserted a claim for declaratory judgment relating to the Sherwin-Williams lien. In this claim, CGFC sought a determination as to which party (or parties) – as among CGFC, Iowa Concrete and Heartland – was obligated to pay Sherwin-Williams, and in what amount(s).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Papasan v. Allain
478 U.S. 265 (Supreme Court, 1986)
Erickson v. Pardus
551 U.S. 89 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Freeman Industries, LLC v. Eastman Chemical Co.
172 S.W.3d 512 (Tennessee Supreme Court, 2005)
Owner-Operator Independent Drivers Ass'n v. Concord EFS, Inc.
59 S.W.3d 63 (Tennessee Supreme Court, 2001)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
Dawson Wise v. Zwicker & Associates PC
780 F.3d 710 (Sixth Circuit, 2015)
Cuspide Properties, Ltd. v. Earl Mechanical Servs.
2015 Ohio 5019 (Ohio Court of Appeals, 2015)
Kelly v. Medical Life Insurance
509 N.E.2d 411 (Ohio Supreme Court, 1987)
Hill v. Sonitrol of Southwestern Ohio, Inc.
521 N.E.2d 780 (Ohio Supreme Court, 1988)
Ohayon v. Safeco Insurance
747 N.E.2d 206 (Ohio Supreme Court, 2001)
Corporex Development & Construction Management, Inc. v. Shook, Inc.
106 Ohio St. 3d 412 (Ohio Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Columbus Garage Floor Coating, Inc. v. Iowa Concrete, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbus-garage-floor-coating-inc-v-iowa-concrete-llc-ohsd-2022.