Thompson Thrift Constr. v. Lynn

2017 Ohio 1530, 89 N.E.3d 249
CourtOhio Court of Appeals
DecidedApril 21, 2017
Docket16 CAE 10 0044
StatusPublished
Cited by19 cases

This text of 2017 Ohio 1530 (Thompson Thrift Constr. v. Lynn) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson Thrift Constr. v. Lynn, 2017 Ohio 1530, 89 N.E.3d 249 (Ohio Ct. App. 2017).

Opinions

Gwin, J.,

{¶ 1} Appellants appeal the September 12, 2016 judgment entry of the Delaware County Court of Common Pleas.

Facts & Procedural History

{¶ 2} The dispute in this case concerns a construction project at 801 Polaris Parkway, a 300,000 square foot extended-stay hotel. Appellant Thompson Thrift Construction, Inc. ("Thompson Thrift") was the general contractor on the project. Thompson Thrift entered into a $1,175,000 subcontract with Scott Lynn d/b/a National Framing & Finishing ("Lynn"), to provide all of the framing services for the project. Lynn had a $975,000, plus additional charges for any changes, subcontract with appellee Mark Hill d/b/a Mega Framing ("Hill") to provide labor services for the project.

{¶ 3} Hill employed carpenters that worked on the project from August to December of 2013. With each payment application Hill made, Hill signed a lien waiver. The last effective date of the lien waivers was December 13, 2013. In December of 2013, disputes arose between Thompson Thrift and Lynn. Lynn walked off the job and was terminated by Thompson Thrift. Hill continued working on the project for two additional pay periods through December 23, 2013. Subsequently, approximately fifteen to twenty carpenters previously employed by Hill continued work on the project through a temporary agency and then later through another individual who was working on the Polaris project.

{¶ 4} On January 6, 2014, Hill recorded a mechanic's lien against the property for $148,058.

{¶ 5} On February 3, 2014, Thompson Thrift filed a complaint against Lynn for breach of contract, unjust enrichment, conversion, and fraud.

{¶ 6} On March 11, 2014, Thompson Thrift filed a complaint against Hill/Mega. The complaint contained the application of Thompson Thrift for approval of a bond discharging the mechanic's lien of Hill and Mega Framing pursuant to R.C. 1311.11(C). Thompson Thrift sought approval from the trial court of a bond to discharge the mechanic's lien of Hill/Mega, the lien claimant, arising out of a contract between Thompson Thrift and Lynn, who subcontracted with Hill/Mega. On March 26, 2014, the trial court granted Thompson Thrift's application for discharge of mechanic's lien and substituted the mechanic's lien discharge bond issued by appellant Fidelity & Deposit Company of Maryland ("Fidelity") in the amount of $222,087.

{¶ 7} Hill filed a complaint against Lynn, Thompson Thrift, and Fidelity on June 30, 2014, including the following: an action on the surety bond against Fidelity, breach of contract claims against Lynn and Thompson Thrift, unjust enrichment claims against Lynn and Thompson Thrift, an intentional interference with contractual relations and business claim against Thompson Thrift, and a conversion claim against Lynn. Both Thompson Thrift and Fidelity filed answers to the complaint. On August 22, 2014, Hill filed a motion for default against Lynn, which the trial court granted on October 21, 2014.

{¶ 8} The above-cases were consolidated by the trial court. On November 5, 2015, Thompson Thrift and Hill filed an agreed entry. The agreed entry stated the cases would be heard by an arbitration panel consisting of three arbitrators, one selected by Thompson Thrift, one selected by Hill, and one selected by the trial court. The parties agreed they would have the right to appeal the findings of the arbitration panel as if the arbitration panel's decision were a magistrate's decision issued pursuant to Civil Rule 53. Lynn did not participate in the arbitration.

{¶ 9} The arbitration panel conducted a hearing beginning on February 15, 2016. Hill testified he has been in the framing business for thirty to thirty-five years and does high-end, specialized framing. Hill stated commercial framing requires unique skills because it is a "dangerous business" and the Polaris project was difficult because of inverted hangers and specialty items. Hill has a core group of carpenters and he recruited them over a period of time. Hill started the project in August of 2013 with fifteen laborers and ramped up the amount of laborers as needed.

{¶ 10} Hill testified the contract price he negotiated with Lynn was $975,000, plus retainage and additional charges for any changes made. Hill sent Lynn weekly invoices. Hill stated retainage is money taken out of each invoice that Lynn deemed necessary to get to the end of the job. Hill testified he was going to get paid the retainage amount at the end of the contract pursuant to his agreement with Lynn. Further, that the change orders amount of $80,514 was not billed to Lynn in the weekly invoices because it was agreed it would be calculated at the end of the job.

{¶ 11} Hill billed Lynn the total amount of $492,750, excluding retainage and change orders, and was paid $415,440. Lynn's last payment to Hill was on December 13, 2013. Hill billed additional amounts to Thompson Thrift after Lynn walked off the job in the amount of $37,800 on December 20th and $11,000 on December 23rd.

{¶ 12} Hill testified that on December 16, 2013, he attended a meeting with Lynn and Thompson Thrift executives in a trailer at the Polaris project site. Hill stated eight staff members of Thompson Thrift were present at the meeting scheduled for Lynn to rectify a forty-eight hour notice of correction. At the meeting, Lynn told Hill to get off the project. Hill testified he did not take his men off the project because he was summoned back into the trailer by one of Thompson Thrift's people. Hill stated the Thompson Thrift staff members reassured him "we were going to work through this, and, yes, I would continue to get paid." Hill testified Thompson Thrift wanted him to complete the job and continue the motion of the project, so he and his men continued to work on the Polaris project. Lynn did not return to the project and did not communicate with Hill. Hill testified no one told him to stop working on the project after Lynn did not correct the items Thompson Thrift told him to correct.

{¶ 13} Hill worked during the week that ended on December 20th and sent the invoice for this period of time to both Lynn and Thompson Thrift. Exhibit C, the invoice for that week, lists the "outstanding unpaid invoices from 12/20/13" as $37,800. Hill testified he calculated the amount outstanding on this invoice by man hours and square footage of completion of the building. Further, that the building was approximately 55% completed at that point in time. Neither Lynn nor Thompson Thrift paid this invoice. Hill testified he asked Thompson Thrift to pay the invoice and, "they reassured me, keep my men building this project, I would get paid." Hill was surprised he was not paid by Thompson Thrift, but since Thompson Thrift said they would work it out, he continued working.

{¶ 14} Hill stated he worked until December 23, 2013 and could not go any further because he did not get paid. Hill told Lynn, Thompson Thrift, and all of his carpenters and laborers that he could not continue on the project without being paid. Hill invoiced Lynn and Thompson Thrift for December 20 through December 23rd (Exhibit E) for $11,000, the amount due since the last invoice. The invoice also stated the amount of extra work not in the contract was $80,514.

{¶ 15} Hill testified that Thompson Thrift told him they would talk about it after Christmas. Hill tried to negotiate with Thompson Thrift a successful conclusion of the project by completing the job with the money left in the draw.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Assn. Local 168, Apprentice Educational Fund v. Robinson
2025 Ohio 2421 (Ohio Court of Appeals, 2025)
Orion Mgt., Inc. v. Kaeka
2025 Ohio 1047 (Ohio Court of Appeals, 2025)
KN Excavation, L.L.C. v. Rockmill Brewey, L.L.C.
2022 Ohio 3414 (Ohio Court of Appeals, 2022)
Zara Constr., Inc. v. Belcastro
2022 Ohio 788 (Ohio Court of Appeals, 2022)
SMS Fin. XXVI, L.L.C. v. Waxman Chabad Ctr.
2021 Ohio 4174 (Ohio Court of Appeals, 2021)
Lathrop v. Wood Cty. Dog Warden
2021 Ohio 2556 (Ohio Court of Appeals, 2021)
Total Quality Logistics, L.L.C. v. Alliance Shippers, Inc.
2021 Ohio 781 (Ohio Court of Appeals, 2021)
A.A. v. F.A.
2018 Ohio 3376 (Ohio Court of Appeals, 2018)
Phoenix Lighting Group, LLC v. Genlyte Thomas Group, LLC
2018 Ohio 2393 (Ohio Court of Appeals, 2018)
Karras v. Karras
2018 Ohio 515 (Ohio Court of Appeals, 2018)
McGarry & Sons, Inc. v. Constr. Resources One, L.L.C.
2018 Ohio 528 (Ohio Court of Appeals, 2018)
Republic Steel v. Protrade Steel Co., Ltd.
2018 Ohio 469 (Ohio Court of Appeals, 2018)
Lambert's Pop A Top, L.L.C.. v. Mills
2017 Ohio 8073 (Ohio Court of Appeals, 2017)
M.R. Durant Elec., L.L.C. v. Awesome87, L.L.C.
2017 Ohio 4331 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 1530, 89 N.E.3d 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-thrift-constr-v-lynn-ohioctapp-2017.