Zara Constr., Inc. v. Belcastro

2022 Ohio 788, 186 N.E.3d 286
Ohio Court of Appeals·Decided March 16, 2022·No. 2021 CA 0039·Published·Cited by 5 cases

Opinion

COURT OF APPEALS

RICHLAND COUNTY, OHIO

FIFTH APPELLATE DISTRICT

ZARA CONSTRUCTION, INC., : JUDGES:

: Hon. W. Scott Gwin, P.J.

Plaintiff - Appellant : Hon. Patricia A. Delaney, J.

: Hon. Craig R. Baldwin, J.

-vs- :

:

SCOTT BELCASTRO, et al., : Case No. 2021 CA 0039 :

Defendants - Appellees : OPINION

CHARACTER OF PROCEEDING: Appeal from the Richland County Court of Common Pleas, Case No.

2019 CV 0537 R

JUDGMENT: Reversed and Remanded

DATE OF JUDGMENT: March 16, 2022

APPEARANCES: For Plaintiff-Appellant For Defendants-Appellees

THOMAS L. ROSENDBERG J. THOMAS NOCAR Roetzel & Andress LPA JAMES A. KING 41 S. High Street, 21st Floore Porter, Wright, Morris & Arthur LLP Columbus, Ohio 43215 41 S. High Street, 29th Floor Columbus, Ohio 43215

BRIAN D. BREMER Roetzel & Andress LPA 222 S. Main Street, Ste. 400 Akron, Ohio 44308

Baldwin, J.

{¶1} Zara Construction, Inc. is appealing the Richland County Court of Common Pleas decision granting appellees’ motion for directed verdict regarding Zara’s complaint to foreclose a mechanic’s lien and its claim for relief in quantum meruit or unjust enrichment. Appellees are Scott and Christine Belcastro.

STATEMENT OF FACTS AND THE CASE

{¶2} Zara Construction, Inc. was started by Joseph Zara in 1992 as a general contracting business, primarily focusing on home construction, but also performing some light commercial work. Zara agreed to build a home designed by Scott and Christine Belcastro. The Belcastros provided plans for the home and, after multiple discussions the Belcastros agreed to have Zara complete some of the work. The Belcastros chose to serve as their own general contractor for several steps of the construction to reduce their costs. Parts of the project, including labor and materials for the footers and foundation, interior post and beam features and the spiral stair case, were completed by persons working under the supervision of the Belcastros.

{¶3} Zara drafted the contract and delivered it to the Belcastros for review on or before December 29, 2017. The Belcastros reviewed the contract and requested changes before it was signed on February 15, 2018.

{¶4} Zara hired Stephen Marek to supervise a portion of the Belcastro project Zara was to complete and, at some point, the Belcastros hired Marek to perform work outside the parameters of the Zara Contract.

{¶5} Zara met with the Belcastros on several occasions to discuss the progress of the construction, work completed by the other contractors and change orders. The

meetings became contentious and the relationship between the parties deteriorated. Zara and the Belcastros held each other responsible for delays and increased costs. Zara claimed that the project was delayed as a result of the use of multiple contractors and the Belcastros practice of reconsidering the plans in the midst of construction. The Belcastros delayed the installation of roofing while they considered a solar power system, but decided against that option due to the expense. Belcastros requested installation of floor drains in the garage, but Zara argued that they were not in the original plans and that a change order must be approved prior to their installation. Zara claimed that timbers installed by a third-party were not properly dried and caused delay in installation of drywall.

{¶6} The Belcastros were frustrated by their perception that they were misled about the cost of the home. They also considered Zara unresponsive to requests for information regarding change orders. Discussions regarding the direction of the project, arguments regarding what was required by the contract and the need for change orders grew heated during construction. The disagreements grew strident, and, in April 2019 the Belcastros issued a notice of termination.

{¶7} On April 2, 2019 the Belcastros delivered a letter to Zara claiming that Zara had defaulted and that the default must be cured within seven days. Zara did not respond and, on April 9, 2019 the Belcastros sent notice that the contract was terminated. Zara did no further work on the Belcastro home and the Belcastros completed the home with the help of other contractors.

{¶8} On May 6, 2019 Zara recorded an Affidavit of Lien stating that it had provided labor and materials for construction of the Belcastros’ home, that the last date

of work was April 9, 2019 and that Zara was owed $147,405.58 over and above all credits and set-offs. (Plaintiff’s Exhibit 4.) On June 20, 2019, Zara filed a second lien, identical to the first except for the following: “Zara Construction is currently owed the sum of $114,632.30 over and above all credits and set-offs for the work or materials described in Paragraph 2 above. This Amended Affidavit of Lien replaces the Affidavit of Lien filed with the County Recorder on May 6, 2019 for a different amount.” (Plaintiff’s Exhibit 5.)

{¶9} On July 23, 2019 Zara filed a complaint to foreclose the mechanic’s lien and included counts seeking compensation based upon theories of quantum meruit and unjust enrichment. On August 28, 2019, the Belcastros filed an answer and counterclaim containing allegations of breach of contract, slander of title, breach of bailment/conversion, unjust enrichment, negligence and a request for declaratory judgment. Zara filed its Reply to the counterclaim on September 12, 2019 and the matter was set for a jury trial.

{¶10} The Belcastros moved for summary judgment on their claim that they were entitled to a declaratory judgment that Zara had violated the Home Construction Service Suppliers Act. (Counterclaim, Count II). The trial court granted that motion, found that Zara had committed several violations of the Act and ordered that damages would be determined at a hearing. Zara also moved for summary judgment regarding the Belcastros’ claims for negligence and unjust enrichment, but that motion was denied.

{¶11} The parties presented volumes of testimony and exhibits during a seven day jury trial, but Zara’s appeal involves a limited amount of the evidence that addressed the validity of the mechanic’s lien and whether the facts support a claim for quantum meruit or unjust enrichment.

MECHANIC’S LIEN

{¶12} The dispute regarding the mechanic’s lien arose from Zara’s admission that the amount listed in the lien filed on May 6, 2019 was incorrect. Joseph Zara confirmed that “we put numbers from different things into that lien that shouldn't have been on there by accident.” (Trial Transcript, p. 72, lines 19-20). He confirmed that the correct amount of the lien was described in Exhibit 5, the amended lien, filed on June 20, 2019.

{¶13} The parties also disputed the date of the last date of work toward completion of the Belcastro home. Joseph Zara’s affidavit listed the last day of work as April 9, 2019, though during the trial he could not recall “what is the last day we were on the job” in response to questions about working on the site. (Trial Transcript, p. 311, line 15). Zara did confirm that he was still working toward fulfilling the contract and finishing the home until termination on April 9, 2019. (Trial Transcript, p. 348, line 16 to p. 349, line 2). Stephen Marek, the project manager, confirmed that Zara was still soliciting contractor bids in furtherance of the project until April 9, 2019. (Trial Transcript, p. 479, lines 2-8).

QUANTUM MERUIT/UNJUST ENRICHMENT

{¶14} Zara claimed that it completed work prior to termination but had not received payment for those efforts. The Belcastros contended that no payment was due.

{¶15} Payment for work completed was divided into four stages by the contract:

Free access — add to your briefcase to read the full text and ask questions with AI

Zara Constr., Inc. v. Belcastro, 2022 Ohio 788, 186 N.E.3d 286 (Ohio Ct. App. 2022).

2022 Ohio 788 (Zara Constr., Inc. v. Belcastro) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

GC3, L.L.C. v. Empowerment Temple, Inc.
2024 Ohio 5509 (Ohio Court of Appeals, 2024)
Fischer v. Monarch Van Lines, L.L.C.
2024 Ohio 2812 (Ohio Court of Appeals, 2024)
Kent State Univ. v. Manley
2023 Ohio 4650 (Ohio Court of Appeals, 2023)
Fox Consulting Group, Inc. v. Mailing Servs. of Pittsburgh, Inc.
2022 Ohio 1215 (Ohio Court of Appeals, 2022)